Book · Julian R. Sterling
A Practitioner's Guide for Developers, Lenders and Investors: Electrolyzers, Power Supply, the Levelized Cost of Hydrogen, the 45V Credit, European Subsidies, Offtake Contracts and Project Finance
Electrolytic hydrogen costs more to make than the fossil hydrogen it replaces sells for. What makes a project financeable is not the electrolyzer alone but a stack of contracts and policies around it: a power purchase agreement that sets most of the cost, a tax credit or subsidy with an end date, an offtake contract that sets the price, and debt sized on cash flows that change shape the year the credit stops.
The Green Hydrogen Handbook builds that structure end to end on one fictional plant, Caliche Point Hydrogen, a 100 MW PEM electrolyzer on the Texas Gulf Coast with a capital cost of $165,000,000. It produces 10,011 tonnes in its first year at a levelized cost of $4.94 per kg, earns a 45V credit of $3.185 per kg sold for cash, supports debt of $112,270,912 at a 1.70x DSCR, and returns 11.6 percent to equity in the base case. Then the book shows how little it takes to break it: a slip in emissions intensity to 0.60 kg CO2e per kg turns that return into -5.2 percent. Tax credits and subsidy schemes in the United States, the European Union and the United Kingdom are described as read in November 2026.
Every figure below is computed by the book's model and reproduced in the companion workbook. The project, its companies, contracts and every figure are fictional teaching assumptions, not market data.
| Item | Value |
|---|---|
| Capital cost (100 MW PEM electrolyzer) | $165,000,000 ($1,650 per kW) |
| Hydrogen output, year 1 / year 10 | 10,011 / 9,185 tonnes |
| Delivered power price, years 1 to 15 | $39.00 per MWh |
| Levelized cost of hydrogen (power / capital) | $4.94 per kg ($2.15 / $2.02) |
| 45V credit and cash after transfer | $3.185 / $2.930 per kg |
| Offtake price, year 1 | $2.60 per kg, escalating 2.0 percent |
| Debt sized at a 1.70x DSCR / equity | $112,270,912 / $67,652,879 |
| Equity IRR / project IRR / multiple | 11.6 percent / 9.6 percent / 2.30x |
| CFADS in year 10 / year 11 (the credit cliff) | $23,725,279 / $4,817,114 |
| Equity IRR if the credit tier slips (CI 0.60) | -5.2 percent |
| Offtake price for a 10 percent equity return: with / without the credit | $2.51 / $4.65 per kg |
The live Excel workbooks behind every table in the book. Blue inputs, black formulas, no macros, no circular references, and a Checks tab that must read zero. No sign-up required for book readers.
Appendix A, chapters 2 to 13
Eleven tabs: README, Inputs, Production, LCOH, Credit, CashFlow, Debt, Returns, Scenarios, Sensitivity and Checks. Twenty-five operating years in columns, from output and the credit to the sculpted debt and the equity returns.
Download Green_Hydrogen_Workbook.xlsx39 KBStandalone practitioner tool
One plant: capacity, consumption and degradation, capacity factor, power price, capital cost, fixed costs, stack replacement and discount rate, with the levelized cost and its five parts. Prefilled with the base case: $4.94 per kg, $2.79 net of the credit.
Download LCOH_Calculator.xlsx14 KBWant the calculator first? Open the free LCOH Calculator page for the worked example and the Excel download.