Why Throughput per Constraint Hour beats unit gross margin, how Kingman's VUT equation explodes queues above 85 percent, and how SMED unlocks hidden hours before CapEx.
In any manufacturing plant, total throughput is dictated by one constraint. Ranking products by unit gross margin instead of Throughput per Constraint Hour destroys hundreds of thousands of dollars in cash profit, while failing to exploit the bottleneck via SMED before buying equipment wastes capital.
Worked in full in The Production Capacity Planning Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Theory of Constraints (TOC) gives plant leaders a strict five-step sequence so they never spend capital prematurely: (1) Identify the constraint via RCCP and floor queues; (2) Exploit it to extract maximum good output from existing assets; (3) Subordinate every non-bottleneck to its pace via Drum-Buffer-Rope; (4) Elevate the constraint with shifts or CapEx only if demand still exceeds capacity; and (5) Repeat once the bottleneck moves.
When Work Center 20 (5-Axis CNC Machining) at Kestrel Precision Components is temporarily capped at 11,520 standard hours against 12,750 hours of Fiscal 2026 demand in The Production Capacity Planning Handbook, management must decide which product to prioritize. Looking only at unit Throughput (Selling Price minus Direct Material), Actuator Housings look best at $1,150/unit versus $480/unit for Precision Valves.
Now divide each family's unit Throughput by the exact CNC hours it consumes on WC-20:
| Product Family | Unit Throughput (T) | WC-20 Hrs/Unit | T / Bottleneck Hr |
|---|---|---|---|
| Precision Valves (PV) | $480 | 0.25 hrs | $1,920/hr (Rank 1) |
| Hydraulic Manifolds (HM) | $900 | 0.50 hrs | $1,800/hr (Rank 2) |
| Actuator Housings (AH) | $1,150 | 0.75 hrs | $1,533.33/hr (Rank 3) |
The ranking completely reverses. Prioritizing Precision Valves and Hydraulic Manifolds leaves 3,270 CNC hours for 4,360 Actuator Housings, generating $20,314,000 in plant Throughput. Prioritizing Actuator Housings by naive unit margin generates only $19,838,400 - throwing away $475,600 per year in gross Throughput (T) on the exact same spindles!
Even before hitting 100 percent load, pushing a bottleneck past 85 percent destroys lead times. On WC-20 (mean batch time 4.0 hrs, combined variability factor V = 0.50), Kingman's equation (W_q = [U / (1 - U)] x V x T_e) shows queue wait time jumping from 6.0 hours at 75.0 percent utilization to 11.3 hours at 85.0 percent, 15.5 hours at 88.5 percent, and 38.0 hours at 95.0 percent. By Little's Law (WIP = lambda x Lead Time at 10.2 batches/day), running at 95 percent instead of 85 percent bloats floor WIP from 9.8 batches to 26.8 batches.
Before buying a fifth machine, Kestrel invests just $45,000 in SMED (zero-point quick-change pallet receivers, off-line tool presetting, cell-side gauges) and autonomous PM. Cutting setup losses 50 percent (1,600 to 800 hrs) and unplanned downtime 25 percent (960 to 720 hrs) recovers 1,040 run hours, lifting WC-20 capacity from 11,520 to 12,456 standard hours (+936 hrs/yr at $48.08/hr one-time). Paired with a 16-hour Drum-Buffer-Rope constraint buffer, exploitation proves that the remaining 294-hour raw deficit (2,544-hour protected gap) requires structural expansion.
Build your own bottleneck load profile with the free Capacity Planning Calculator, review a worked Rough-Cut Capacity Planning (RCCP) example, and compare permanent expansion paths in adding a third shift vs. buying a new machine.
Divide each product's unit Throughput (Selling Price minus Truly Variable Direct Material) by the hours it consumes on the bottleneck work center. Fulfill the highest Throughput-per-constraint-hour products first.
DBR schedules the bottleneck finitely (the Drum), stages a protected time buffer directly in front of it (the Buffer), and ties raw-material release upstream (the Rope) strictly to bottleneck consumption so WIP cannot bloat.
SMED unlocks hidden capacity on existing assets for a fraction of capital cost ($48.08/std hr one-time at Kestrel) with zero added fixed labor, and every future machine added to the cell inherits the higher effective yield.
This guide is drawn from The Production Capacity Planning Handbook, following Kestrel Precision Components through a complete Rough-Cut Capacity Plan, SMED unlock, and 5-year shift-vs-machine capital decision.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Capacity Planning Calculator (Excel).
Illustrative figures computed by the book model; Kestrel Precision Components, Inc. is fictional. Education only, not legal, tax, or accounting advice.