Articles

Transformer sizing per data hall: an MVA worked case

Inside the building, each hall gets its own transformers and its own redundancy. The arithmetic is short; the trap is adding it up to size the grid connection.

Size the transformers of a data hall from its IT load grossed up for UPS losses and divided by the power factor, then add the redundancy the design promises. For an illustrative 6.0 MW hall with 96% efficient UPS and a 0.95 power factor, the IT side needs 6.58 MVA: three 2.5 MVA transformers per side in a 2N design, 15.0 MVA installed, or four in a block-redundant N+1 design, 10.0 MVA. The hall's cooling adds 2.11 MVA, served by two more units.

Related reading: The Data Center Development Handbook by Julian R. Sterling works its subject on one fully specified case, with free companion workbooks. The figures below are an illustrative case built for this article.Get the DRM-free PDF, $19.99 →or see it on Amazon

From kW of IT to kVA of transformer

A hall is leased in kilowatts of IT load, but the transformers that feed it are rated in kVA and see more than the IT load. The UPS draws its losses on top of what the servers use, and the current the transformer carries depends on apparent power, so the power factor divides the result. The same conversion at site level is in how many MVA of grid capacity a 100 MW data center needs; this article applies it one hall at a time, inside the building.

UPS input = IT load / UPS efficiency

Transformer MVA = UPS input / power factor

Units per side = MVA needed / unit rating, rounded up

The case and its assumptions

Illustrative hall. Efficiencies, power factors and ratings are design assumptions, not equipment specifications.
InputValue
Critical IT load per hall6.0 MW
UPS efficiency at design load96%
Power factor seen by the IT transformers0.95
Cooling and auxiliary load per hall at peak, power factor1.9 MW, 0.90
Medium-voltage to low-voltage transformer rating2.5 MVA
Halls in the building4

The calculation for one hall

Step 1, UPS input = 6.0 / 0.96 = 6.25 MW

Step 2, IT transformer capacity = 6.25 / 0.95 = 6.58 MVA, or 1.10 kVA per kW of IT

Step 3, units of 2.5 MVA to carry it = 6.58 / 2.5 = 2.63, rounded up to 3

Step 4, cooling = 1.9 / 0.90 = 2.11 MVA, one unit, plus one spare in N+1

Three redundancy layouts for the IT side

Transformers for the 6.0 MW hall's IT load. Loading per unit in MVA, and as a share of the 2.5 MVA rating. In 2N the worst single failure takes out a whole side.
LayoutUnitsInstalled MVALoad per unit, normalWorst single failure
2N, A and B sides615.01.10 (44%)2.19 (88%)
Block redundant, N+1 with a catcher410.02.19 (88%)2.19 (88%)
Distributed redundant, four to make three410.01.64 (66%)2.19 (88%)

All three carry the hall through the worst single failure (in 2N, the loss of a whole side), and in every case the surviving units run at 88% of rating. They differ in what is bought and how it runs day to day. In 2N each side carries half the load, so every unit runs at only 44%, and 15.0 MVA is installed for 6.58 needed. Block redundancy runs three units near their limit and keeps a fourth as a catcher. The distributed design spreads the load across all four, so each runs at 66% in normal operation. The cost side of the choice is in what 2N redundancy costs per MW compared with N+1.

Per hall, all in

2N IT side 15.0 MVA + cooling 5.0 MVA = 20.0 MVA installed, 3.33 kVA per kW of IT

Block N+1 IT side 10.0 MVA + cooling 5.0 MVA = 15.0 MVA installed, 2.50 kVA per kW of IT

Why the hall transformers do not size the substation

The building has 4 halls, 24 MW of IT. Adding up the hall transformers gives 80 MVA installed in 2N, or 60 MVA in block N+1. The grid connection does not need that. It needs the simultaneous peak demand of the building:

Peak demand = 4 × (6.25 + 1.9) = 32.6 MW, an implied peak PUE of 1.36

Grid capacity = 4 × (6.58 + 2.11) = 34.8 MVA, a combined power factor of 0.938

Hall transformers are sized for redundancy inside the building; the substation is sized for firm capacity at the connection, with its own N+1, as in the site-level article. Mixing the two would overstate the grid request 1.7 to 2.3 times. Peak PUE drives both numbers, and how much leasable capacity a higher PUE costs shows the effect on what can be leased.

The free data center financial model takes a campus from power capacity to rent and returns.

What this leaves out

The electrical engineer sets all three. The point for the model is to use the same IT load, UPS efficiency and power factor as the design.

Takeaway

IT MW / UPS efficiency / power factor gives the transformer MVA per hall: 6.58 MVA for 6.0 MW here, 20.0 MVA installed with cooling in 2N and 15.0 MVA in block N+1. Size the substation on the building's simultaneous peak, 34.8 MVA for four halls, not on the sum of the hall transformers.

Questions readers ask

How do you size a transformer for a data hall?

Divide the IT load by the UPS efficiency and by the power factor, then round up to whole units with the redundancy required. A 6.0 MW hall at 96% and 0.95 needs 6.58 MVA, or three 2.5 MVA units per side.

How many transformers does a 2N data hall need?

Enough on each side to carry the whole IT load alone. Here that is three 2.5 MVA units per side, six in total and 15.0 MVA installed for 6.58 MVA needed, plus two units for cooling in N+1.

Can you add up hall transformers to size the substation?

No. The hall transformers include redundancy inside the building. Four halls carry 80 MVA of transformers in 2N but a simultaneous peak of only 34.8 MVA, which is what the grid connection must supply firm.

Go further

This article applies the method to an illustrative case built for it. The Data Center Development Handbook works its own fully specified case chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99

Not on Amazon: 19 paperbacks by Julian R. Sterling on energy, infrastructure and land, printed on demand and shipped worldwide. Browse the bookshop →

Also on this site

Reading guide: infrastructure, data centres and energy → · All 1908 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.