Earned Value Formulas: CV, SV, CPI, SPI and TCPI Worked

The core earned value formulas worked on one program at Month 12: CPI 0.89, SPI 0.77, a cost variance of -$6,116,990.40 and a TCPI of 1.11.

Earned value management reduces a program to three numbers: planned value (BCWS), earned value (BCWP) and actual cost (ACWP). Every index is a difference or a ratio of the three: CV = BCWP - ACWP, SV = BCWP - BCWS, CPI = BCWP / ACWP and SPI = BCWP / BCWS. On a fictional defense program at Month 12 they give CPI 0.89 and SPI 0.77, both below DCMA's 0.95 flag.

Worked in full in The Earned Value Management Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

The three inputs

Every earned value metric comes from three time-phased numbers kept at the control account and summed upward. The budgeted cost for work scheduled (BCWS), also called planned value or PV, is the sum of the budgets scheduled to be accomplished in a period or to date, including the level of effort and apportioned effort scheduled. The budgeted cost for work performed (BCWP), or earned value (EV), is the sum of the budgets for completed work packages and the completed portions of open ones, plus the applicable share of level of effort and apportioned effort. The actual cost of work performed (ACWP), or AC, is the cost incurred and recorded in the accounting system for the work performed, adjusted for items such as material estimates and subcontractor billing lags.

The budget at completion (BAC) is the sum of all budget established at a given level: work package, control account or the whole performance measurement baseline. BCWP is measured in budget dollars, not in cost: it is what the completed work was supposed to cost, which is why it can be compared with both the plan and the spend.

The formula sheet

MeasureFormulaFavorable when
Cost variance (CV)BCWP - ACWPPositive
Schedule variance (SV)BCWP - BCWSPositive
Cost performance index (CPI)BCWP / ACWPAbove 1.0
Schedule performance index (SPI)BCWP / BCWSAbove 1.0
CV percent (common convention)CV / BCWPPositive
SV percent (common convention)SV / BCWSPositive
Budgeted cost for work remaining (BCWR)BAC - BCWPNot a performance measure
Percent completeBCWP / BAC x 100Not a performance measure
Percent spentACWP / BAC x 100Below percent complete
Estimate at completion (EAC)ACWP + ETCAt or below BAC
Variance at completion (VAC)BAC - EACPositive
To-complete index to BAC, TCPI(BAC)(BAC - BCWP) / (BAC - ACWP)At or below the CPI
To-complete index to EAC, TCPI(EAC)(BAC - BCWP) / (EAC - ACWP)Close to the CPI

Each is computed for the current period and cumulatively. The DoD glossary adds a caution on the schedule index: "SPI of 1.0 indicates on-plan performance or the effort is complete." The two percentages are a widely used convention rather than a DoD definition. Percent complete divided by percent spent equals the CPI, and DCMA computes percent spent against the BAC, not against the EAC.

A small example first

Take a project with a BAC of $10,000,000 that, at its status date, has cumulative BCWS of $4,000,000, BCWP of $3,600,000 and ACWP of $4,000,000. Then CV = 3,600,000 - 4,000,000 = -$400,000, and SV is also -$400,000. CPI = 3,600,000 / 4,000,000 = 0.90 and SPI = 0.90 as well. CV percent is -11.1 percent and SV percent -10.0 percent. The project is 36 percent complete and 40 percent spent.

The remaining work is $6,400,000 of budget. At the efficiency achieved so far it costs 6,400,000 / 0.90, so EAC = 4,000,000 + 6,400,000 / 0.90 = $11,111,111, which is the same as BAC / CPI. VAC is -$1,111,111. To finish on the original budget, the remaining $6,400,000 of work must be done with the $6,000,000 left: a TCPI of 1.067, against a CPI to date of 0.90.

