Five index EACs, a bottom-up EAC and a program manager's EAC worked at Month 12, then scored against the final cost of $125,271,350.33.
An estimate at completion is actual cost to date plus the estimate to complete: EAC = ACWP + ETC. The index formulas replace the ETC with the remaining budget divided by an efficiency factor. On a fictional program at Month 12, five index EACs ran from $124,852,667.80 to $145,259,769.24; the program finished at $125,271,350.33, within 0.3 percent of the cumulative CPI forecast.
Worked in full in The Earned Value Management Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
An estimate at completion is actual cost to date plus an estimate to complete: EAC = ACWP + ETC. The variance at completion is VAC = BAC - EAC, and a negative VAC is an expected overrun. Every index formula is the same equation with the ETC replaced by the remaining budget divided by an efficiency index: EAC = ACWP + (BAC - BCWP) / index. GAO's cost estimating guide lists the choices: cumulative, current or averaged CPI or SPI, the product CPI x SPI, or a weighted mix of the two.
EIA-748 asks for more than a formula. Of its 27 guidelines, Guideline 20 requires estimates at completion to be updated for control accounts and summary level planning packages, with the variance at completion, and Guideline 23 requires program manager estimates at completion compared with the contract budget base. An index EAC is the independent check on those estimates, not a substitute for them.
| Method | Index | Formula |
|---|---|---|
| Remaining work at budget | 1.0 | ACWP + (BAC - BCWP) |
| Cumulative CPI | CPI | ACWP + (BAC - BCWP) / CPI |
| Three-month average CPI | BCWP / ACWP of the last three months | ACWP + (BAC - BCWP) / CPI(3) |
| Weighted | 0.8 CPI + 0.2 SPI | ACWP + (BAC - BCWP) / (0.8 CPI + 0.2 SPI) |
| Composite | CPI x SPI | ACWP + (BAC - BCWP) / (CPI x SPI) |
DCMA uses the cumulative CPI EAC as the usual lower, optimistic bound and the composite as the usual upper bound when both indices are below 1, and says these formulas are most accurate between 15 and 95 percent complete. GAO reports that the cumulative CPI EAC typically forecasts the lowest possible EAC, that the CPI x SPI index produces an even higher one, and that no single factor was superior: the best factor changes with the stage of the program.
Tamsfield Aerosystems, Inc., the fictional contractor in The Earned Value Management Handbook, is 45.1 percent complete at the end of Month 12 on its Corriden contract: BAC $111,280,000.00, BCWP $50,152,166.24, ACWP $56,269,156.64, so the remaining budget is $61,127,833.76. The cumulative CPI is 0.891 and the SPI 0.77. The three-month CPI takes Months 10 to 12 only: $15,061,307.02 earned for $17,488,552.58 spent, 0.86. The weighted index is 0.8 x 0.891 + 0.2 x 0.77 = 0.87, and the composite 0.891 x 0.77 = 0.69.
| Method | Index | EAC | VAC |
|---|---|---|---|
| At budget | 1.00 | $117,396,990.40 | -$6,116,990.40 |
| Cumulative CPI | 0.89 | $124,852,667.80 | -$13,572,667.80 |
| Three-month CPI | 0.86 | $127,248,211.34 | -$15,968,211.34 |
| Weighted | 0.87 | $126,760,420.50 | -$15,480,420.50 |
| Composite | 0.69 | $145,259,769.24 | -$33,979,769.24 |
Each EAC is computed from the unrounded index. Dividing the remaining budget by a rounded 0.89 instead of 0.891 would add $99,448.12 to the CPI EAC, which is why a forecast should never be recomputed from an index read off a report. The cumulative CPI EAC also equals BAC / CPI, a handy check. The range DCMA would quote runs from $124,852,667.80 to $145,259,769.24.
The program finished in Month 24 at $125,271,350.33. Scored against that final cost, the Month 12 estimates missed by:
| Month 12 EAC | Error against the final cost | Error |
|---|---|---|
| At budget | -$7,874,359.93 | -6.3 percent |
| Cumulative CPI | -$418,682.53 | -0.3 percent |
| Three-month CPI | $1,976,861.01 | 1.6 percent |
| Weighted | $1,489,070.17 | 1.2 percent |
| Composite | $19,988,418.91 | 16.0 percent |
| Bottom-up | -$3,026,797.43 | -2.4 percent |
| Program manager | -$626,797.43 | -0.5 percent |
The composite overshot because the schedule slip did not turn into cost at the same rate. Earlier and later snapshots tell a similar story. At Month 6, 18.8 percent complete, the CPI EAC of $116,732,266.01 was 6.8 percent low and the composite of $142,221,096.60 13.5 percent high. At Month 18, 81.5 percent complete, the CPI EAC missed by -0.8 percent and the composite by 2.5 percent.
Tamsfield's cumulative CPI moved only from 0.891 at Month 7 to a final 0.896, in line with GAO's observation that it varies by less than 10 percent once a program is 20 percent complete. One program is not a statistic, though: GAO found no single best formula, and reports that three-month averages predicted better than 6 to 12 months, especially mid-program. It also cites studies of more than 700 defense programs showing limited opportunity to get back on track once a program is more than 15 to 20 percent complete.
