Exact 3-bus DC-OPF proof of PTDFs (0.500, 0.250), $100.00/MW-h shadow price, $70.00/MWh sink LMP, and 87.5% derate funding.
Every nodal congestion spread is a linear combination of transmission shift factors and binding shadow prices. Once you derive the Simultaneous Feasibility Test (SFT) on a three-bus grid, both revenue adequacy and outage-driven funding haircuts become completely transparent.
Worked in full in The Congestion Revenue Rights Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
On the fictional Redwood-Sierra-Bay 3-Bus System in The Congestion Revenue Rights Handbook (Bus A at $20.00/MWh, Bus B at $45.00/MWh, Bus C load 400 MW), Kirchhoff's Voltage Law sets Line L2 shift factors at 0.500 (Bus A to C) and 0.250 (Bus B to C). When Line L2 binds at 120 MW, its shadow price equals $100.00/MW-h, pushing Bus C's LMP to $70.00/MWh (higher than the most expensive generator on the grid!):
| 3-Bus System Metric | Base Case (120 MW L2) | Outage Derate (105 MW L2) | Variance |
|---|---|---|---|
| Bus A / Bus B Dispatch | 80 MW / 320 MW | 20 MW / 380 MW | -60 MW / +60 MW |
| ISO Congestion Rent Collected | $12,000 | $10,500 | -$1,500 |
| Awarded CRR Target Payouts | $12,000 | $12,000 | $0 |
| System Funding Ratio | 100.0% | 87.5% | -12.5% |
When Line L2 is intact, 160 MW of A-to-C CRRs plus 160 MW of B-to-C CRRs use exactly 120 MW of SFT capacity and settle at 100.0% revenue adequacy. A 15 MW Day-Ahead derate to 105 MW shrinks congestion rent to $10,500 and cuts Path A-to-C pro-rata payout from $8,000 to $7,000.
The trap: Never confuse individual node MCCs with invariant spreads. While single-node MCCs depend on the ISO's reference slack bus, source-to-sink differentials are strictly shift-factor invariant.
Next steps: compare CAISO Track 1B vs. ERCOT CRRBA vs. PJM funding, review FERC Order 741 and PJM HSIM collateral, and download the free CRR Valuation & Settlement Calculator (Excel).