From legacy serial queues to first-ready, first-served clusters: 90% site control, escalating CRDs, withdrawal penalties, and Order 2023-A surety bond savings.
Active U.S. interconnection queues hold over 2,061 GW of generation and storage while historical completion rates sit near 13 percent. FERC Order No. 2023 and Order No. 2023-A replaced legacy serial queues with a capital-intensive first-ready, first-served cluster process requiring 90 percent site control, escalating Commercial Readiness Deposits, and steep withdrawal penalties.
Worked in full in The Interconnection Queue Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
For two decades under FERC Order No. 2003, U.S. transmission providers studied new power plants one at a time on a "first-come, first-served" serial basis. Cheap, refundable deposits invited developers to file multiple speculative queue positions, while late withdrawals triggered endless cascading restudies. According to Lawrence Berkeley National Laboratory's Queued Up reports (2025 and 2026 editions), active U.S. queue capacity reached roughly 2,061 GW across 8,200 projects at the end of 2025, 75 percent of 2000-2020 requests were withdrawn, and median request-to-COD timelines surpassed 5 years (60+ months).
Under FERC Order No. 2023 and Order No. 2023-A (18 CFR 35.28), FERC dismantled serial studies and mandated a first-ready, first-served annual cluster study model resting on five binding rules:
In The Interconnection Queue Handbook, every regulatory rule, deposit tier, and 25-year return calculation is worked on one fictional 150 MW AC hybrid project (150 MW solar + 50 MW / 200 MWh co-located BESS behind a single 230 kV POI) entering Cluster C-2026:
| Queue Milestone | FERC Order No. 2023 Rule | Alderbrook (150 MW AC) |
|---|---|---|
| Day-0 Cluster Entry | $5k fee + $150k study + 2x CRD-1 | $455,000 (90% = 1,080 acres) |
| Restudy Entry (CRD-2) | 5% of Phase 1 NU ($13,500,000) | $675,000 cumulative (+$375,000) |
| Facilities Entry (CRD-3) | 10% of Mitigated NU ($13,600,000) | $1,360,000 cumulative (+$685,000) |
| LGIA Execution Security | 20% of Final NU ($13,600,000) | $2,720,000 cumulative (+$1,360,000) |
Across the 24-month study-to-LGIA cycle ($1,338,750 average posted collateral), funding security with 100 percent cash at 10.0 percent WACC costs $267,750 in opportunity cost. Switching to an Order No. 2023-A surety bond at 1.25 percent cuts 24-month carry cost to $33,469, saving $234,281 per project while preserving bank revolver lines.
Before filing, developers must align service type with revenue underwriting: Energy Resource Interconnection Service (ERIS) tests basic local reliability, whereas Network Resource Interconnection Service (NRIS) tests full peak deliverability required to unlock battery capacity payments ($3,600,000/yr at Alderbrook). Order No. 2023 also allows co-located solar and storage to share one POI request under realistic storage operating assumptions and opens Surplus Interconnection Service (SIS) as soon as a host LGIA is executed.
Note that while PJM, MISO, CAISO, SPP, NYISO, and ISO-NE all implement Order No. 2023 via Independent Entity Variations, ERCOT is not FERC-jurisdictional and retains its faster "connect-and-manage" FIS model, trading upfront Network Upgrades for operational curtailment and nodal basis risk.
Next, learn how shared upgrades are split in network upgrade cost allocation (DFAX vs. per capita), model schedule risk in interconnection study timelines, delay penalties, and IRR impact, and download the free Interconnection Cost and Timeline Model (Excel).
Serial queues studied projects one by one by filing timestamp, causing first-mover cost cliffs and endless restudies. FERC Order No. 2023 cluster queues group annual applicants together, allocate shared upgrades proportionally, and enforce strict land, deposit, and withdrawal penalty gates.
Yes. In Order No. 2023-A, FERC explicitly modified the pro forma LGIP to allow surety bonds alongside cash and irrevocable letters of credit for study deposits and Commercial Readiness Deposits.
Developers can exit penalty-free during the 60-day Customer Engagement Window (forfeiting only the $5,000 fee), when withdrawal causes no material impact on equal- or lower-queued requests, or when Network Upgrade cost estimates exceed pro forma LGIP Section 3.7.1.1 safe-harbor thresholds (>25 percent in a Cluster Restudy relative to the prior Cluster Study/Restudy, or >100 percent in the Facilities Study).
No. Because ERCOT operates intrastate within Texas without synchronous interstate AC ties, it is not FERC-jurisdictional and operates under PUCT/ERCOT Full Interconnection Study rules.
This guide is drawn from The Interconnection Queue Handbook, following Alderbrook Solar + Storage I (150 MW AC) through Cluster C-2026 from heatmap screening to LGIA execution.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Interconnection Cost and Timeline Model (Excel).
Illustrative figures computed by the book model; Alderbrook Grid Partners, LLC is fictional. Education only, not legal, engineering, tax, or investment advice.