Tamsfield's eleven control account managers each re-estimated their remaining work at Month 12. Summed, the comprehensive EAC is $122,244,552.90: an ETC of $65,975,396.26 and a VAC of -$10,964,552.90. The program manager, Celeste Rowan, added a risk adjustment of $2,400,000.00 for test failures and the software integration trend, for a most likely EAC of $124,644,552.90 and a VAC of -$13,364,552.90.
Revision C of the IPMDAR data item asks the contractor for best case, worst case and most likely EACs. Tamsfield reported $122,244,552.90 as best case (the bottom-up figure), $124,644,552.90 as most likely and $145,259,769.24 as worst case, the composite index. Some account estimates proved optimistic: CA 1.7 Prototype Fabrication and Assembly forecast $14,250,000.00 at Month 12 and finished at $15,000,000.00.
TCPI(EAC) = (BAC - BCWP) / (EAC - ACWP) is the efficiency the remaining work needs to land on a given EAC; compare it with the cumulative CPI. At Month 12, TCPI to the BAC is 1.11, 22.0 points above the CPI of 0.891: the BAC cannot be met. TCPI to the program manager's EAC is 0.894, 0.3 points above the CPI, which is consistent. TCPI to the bottom-up EAC is 0.926, 3.5 points above: inside GAO's 5-point rule of thumb and DCMA's 0.10 screen, yet that estimate still proved 2.4 percent low. A screen catches implausible EACs; it does not certify the plausible ones.
A VAC against the BAC is only half the answer. Tamsfield's contract budget base after a modification is $116,800,000.00, with $5,520,000.00 of management reserve left at Month 12. The PM EAC of $124,644,552.90 exceeds the contract budget base by $7,844,552.90 even if every dollar of reserve were consumed, and management reserve is not a source of funding for eliminating performance variances in any case. Under the case contract's incentive terms, the fee at that EAC is $6,990,634.13 against a target fee of $9,344,000.00. The program weighed an over target baseline: 2 of the 4 rules of thumb in the DoD guide were met, and it kept its baseline and managed to the EAC. The final overrun was $13,011,350.33 against the BAC.
The free Earned Value Calculator computes four of these methods (at budget, cumulative CPI, the weighted 0.8 CPI + 0.2 SPI and the composite) with the VAC of each and TCPI, and flags any EAC above BAC plus management reserve. Its prefilled Example Project, a BAC of $2,400,000.00 with $120,000.00 of reserve, reads at Month 6: EAC $2,543,000.00 at budget, $2,641,690.14 by CPI, $2,639,883.76 weighted and $2,740,443.46 composite. The CPI EAC exceeds BAC plus reserve by $121,690.14. The definitions behind the indices are in the earned value formulas for CV, SV, CPI and SPI, and the time-based forecast of the finish date in earned schedule, SPI(t) and IEAC(t).
The Earned Value Management Handbook builds all seven Month 12 estimates, the Month 6 and Month 18 comparisons, the bottom-up roll-up by control account and the TCPI tests, with the live workbook behind every figure.
None is best in every case. GAO found that no single factor was superior and that the best one changes with the stage of the program; its table describes a weighted 50 percent CPI and 50 percent SPI as statistically the most accurate. Compute several and explain the spread.
ETC is the estimated cost of the work remaining; EAC is the actual cost to date plus the ETC. The variance at completion is VAC = BAC - EAC.
As the upper bound of a range: DCMA treats it as typically the higher estimate when both indices are below 1. On the case program it overshot the final cost by 16.0 percent, because the schedule slip did not turn into cost at the same rate.
Revision C of the IPMDAR data item asks for best case, worst case and most likely EACs, and Guideline 23 of EIA-748 calls for program manager estimates at completion compared with the contract budget base.
This guide is one arc of The Earned Value Management Handbook. The book follows one fictional contractor through a 24-month development contract: the 27 EIA-748 guidelines and the 2026 DoD thresholds, the WBS and control accounts, earned value techniques, the performance measurement baseline, integrated baseline reviews, CV, SV, CPI and SPI, earned schedule, estimates at completion and TCPI, variance analysis reports, the IPMDAR, baseline changes, over target baselines, surveillance and withholding, and lighter EVM for construction.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Earned Value Calculator (Excel).
Illustrative figures computed by the book model; Tamsfield Aerosystems, Inc., the Corriden program, the Pellwood Clinic and every person, budget, cost, count and month are fictional and invented for illustration. Standards, guidance and rules described as read in November 2026 (EIA-748 revision E; DoD EVMS Interpretation Guide, June 24, 2026; DoD integrated program management glossary; Class Deviation 2026-O0011 and its Revision 1 of August 5, 2026, with clause 252.234-7999; IPMDAR data item DI-MGMT-81861, revision C; GAO Cost Estimating and Assessment Guide, GAO-20-195G, March 2020; DCMA-EA PAM 200.1, October 2012; the earned schedule method as published by Lipke). Education only, not legal, contracting or accounting advice.