Worked on a full-size program

Tamsfield Aerosystems, Inc., the fictional contractor followed through The Earned Value Management Handbook, runs the Corriden airborne sensor pod development contract: cost-plus-incentive-fee, eleven control accounts, a 20-month plan. At the end of Month 12 the BAC is $111,280,000.00 and the cumulative data read:

MeasureMonth 12, cumulative
BCWS (planned value)$65,075,000.12
BCWP (earned value)$50,152,166.24
ACWP (actual cost)$56,269,156.64
CV-$6,116,990.40 (-12.2 percent)
SV-$14,922,833.88 (-22.9 percent)
CPI0.89
SPI0.77
BCWR$61,127,833.76
Percent complete / percent spent45.1 percent / 50.6 percent

In plain words, Tamsfield has earned $0.89 of budgeted work for every dollar spent, and has accomplished 77 cents of work for every dollar of work it planned to have done by now. Percent complete divided by percent spent, 45.1 over 50.6, gives back the CPI of 0.891. Both cumulative indices are below the 0.95 level that DCMA's analysts treat as a signal to investigate.

Cumulative versus current period

The current-period indices use only the month's figures. In Month 12 Tamsfield planned $8,474,666.68 of work, earned $4,317,102.34 and spent $5,797,639.13: a current cost variance of -$1,480,536.79, a current CPI of 0.74 and a current SPI of 0.51, against cumulative values of 0.89 and 0.77. One month later the current CPI was 1.17. In Month 1 the cumulative CPI was 0.39: start-up cost came before measurable work.

That noise is why forecasts lean on cumulative indices once a program is under way. GAO reports research showing that once a program is 20 percent complete, the cumulative CPI does not vary much from its value, less than 10 percent, and most often tends to get worse. Tamsfield first passed 20 percent complete in Month 7, at 22.5 percent, with a cumulative CPI of 0.891; it finished at 0.896, a change of 0.6 percent.

Control accounts: where the variances live

Guideline 17 of the 27 guidelines of EIA-748 requires schedule and cost variances at least monthly at the control account and higher levels, and Guideline 18 requires significant variances to be analyzed at least monthly for each control account. The program total is an average; the control accounts show where the problem sits. Six of Tamsfield's eleven accounts at Month 12:

Control accountCVSVCPISPI
CA 1.3 Sensor Head Design-$2,838,938.33-$3,550,822.540.810.78
CA 1.4 Signal Processor (subcontract)-$780,979.21-$3,415,607.840.950.81
CA 1.5 Embedded Software-$885,793.63-$2,161,403.500.900.79
CA 1.6 Pod Structure-$771,929.80-$1,600,000.000.840.71
CA 1.7 Prototype Fabrication and Assembly$0.00-$2,100,000.00n/a0.00
CA 1.8 Test and Evaluation$0.00-$700,000.00n/a0.00

CA 1.7 and CA 1.8 have no actual cost and no earned value yet, so no CPI can be computed and the story is in the schedule variance: the first engineering development model pod, worth $2,100,000.00, was due in Month 12, and the first test event has not started. Under Tamsfield's own system description thresholds, which are case conventions and not DoD values, 8 of the 11 accounts needed a variance analysis report that month.

Level of effort hides problems

Level of effort earns with the passage of time, so its BCWP always equals its BCWS and it never shows a schedule variance. Mixed with discrete work, it dilutes the signal. In Month 6, Tamsfield's systems engineering account combined a discrete requirements work package (BCWS $2,700,000.00, BCWP $1,800,000.00, SPI 0.67, CPI 0.78) with a level of effort package that earned its $1,620,000.00 exactly on schedule. The account as reported showed SPI 0.79 and CPI 0.86: a schedule variance of -20.8 percent instead of -33.3 percent for the real work. Level of effort was 60 percent of that account's budget. The DoD interpretation limits level of effort to activities that have no practicable, measurable output, and expects controls where a control account mixes the two kinds of work.

