Free Excel templates

A free data center financial model: three business models, one campus

A 180 MW campus underwritten as turnkey, powered shell or powered land, a monthly construction cash flow, levered returns, and what a rent miss, a delay and a correlated downside each cost.

The same 180 MW site can be three different businesses. Built turnkey at $11 million a megawatt it yields 10.9% on cost; as a powered shell at $5 million, 10.2%; sold as powered land it is a trade, not a building. This model underwrites all three and then runs the monthly cash flow: a base levered return of 22.6%, and 18.1% if energization slips twelve months.

Download the template

One Excel file, no macros, nothing locked. No account, no email address.

The_Underwrite_Computed.xlsx51 KB

The three business models

TurnkeyPowered shellPowered land
Capital cost per MW$11m$5m
Rent, $ per kW-month10545
Yield on cost10.9%10.2%
Value created$794m$327m$33.4m

What goes wrong, in basis points

ScenarioLevered returnAgainst base
Base (3% rent escalator)22.6%
Rent 8% below plan20.2%-239 bp
Energization 12 months late18.1%-450 bp
Correlated: delay, +5% cost, -8% rent, +25bp exit cap14.5%-809 bp

The delay costs more than the rent miss, and it has to be funded: $94.8m of new equity, because lenders do not enlarge a construction loan for delay. And the combined case is not the sum of its parts. Run it, do not add it.

What is in the file

1. The Inputs
Capacity, capital cost, rents, NOI, exit caps, loan to cost and hold. The inputs the book does not state are marked ADDED, with the reason.
2. The Three Models
Turnkey, powered shell and powered land reconciled to the figures the chapter prints.
3. The Cash Flows
Monthly, five scenarios side by side, each driven by its own parameter block.
4. Scenarios
Levered returns and capital calls side by side, in basis points.
5. The Escalator
What a point of rent escalation is worth over a fifteen-year lease.
6. Powered Land
The hit rate at which buying and entitling land breaks even, in one cell.
7. Checks
Thirty-one controls, all passing as shipped.

Questions people ask about it

Turnkey or powered shell?

Turnkey earns the higher yield on cost and the higher rent, and carries the fit-out and the tenant risk. The model shows both on the same site so the choice is a number, not a view.

Where does the construction interest rate come from?

It is derived, not invented: the chapter's own figure for the interest cost of a twelve-month slip, on its own drawn balance.

Can I change a single scenario?

Yes. Each scenario column on the cash flow sheet has its own parameter block.

Is it free?

Yes, no sign-up and nothing locked.

The rest of the files

This template is one of the companion files for The Data Center Development Handbook: the full set adds a blank model set, working documents, forty self-marking questions and three worked cases. Free, like this one.

Open the companion files →