Earned Value Calculator (Excel)

An unlocked Excel calculator for one project: enter the BAC and the monthly planned value, earned value and actual cost, and read the variances, the indices, four estimates at completion, TCPI and earned schedule.

Earned value needs three monthly series and a dozen formulas that are easy to get subtly wrong: an EAC recomputed from a rounded index, a percent spent taken against the EAC, an earned schedule interpolated across the wrong month. This calculator applies them all from the same inputs, month by month, with a Checks tab that must read zero.

Get the Excel calculator

One unlocked Excel workbook, zero macros. Free: enter your email address and the download opens at once, along with the other free models.

Earned_Value_Calculator.xlsx (17 KB)

You join the reader list: one email when a new free model or book comes out. Unsubscribe in one click. Already subscribed? Enter the same address. How your address is used.

The handbook behind this calculator

This calculator is the reusable core of the 22-tab workbook in The Earned Value Management Handbook, which takes one fictional defense contractor through a 24-month development contract: the baseline and its review, eleven control accounts, earned value techniques, the monthly indices, earned schedule, seven estimates at completion, variance analysis reports, an over target baseline decision and the final cost.

Paperback, $32.99 PDF edition, $19.99 Book page and full workbook

What is inside the workbook

Instructions
What the file does, how to fill it, the earned schedule method it uses, what it never does, and the prefilled worked example with its results.
Calculator
Blue inputs: the project name, the BAC, the management reserve (optional), the planned duration, the weight of the CPI in the weighted EAC, then one row per month with PV, EV and AC for up to 36 months. Black formulas: cumulative PV, EV and AC, cumulative and current CPI and SPI, and earned schedule for every month; at the status month, CV, SV, CV and SV percent, percent complete and spent, four EACs with their VAC, TCPI to the BAC and to the CPI EAC, ES, SV(t), SPI(t), IEAC(t) by both formulas, and a flag when an EAC exceeds BAC plus reserve.
Chart_Data
Month, cumulative PV, cumulative EV and cumulative AC, ready to select and plot as the three classic curves; months after the status month show planned value only.
Checks
Tests that hold for any inputs: total planned value equals the BAC, no month with EV but no AC, no gap in the EV entries, cumulative EV not above the BAC, the CPI EAC equal to BAC / CPI, both IEAC(t) formulas equal, the chart table tied to the results, and percent complete over percent spent equal to the CPI. The total counts the exceptions and must read zero.

The prefilled example

The file opens with an illustrative Example Project: BAC $2,400,000.00, management reserve $120,000.00, 10 planned months, status at Month 6. Cumulative planned value is $1,550,000.00, earned value $1,420,000.00 and actual cost $1,563,000.00: CV -$143,000.00 (-10.1 percent) and SV -$130,000.00 (-8.4 percent). The cumulative CPI is 0.91 and the SPI 0.92; in Month 6 alone the project planned $310,000.00, earned $285,000.00 and spent $318,000.00, a current CPI of 0.90. It is 59.2 percent complete and 65.1 percent spent.

EAC methodEACVAC
Remaining work at budget$2,543,000.00-$143,000.00
Cumulative CPI$2,641,690.14-$241,690.14
Weighted 0.8 CPI + 0.2 SPI$2,639,883.76-$239,883.76
Composite CPI x SPI$2,740,443.46-$340,443.46

TCPI to the BAC is 1.17: the remaining $980,000.00 of work would have to be done with $837,000.00, against a CPI to date of 0.91. Every one of the four EACs exceeds BAC plus reserve, $2,520,000.00; the CPI EAC by $121,690.14, so the flag is raised.

Earned schedule: cumulative planned value was $1,240,000.00 at Month 5 and $1,550,000.00 at Month 6, so the $1,420,000.00 earned is worth ES = 5.58 months. With 6 months elapsed, SV(t) is -0.42 months, SPI(t) 0.93, and IEAC(t) = 10 / SPI(t) = 10.75 months against 10 planned. Replace the blue cells with your own data and keep the formulas.

How to use it on a project

  1. Enter the BAC, any management reserve held outside it, and the planned duration in months.
  2. Enter the planned value for every planned month, so that the months add up to the BAC; the Checks tab tests it.
  3. Each month, enter the earned value and the actual cost of the month just closed. The status month moves on by itself.
  4. Read the indices, the four EACs and earned schedule; compare the TCPI with the CPI, and write the explanation and the bottom-up estimate yourself. Keep the Checks tab at zero.

For the method behind each result, read the earned value formulas for CV, SV, CPI and SPI, the estimate at completion formulas and earned schedule, SPI(t) and IEAC(t).

The calculator handles one project and one baseline; it holds no baseline changes, no management reserve releases and no control account detail. A working aid, not a substitute for your contract's reporting requirements. Education only, not legal, contracting or accounting advice.

Questions practitioners ask

What does the calculator compute?

From the BAC and monthly planned value, earned value and actual cost, it returns CV, SV, CPI and SPI (cumulative and current), CV and SV percent, percent complete and spent, the EAC at budget, by cumulative CPI, weighted 0.8 CPI plus 0.2 SPI and composite CPI x SPI with the VAC of each, TCPI to the BAC and to the CPI EAC, and earned schedule ES, SV(t), SPI(t) and IEAC(t).

How many months can I enter?

Up to 36 months of planned value, and earned value and actual cost from Month 1 to the status month with no gaps. The status month is the last month with earned value.

Can I change the weighted EAC?

Yes. The weight of the CPI in the weighted EAC is an input, prefilled at 0.8 with 0.2 on the SPI. GAO's guide describes several index choices; no single one is best on every project.

What does it not do?

It does not produce a bottom-up EAC or a variance explanation: those remain the work of the people who own the work. It handles one project and one baseline, does not track baseline changes or management reserve releases, and does not replace your contract's reporting requirements.