An unlocked Excel calculator for one project: enter the BAC and the monthly planned value, earned value and actual cost, and read the variances, the indices, four estimates at completion, TCPI and earned schedule.
Earned value needs three monthly series and a dozen formulas that are easy to get subtly wrong: an EAC recomputed from a rounded index, a percent spent taken against the EAC, an earned schedule interpolated across the wrong month. This calculator applies them all from the same inputs, month by month, with a Checks tab that must read zero.
One unlocked Excel workbook, zero macros. Free: enter your email address and the download opens at once, along with the other free models.
Earned_Value_Calculator.xlsx (17 KB)
You join the reader list: one email when a new free model or book comes out. Unsubscribe in one click. Already subscribed? Enter the same address. How your address is used.
This calculator is the reusable core of the 22-tab workbook in The Earned Value Management Handbook, which takes one fictional defense contractor through a 24-month development contract: the baseline and its review, eleven control accounts, earned value techniques, the monthly indices, earned schedule, seven estimates at completion, variance analysis reports, an over target baseline decision and the final cost.
Paperback, $32.99 PDF edition, $19.99 Book page and full workbook
The file opens with an illustrative Example Project: BAC $2,400,000.00, management reserve $120,000.00, 10 planned months, status at Month 6. Cumulative planned value is $1,550,000.00, earned value $1,420,000.00 and actual cost $1,563,000.00: CV -$143,000.00 (-10.1 percent) and SV -$130,000.00 (-8.4 percent). The cumulative CPI is 0.91 and the SPI 0.92; in Month 6 alone the project planned $310,000.00, earned $285,000.00 and spent $318,000.00, a current CPI of 0.90. It is 59.2 percent complete and 65.1 percent spent.
| EAC method | EAC | VAC |
|---|---|---|
| Remaining work at budget | $2,543,000.00 | -$143,000.00 |
| Cumulative CPI | $2,641,690.14 | -$241,690.14 |
| Weighted 0.8 CPI + 0.2 SPI | $2,639,883.76 | -$239,883.76 |
| Composite CPI x SPI | $2,740,443.46 | -$340,443.46 |
TCPI to the BAC is 1.17: the remaining $980,000.00 of work would have to be done with $837,000.00, against a CPI to date of 0.91. Every one of the four EACs exceeds BAC plus reserve, $2,520,000.00; the CPI EAC by $121,690.14, so the flag is raised.
Earned schedule: cumulative planned value was $1,240,000.00 at Month 5 and $1,550,000.00 at Month 6, so the $1,420,000.00 earned is worth ES = 5.58 months. With 6 months elapsed, SV(t) is -0.42 months, SPI(t) 0.93, and IEAC(t) = 10 / SPI(t) = 10.75 months against 10 planned. Replace the blue cells with your own data and keep the formulas.
For the method behind each result, read the earned value formulas for CV, SV, CPI and SPI, the estimate at completion formulas and earned schedule, SPI(t) and IEAC(t).
The calculator handles one project and one baseline; it holds no baseline changes, no management reserve releases and no control account detail. A working aid, not a substitute for your contract's reporting requirements. Education only, not legal, contracting or accounting advice.
From the BAC and monthly planned value, earned value and actual cost, it returns CV, SV, CPI and SPI (cumulative and current), CV and SV percent, percent complete and spent, the EAC at budget, by cumulative CPI, weighted 0.8 CPI plus 0.2 SPI and composite CPI x SPI with the VAC of each, TCPI to the BAC and to the CPI EAC, and earned schedule ES, SV(t), SPI(t) and IEAC(t).
Up to 36 months of planned value, and earned value and actual cost from Month 1 to the status month with no gaps. The status month is the last month with earned value.
Yes. The weight of the CPI in the weighted EAC is an input, prefilled at 0.8 with 0.2 on the SPI. GAO's guide describes several index choices; no single one is best on every project.
It does not produce a bottom-up EAC or a variance explanation: those remain the work of the people who own the work. It handles one project and one baseline, does not track baseline changes or management reserve releases, and does not replace your contract's reporting requirements.