Articles

How many MVA of grid capacity does a 100 MW data centre need?

Tenants lease megawatts, utilities and transformers are rated in MVA, and the gap between them is where site models go wrong.

Size a data centre substation from the critical IT load times the peak PUE, divided by the power factor, then add a spare transformer. For an illustrative 100 MW of IT at a peak PUE of 1.35 and a 0.95 power factor, the site needs 142.1 MVA of firm capacity, about 1.42 MVA per MW of IT. In an N+1 layout of three 75 MVA transformers, that means 225 MVA installed for 150 MVA firm.

Free Excel workbook: A free data center financial model: three business models, one campus, the worked case from The Data Center Development Handbook. Live formulas, no macros.Get the free workbook →

Worked in full in The Data Center Development Handbook by Julian R. Sterling, with every figure reproduced in a free workbook.Get the DRM-free PDF, $19.99 →or see it on Amazon

Learn the whole method: Data Center Development & Finance

A course built on one 60 MW campus, from grid tranches and cost per MW to leases, the power recharge, the construction loan, the refinancing and the stress tests, with Excel exercises, a 162-question quiz and the Data Center Development Model, Pro Edition included ($149).

Try module 3 and ten quiz questions, free →

Why MW and MVA are not the same number

A tenant leases kilowatts of IT load. A utility, a transformer and a cable are rated in volt-amperes, because the current they carry, and the heat that limits them, depends on apparent power, not on the real power that does useful work. The two are linked by the power factor: real power (MW) = apparent power (MVA) × power factor. Part of the current a site draws is reactive, here 44.4 MVAr, which does no work in the servers but still loads every transformer on the way in. A development team that writes “120 MW” in the model when the grid offer says “120 MVA” has overstated what it can sell before it has built anything.

The case and its assumptions

Illustrative campus. Ratings and factors are illustrative design assumptions, not equipment specifications.
InputValue
Critical IT load to be leased, MW100
Peak design PUE (hottest hour)1.35
Annualised PUE, for comparison1.25
Blended power factor at the point of connection0.95
Transformer redundancyN+1

The power factor is a blended figure. Modern UPS systems present a power factor close to one to the grid; motors, pumps and chillers less so. The design team will compute it, and the utility may set a minimum it requires at the connection point.

The calculation, step by step

Step 1, real power at peak = IT load × peak PUE = 100 × 1.35 = 135.0 MW

Step 2, apparent power = 135.0 / 0.95 = 142.1 MVA (reactive part = √(142.12 − 135.02) = 44.4 MVAr)

Step 3, transformers in N+1: with three units, any two must carry the full load, so each needs 142.1 / 2 = 71.1 MVA. The next rating offered is 75 MVA.

Installed = 3 × 75 = 225 MVA; firm (one unit out) = 2 × 75 = 150 MVA, a headroom of 7.9 MVA

Excel: =IT_MW*PeakPUE/PF for MVA, and =MVA/(Units-1) for the rating each unit needs

Two shortcuts follow. The ratio is 1.42 kVA of grid capacity per kW of IT on these assumptions, a number worth checking against every grid offer. And using the annualised PUE of 1.25 instead of the peak gives 131.6 MVA, 10.5 MVA short on the one afternoon a year when it matters, the same trap described for capacity in how much leasable IT capacity a higher PUE costs.

The redundancy choice

Three ways to deliver 142.1 MVA of firm capacity.
LayoutRating needed per unitUnit chosenInstalled MVAFirm MVAInstalled / need
N+1, three units71.1752251501.58
N+1, four units47.4502001501.41
Two units, each carrying the full load142.11503001502.11

All three deliver the same 150 MVA of firm capacity. What changes is how much transformer is bought and stands idle: 2.11 MVA installed for every MVA needed with two full-size units, 1.41 with four smaller ones. More units means less spare iron but more bays, switchgear and space in the substation compound, and the economics of that trade-off belong to the electrical engineer. The developer's job is to make sure the model uses firm capacity, never installed.

Running it backwards: what does a grid offer support?

The more common question on the deal side runs the other way. A utility offers 120 MVA. How much IT can be leased?

Real power = 120 × 0.95 = 114.0 MW; leasable IT = 114.0 / 1.35 = 84.4 MW

Read 120 MVA as 120 MW and you get 120 / 1.35 = 88.9 MW: 4.4 MW too much, a 5.3 per cent overstatement

At the book's illustrative turnkey rent of $105 per kW-month, the 4.4 MW that does not exist would have been $5.60 million a year of rent in the model, before anyone capitalised it into a site value.

Leasable IT MW per 100 MVA of firm grid capacity.
Power factorPUE 1.20PUE 1.35PUE 1.50
0.9075.066.760.0
0.9579.270.463.3
0.9982.573.366.0

The grid is the same in every cell; the leasable capacity ranges from 60.0 to 82.5 MW. Peak PUE moves it more than the power factor, but both are worth a line in the model rather than a hard-coded MW figure. The inverse table, MVA needed for 100 MW of IT, runs from 121.2 MVA at the best corner to 166.7 at the worst.

The common mistakes

Power procurement and grid interconnection are at the centre of the book, and the free workbook for the book's 180 MW site builds the campus economics on the same turnkey rent.

The same conversion one hall at a time, with 2N and block-redundant layouts inside the building, is in transformer sizing per data hall.

Takeaway

Grid MVA × power factor / peak PUE is what you can lease; IT MW × peak PUE / power factor is what you must connect. Here 100 MW of IT needs 142.1 MVA of firm capacity, delivered by 225 MVA of transformers in an N+1 layout, and a 120 MVA offer supports 84.4 MW, not 88.9.

Free Excel template: data center financial model.

Questions readers ask

How many MVA does a 100 MW data centre need?

Multiply the IT load by the peak PUE to get the site load, then divide by the power factor: 100 × 1.35 ÷ 0.95 = 142.1 MVA of firm capacity. With N+1 redundancy the installed transformer capacity is higher again.

How do you convert MVA to MW for a data centre?

Multiply MVA by the power factor. A 120 MVA connection at a 0.95 power factor delivers 114.0 MW of real power. Dividing by a peak PUE of 1.35 then gives 84.4 MW of IT load that can be leased. Treating the 120 MVA as 120 MW would overstate leasable capacity by 4.4 MW, or 5.3 per cent.

How many kVA per kW of IT does a data centre need?

Peak PUE divided by power factor. At 1.35 and 0.95 it is 1.42 kVA of firm grid capacity per kW of IT. With a 1.20 peak PUE and a 0.99 power factor it falls to about 1.21, and at 1.50 and 0.90 it rises to about 1.67, so the ratio varies by more than a third across plausible designs.

What does N+1 mean for data centre transformers?

That the site can lose any one transformer and still carry its full load. With three units, two must carry 142.1 MVA, so each needs 71.1 MVA and a 75 MVA rating is chosen: 225 MVA installed but 150 MVA firm. Only the firm figure should be used to size what can be leased.

Read the whole case

This article is one calculation from The Data Center Development Handbook. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99

Not on Amazon: 19 paperbacks by Julian R. Sterling on energy, infrastructure and land, printed on demand and shipped worldwide. Browse the bookshop →

Also on this site

Reading guide: infrastructure, data centres and energy → · All 3450 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.