Earned Schedule: How to Calculate SPI(t) and IEAC(t)

Earned schedule turns earned value into months: ES, SV(t), SPI(t), IEAC(t) and TSPI worked on a program that finished four months late.

Earned schedule asks when the work performed should have been done. ES is the point on the planned value curve where cumulative PV equals today's earned value; SPI(t) = ES / AT and IEAC(t) = PD / SPI(t). On a fictional 20-month program at Month 12, ES was 9.81 months, SPI(t) 0.82 and IEAC(t) 24.47 months. The program finished in Month 24.

Worked in full in The Earned Value Management Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Why the dollar SPI is not enough

The classic schedule performance index is SPI = BCWP / BCWS, earned value over planned value, both in dollars. It works early on, but it is built to finish at 1.00: once all the work is done, earned value equals planned value however late the finish. The DoD glossary says it plainly: "SPI of 1.0 indicates on-plan performance or the effort is complete." The schedule variance in dollars shrinks to zero at completion for the same reason.

Tamsfield Aerosystems, Inc., the fictional contractor followed through The Earned Value Management Handbook, shows the effect. Its Corriden program was planned for 20 months and finished at the end of Month 24, four months late. Its dollar SPI rose from 0.77 at Month 12 to 0.91 at Month 20, 0.97 at Month 22 and 1.00 at Month 24: a picture of steady recovery that never happened. The classic formulas are set out in the earned value formulas for CV, SV, CPI and SPI.

The earned schedule formulas

Earned schedule, as published by Lipke, measures schedule performance in units of time instead of dollars:

MeasureFormula
Earned schedule (ES)C + I, with I = (EV - PV(C)) / (PV(C+1) - PV(C))
Actual time (AT)Duration from the start to the status date
Schedule variance in time, SV(t)ES - AT
Schedule performance index in time, SPI(t)ES / AT
Independent estimate of duration, IEAC(t)PD / SPI(t), or AT + (PD - ES) / PF(t)
To-complete schedule performance index, TSPI(PD - ES) / (TD - AT)

C is the number of whole time increments for which cumulative earned value is at least the cumulative planned value, and I interpolates within the next increment only. PD is the planned duration, TD the target duration and PF(t) a time-based performance factor; using SPI(t) as the factor gives the same result as PD / SPI(t). Unlike SV and SPI in dollars, the time-based indicators do not converge to perfect values on a late project.

Step by step at Month 12

At the end of Month 12 Tamsfield's cumulative BCWP is $50,152,166.24. Read along the planned value curve: cumulative BCWS was $43,405,444.54 at Month 9 and $51,742,889.00 at Month 10. The earned value lies between the two, so C = 9.

  1. Interpolate: I = ($50,152,166.24 - $43,405,444.54) / ($51,742,889.00 - $43,405,444.54) = $6,746,721.70 / $8,337,444.46 = 0.81.
  2. Earned schedule: ES = 9 + 0.81 = 9.81 months. Work worth 9.81 months of the plan has been done in 12 months.
  3. Schedule variance in time: SV(t) = 9.81 - 12 = -2.19 months.
  4. SPI(t) = 9.81 / 12 = 0.82.
  5. IEAC(t) = 20 / SPI(t) = 24.47 months, computed on the unrounded index. The other form, AT + (PD - ES) / SPI(t) = 12 + 10.19 / SPI(t), gives the same 24.47 months.
  6. TSPI to the 20-month plan = (20 - 9.81) / (20 - 12) = 1.27.

The same Month 12 data read in dollars give an SPI of 0.77 and an SV of -$14,922,833.88. Earned schedule restates that shortfall as 2.19 months and forecasts a finish near Month 24 or 25 when the plan says 20. The program actually took 24 months. Lipke cites research setting 1.10 as the TSPI threshold for an irrecoverable status; at 1.27, the 20-month date was already gone.

SPI and SPI(t) side by side

MonthSPI (dollars)SPI(t)SV (dollars)SV(t), months
60.790.84-$5,292,606.58-0.96
120.770.82-$14,922,833.88-2.19
160.780.83-$21,155,082.44-2.64
180.850.84-$16,406,284.64-2.82
200.910.83-$10,533,526.24-3.37
220.970.83-$3,816,000.00-3.76
241.000.83$0.00-4.00

From Month 18 the two indicators part ways. The dollar SV is deepest in Month 15, at -$21,529,314.74, then shrinks to zero; SV(t) keeps growing to -4.00 months, exactly how late the program finished. SPI(t) ends at 0.83: 20 months of schedule earned in 24.

Choosing the time increment

Earned schedule can be computed in any increment of the baseline: weeks on a short project, months on a program that reports monthly, as Tamsfield does. The interpolation assumes that planned value accrues evenly inside the increment, so a finer increment gives a finer ES when the baseline is available at that grain. Keep the increment the same as the reporting period, so that AT is a whole number of periods at each status date and SV(t) can be read straight into the monthly report. On a program whose planned value curve is flat for several periods, a small change in earned value can move ES by a whole period: read the curve, not only the index.

