Book · Julian R. Sterling

The Interconnection Queue Handbook

Queue Positions, Cluster Studies, Network Upgrade Costs, Readiness Deposits, Withdrawal Penalties, and the Grid Access Math of Renewable Developers

About the book

Cover of The Interconnection Queue Handbook

With more than 2,061 GW waiting in U.S. interconnection queues and only 13 percent of historical projects reaching commercial operation, grid access has become the binding project-finance constraint of renewable energy development. This handbook gives developers, transmission engineers, project finance VPs, and energy counsel the complete quantitative playbook for FERC Order No. 2023 and Order No. 2023-A cluster studies, Proportional Impact (DFAX) cost allocation, restudy cascades, Commercial Readiness Deposits, surety bonds, withdrawal penalties, and 25-year IRR kill-switch governance.

Every calculation is worked on one fictional 150 MW AC solar-plus-storage project (Alderbrook Grid Partners, LLC / Alderbrook Solar + Storage I in Cluster C-2026): mapping the 645-day study clock (48 months to COD), absorbing a +$2,800,000 neighbor-withdrawal restudy shock, cutting $2,700,000 via enumerated Alternative Transmission Technologies, saving $234,281 with Order No. 2023-A surety bonds, setting an exact $20,925,505 ($139.50/kW) kill-switch ceiling at a 9.00 percent hurdle, and proving why a one-year queue delay (-59 bps IRR) is four times deadlier than a $2.7 million upgrade shock (-14 bps).

Paperback, $32.99, shipping included to the United States, the United Kingdom, Europe, and Australia.

PDF edition, $19.99, DRM-free, delivered at once by email.

Paperback, $32.99 PDF edition, $19.99

What is inside

Free companion files

Unlocked Excel workbooks, blue inputs, black formulas, zero macros, and a Controls tab that reads 0.

Download all files (ZIP)39 KB

Start with 00_START_HERE.md.

Want the standalone template first? Open the free Interconnection Cost and Timeline Model (Excel) page.

Worked articles from the book

Questions practitioners ask

Who is this handbook written for?

Renewable energy and battery storage developers, transmission and interconnection engineers, project finance VPs, infrastructure lenders, tax equity structurers, and energy regulatory counsel.

Which regulatory and tax frameworks are covered?

FERC Order No. 2003, Order No. 2023, Order No. 2023-A (18 CFR 35.28), pro forma LGIP and LGIA, regional RTO/ISO tariffs (PJM, MISO, CAISO, SPP, NYISO, ISO-NE), non-FERC ERCOT procedures, IRC Section 48E QIP (5 MW AC threshold), Section 6418 transferability, and IRS Notice 2016-36 CIAC safe harbors, all as read in November 2026.

Are the Excel models included free?

Yes. Both Interconnection_Queue_Case_Workbook.xlsx and the standalone Interconnection_Cost_and_Timeline_Model.xlsx are free on this page, unlocked, and macro-free.