Why the dollar SPI drifts back to 1.00

At completion BCWP equals BCWS equals BAC, so the SPI ends at 1.00 however late the work was. Tamsfield finished in Month 24 against a 20-month plan, yet its Month 24 SPI is 1.00. For a schedule measure that keeps its meaning to the end, use the time-based indicators explained in earned schedule, SPI(t) and IEAC(t).

TCPI: the efficiency the rest of the work needs

The to-complete performance index divides the work remaining by the money remaining. At Month 12 the remaining budget is $61,127,833.76 and the money left inside the BAC is $55,010,843.36, so TCPI to the BAC is 1.11, 22.0 points above the cumulative CPI of 0.891. GAO's rule of thumb treats a TCPI more than 5 percentage points above the CPI as a sign that the estimate is too optimistic; here it says the BAC is out of reach. Against the program manager's EAC of $124,644,552.90 the TCPI is 0.894, 0.3 points above the CPI: consistent. How the EACs themselves are built and tested is covered in the estimate at completion formulas.

Who has to compute these

Under Revision 1 of DoD Class Deviation 2026-O0011, cost or incentive contracts and subcontracts valued at $50 million or more must use an EVMS that complies with EIA-748 (clause 252.234-7999), and those valued at $100 million or more require an EVMS that the cognizant Federal agency has determined to comply with EIA-748. Below $50 million, EVM on cost or incentive contracts is optional and risk-based; on firm-fixed-price contracts of any value it is discouraged. The indices are the same on a construction project, where the inputs are usually called PV, EV and AC: the construction version of this calculation works them on a building contract.

The Earned Value Management Handbook computes every one of these metrics month by month for all eleven control accounts, with the live workbook behind each figure. The free Earned Value Calculator returns CV, SV, CPI, SPI, percent complete and spent and TCPI from your own monthly PV, EV and AC.

Questions practitioners ask

What is the formula for CPI and SPI?

CPI = BCWP / ACWP, earned value divided by actual cost; SPI = BCWP / BCWS, earned value divided by planned value. Above 1.0 is favorable for both.

Is a negative cost variance bad?

Yes. CV = BCWP - ACWP, so a negative CV means the work performed cost more than its budget. Read it by control account: a large negative CV in one account can hide inside a modest total.

What CPI or SPI should trigger a review?

DCMA's published analysis practice flags a cumulative CPI or SPI below 0.95 for investigation. Variance thresholds for reports are set in the contract data requirements or in the contractor's system description, not by a single DoD number.

Why does SPI return to 1.0 at the end of a late project?

Because at completion all the planned work has been earned, so BCWP equals BCWS. The time-based SPI(t) from earned schedule does not converge that way and keeps showing the delay.

Read the full handbook

This guide is one arc of The Earned Value Management Handbook. The book follows one fictional contractor through a 24-month development contract: the 27 EIA-748 guidelines and the 2026 DoD thresholds, the WBS and control accounts, earned value techniques, the performance measurement baseline, integrated baseline reviews, CV, SV, CPI and SPI, earned schedule, estimates at completion and TCPI, variance analysis reports, the IPMDAR, baseline changes, over target baselines, surveillance and withholding, and lighter EVM for construction.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Earned Value Calculator (Excel).

Also on this site

Illustrative figures computed by the book model; Tamsfield Aerosystems, Inc., the Corriden program, the Pellwood Clinic and every person, budget, cost, count and month are fictional and invented for illustration. Standards, guidance and rules described as read in November 2026 (EIA-748 revision E; DoD EVMS Interpretation Guide, June 24, 2026; DoD integrated program management glossary; Class Deviation 2026-O0011 and its Revision 1 of August 5, 2026, with clause 252.234-7999; IPMDAR data item DI-MGMT-81861, revision C; GAO Cost Estimating and Assessment Guide, GAO-20-195G, March 2020; DCMA-EA PAM 200.1, October 2012; the earned schedule method as published by Lipke). Education only, not legal, contracting or accounting advice.