How stable is IEAC(t)?

After Month 1, Tamsfield's IEAC(t) stayed between 23.26 months (Month 8) and 25.39 months (Month 3). It read 23.81 months at Month 6, 24.47 at Month 12, 23.71 at Month 18 and 24.06 at Month 20, against an actual 24. A reader of the dollar SPI at Month 20, 0.91, would have seen a program almost back on plan. IEAC(t) is still a forecast from past efficiency: it says nothing about which tasks drive the finish. That is the job of the integrated master schedule.

Pair it with schedule health checks

Earned schedule reads the baseline from the outside. DCMA's published 14-point assessment (2012 pamphlet) reads the schedule itself, and two of its metrics complement SPI(t). The baseline execution index, BEI, is tasks completed divided by tasks with a baseline finish on or before the status date; the critical path length index, CPLI, is critical path length plus total float, divided by critical path length. Both are flagged below 0.95. At Month 12 Tamsfield had completed 431 of the 486 tasks due, a BEI of 0.89, and its critical path of 168 workdays carried -22 workdays of total float, a CPLI of 0.87. Three signals, one message: the 20-month plan was not going to hold.

A construction example

The method works the same way on a commercial project. The Pellwood Clinic, a fictional outpatient building in the book, was planned over 12 months. At the end of Month 7 the owner measured earned value of $9,048,000.00 against cumulative planned value of $7,010,000.00 at Month 5 and $9,240,000.00 at Month 6. So C = 5, I = $2,038,000.00 / $2,230,000.00 = 0.91, ES = 5.91 months and SPI(t) = 5.91 / 7 = 0.84. IEAC(t) is 14.20 months against 12 planned, while the dollar SPI was 0.83.

Run it on your own project

The free Earned Value Calculator computes ES, SV(t), SPI(t) and IEAC(t) month by month from your planned value, earned value and actual cost. Its prefilled Example Project, 10 planned months, has earned $1,420,000.00 by Month 6 against cumulative planned value of $1,240,000.00 at Month 5 and $1,550,000.00 at Month 6: ES 5.58 months, SPI(t) 0.93 and IEAC(t) 10.75 months. The cost side of the same forecast is in the estimate at completion formulas.

Limits

The Earned Value Management Handbook tracks SPI and SPI(t), SV(t), IEAC(t) and TSPI for all 24 months of the case, with the live workbook behind every figure.

Questions practitioners ask

How do you calculate earned schedule?

Find the last whole period C in which cumulative planned value is at or below cumulative earned value, then add the fraction I = (EV - PV(C)) / (PV(C+1) - PV(C)). ES = C + I, in months or weeks of the baseline.

What is a good SPI(t)?

1.0 means on plan; below 1.0 means behind. Read it with SV(t) in time units: an SPI(t) of 0.82 at Month 12 meant 2.19 months behind on a 20-month plan.

Is IEAC(t) better than the dollar SPI for forecasting the end date?

It keeps its meaning to the end of a late project, where the dollar SPI returns to 1.0. It is still a forecast from past efficiency; the integrated master schedule shows which tasks drive the finish.

What TSPI means the plan cannot be recovered?

Lipke cites research setting 1.10 as the threshold for an irrecoverable status. TSPI = (PD - ES) / (TD - AT); at 1.27 on the case program, the 20-month date was out of reach.

Read the full handbook

This guide is one arc of The Earned Value Management Handbook. The book follows one fictional contractor through a 24-month development contract: the 27 EIA-748 guidelines and the 2026 DoD thresholds, the WBS and control accounts, earned value techniques, the performance measurement baseline, integrated baseline reviews, CV, SV, CPI and SPI, earned schedule, estimates at completion and TCPI, variance analysis reports, the IPMDAR, baseline changes, over target baselines, surveillance and withholding, and lighter EVM for construction.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Earned Value Calculator (Excel).

Also on this site

Illustrative figures computed by the book model; Tamsfield Aerosystems, Inc., the Corriden program, the Pellwood Clinic and every person, budget, cost, count and month are fictional and invented for illustration. Standards, guidance and rules described as read in November 2026 (EIA-748 revision E; DoD EVMS Interpretation Guide, June 24, 2026; DoD integrated program management glossary; Class Deviation 2026-O0011 and its Revision 1 of August 5, 2026, with clause 252.234-7999; IPMDAR data item DI-MGMT-81861, revision C; GAO Cost Estimating and Assessment Guide, GAO-20-195G, March 2020; DCMA-EA PAM 200.1, October 2012; the earned schedule method as published by Lipke). Education only, not legal, contracting or accounting advice.