Rough-Cut Capacity Planning (RCCP) Example: Five-Work-Center Walkthrough

How to compute honest Rated Capacity, build a Bill of Resources, isolate a 110.7 percent bottleneck, and separate your raw deficit from your protected capacity gap.

Average plant utilization hides fatal bottlenecks behind underloaded departments. Rough-Cut Capacity Planning (RCCP) translates a Master Production Schedule through a Bill of Resources into work-center load percentages, exposing both your raw deficit and your protected capacity gap months before delivery lead times expire.

Worked in full in The Production Capacity Planning Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Why Plant-Wide Averages Lie About Capacity

In almost every discrete manufacturing plant, finance looks at aggregate scheduled hours across all departments and sees 70 to 83 percent utilization, while the plant manager stares at overflowing staging pallets and weekend overtime rosters. Both are right, because capacity is non-fungible: spare hours on an assembly bench cannot cut 5-axis stainless steel housings on an overloaded machining center.

Within the ASCM/APICS hierarchy, Rough-Cut Capacity Planning (RCCP) sits directly beneath the Master Production Schedule (MPS) on a 3-to-18-month horizon. Its job is to verify whether critical work centers can actually support the sales plan before Material Requirements Planning (MRP) releases work orders and before lead times for hiring shifts or buying equipment run out.

Step 1: Compute Honest Rated Capacity (Not Scheduled Clock Hours)

Never load a forecast against raw scheduled clock hours. Under ASCM conventions, forward-looking Rated Capacity converts scheduled time into standard earned hours:

Rated Capacity = Scheduled Hours x Utilization x Efficiency

In The Production Capacity Planning Handbook, every calculation is worked on one fictional U.S. manufacturer, Kestrel Precision Components, Inc., operating a 110,000-square-foot plant across 250 operating days per year (50 weeks x 5 days) on 2 shifts of 8.0 hours (4,000 scheduled hours per machine). On Work Center 20 (WC-20, four 5-axis CNC machining centers = 16,000 scheduled hours), 3,200 hours are lost annually to setups (1,600 hrs), unplanned breakdowns (960 hrs), and planned PM/handoffs (640 hrs), yielding 80.0 percent utilization and 90.0 percent efficiency (72.0 percent combined):

WC-20 Rated Capacity = 16,000 x 0.80 x 0.90 = 11,520 standard hours/year

Step 2: Multiply the Forecast by the Bill of Resources

Kestrel builds three product families: Precision Valves (0.25 WC-20 hrs/unit), Hydraulic Manifolds (0.50 hrs/unit), and Actuator Housings (0.75 hrs/unit). In Fiscal 2025, Kestrel shipped 24,000 units ($36,000,000 revenue). Entering Fiscal 2026, two new OEM contracts lift forecast volume by 25.0 percent to 30,000 units ($45,000,000 revenue). Loading all five work centers exposes the exact constraint immediately:

Work CenterRated Cap (Std Hrs)FY2025 Load (%)FY2026 Load (%)
WC-10: Sawing (2 saws)6,4604,080 (63.2%)5,100 (78.9%)
WC-20: 5-Axis CNC (4 mach)11,52010,200 (88.5%)12,750 (110.7%)
WC-30: Heat Treat (2 lines)6,2563,552 (56.8%)4,440 (71.0%)
WC-40: Assembly (6 benches)18,36011,400 (62.1%)14,250 (77.6%)
WC-50: Automated Test (3 stands)10,0325,736 (57.2%)7,170 (71.5%)

Notice the trap: aggregate plant load across all five work centers is only 83.1 percent, yet WC-20 hits 110.7 percent while every other department sits safely between 71.0 percent and 78.9 percent.

Step 3: Separate the Raw Deficit From the Protected Capacity Gap

Subtracting 11,520 rated hours from 12,750 required hours shows a 1,230-hour raw deficit. Expanding only to 12,750 hours, however, leaves WC-20 at 100.0 percent utilization, where queueing wait times under Kingman's VUT equation explode toward infinity. Setting an 85.0 percent utilization ceiling (retaining 15 percent protective capacity) reveals the true gap:

Required Protected Capacity = 12,750 / 0.85 = 15,000 standard hours/year

Protected Capacity Gap = 15,000 - 11,520 = 3,480 standard hours/year

Without expanding WC-20, Kestrel forfeits 1,640 Actuator Housings ($3,772,000 revenue and $1,886,000 Throughput). To run this exact five-work-center RCCP on your own plant, download the free Capacity Planning Calculator, then read bottleneck analysis and Theory of Constraints and adding a third shift vs. buying a new machine.

Questions practitioners ask

What is the difference between RCCP and CRP?

Rough-Cut Capacity Planning (RCCP) checks medium-term (3 to 18 months) feasibility of the Master Production Schedule against critical work centers using a Bill of Resources. Capacity Requirements Planning (CRP) checks short-term (1 to 12 weeks) MRP work-order loads across all work centers including existing WIP and setup lot sizes.

How do you calculate Rated Capacity in RCCP?

Multiply Scheduled Hours (machines x shifts x hours per shift x operating days) by Utilization (actual run hours / scheduled hours) and Efficiency (earned standard hours / actual run hours).

Why should you plan to an 85 percent utilization ceiling instead of 100 percent?

Under Kingman's VUT queueing equation, queue wait times scale by U / (1 - U). Pushing a variable work center from 85 percent to 95 percent utilization more than triples queue wait time and floor WIP without adding proportional throughput.

Read the full handbook

This guide is drawn from The Production Capacity Planning Handbook, following Kestrel Precision Components through a complete Rough-Cut Capacity Plan, SMED unlock, and 5-year shift-vs-machine capital decision.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Capacity Planning Calculator (Excel).

Illustrative figures computed by the book model; Kestrel Precision Components, Inc. is fictional. Education only, not legal, tax, or accounting advice.