How do you calculate unabsorbed overhead with the Eichleay formula?

Eichleay allocates head office overhead to the contract by its share of billings and spreads it over the days actually worked, which is why it gives less than Emden on the same accounts.

The Eichleay formula allocates the contractor's home office overhead to the delayed contract in proportion to its billings, divides it by the days the contract was actually performed, and multiplies by the days of compensable delay. On an illustrative 24,000,000 contract, for a contractor billing 160,000,000 with 12,800,000 of home office overhead, a 90-day delay on a 600-day programme gives 2,782.61 a day and a claim of 250,435, against 288,000 by the Emden formula on the same accounts.

Worked in full in Construction Cost Control by Julian R. Sterling, with every figure reproduced in a free workbook.See the book on Amazon →

What the formula is for

When an owner suspends or delays the work, the site costs of the delay can be counted: plant, supervision, welfare. The head office cannot. Its rent, its estimators and its accounts department carry on, and the delayed contract is no longer generating the turnover that was meant to pay its share of them. That share is unabsorbed overhead. The Eichleay formula, named after a 1960 decision of the US Armed Services Board of Contract Appeals, is the standard way of quantifying it on US federal work; in the UK and Commonwealth the Hudson and Emden formulas do the same job.

US federal boards and courts allow Eichleay only where the government delayed the work for an uncertain period, the contractor was on standby and it could not reasonably take on replacement work. The arithmetic below is the easy part; proving those conditions is the hard one.

The assumptions

Illustrative contractor and contract
InputValue
Contract billings over the actual performance period24,000,000
Total company billings over the same period160,000,000
Total home office overhead over the same period12,800,000
Original contract period, days600
Compensable delay, days90
Actual days of performance690
Head office overhead in the tender, for Hudson6.0%

Overhead here means head office costs only, excluding profit, so that the three formulas compare like with like. All figures are illustrative.

The calculation, step by step

1. Allocable overhead = (contract billings / total company billings) × total home office overhead = (24,000,000 / 160,000,000) × 12,800,000 = 15.0% × 12,800,000 = 1,920,000.

2. Daily overhead rate = allocable overhead / actual days of performance = 1,920,000 / 690 = 2,782.61.

3. Claim = daily rate × days of compensable delay = 2,782.61 × 90 = 250,435.

Excel: =24000000/160000000*12800000/(600+90)*90

The claim is 1.04 per cent of the contract billings. The divisor is what distinguishes Eichleay: the overhead allocated by billings is the overhead of the whole period the contract was on the books, delay included, so it is spread over the 690 days actually worked, not the 600 planned.

Eichleay against Emden and Hudson

Same delay, three formulas
FormulaMethodDaily rate90-day claim
EichleayBillings share of actual overhead, over actual days2,783250,435
EmdenOverhead % from the accounts (8.0%) × contract sum, over the original period3,200288,000
HudsonOverhead % in the tender (6.0%) × contract sum, over the original period2,400216,000

Emden and Eichleay start from the same accounts and the same 8.0 per cent overhead ratio, yet Eichleay gives 13.0 per cent less. The only difference is the divisor. Hudson uses the percentage the contractor priced rather than the one it incurred, so a contractor that priced its overhead below what it actually carries claims less, and one that priced above it claims more.

What moves the claim

Eichleay claim by length of delay
Delay, daysActual daysDaily rateEichleayEmden
306303,047.6291,42996,000
606602,909.09174,545192,000
906902,782.61250,435288,000
1207202,666.67320,000384,000
1807802,461.54443,077576,000

The Eichleay claim grows less than in proportion to the delay, because a longer delay lowers its own daily rate. The billings ratio matters as much: if the company's total billings over the period were 120,000,000 rather than 160,000,000, the contract's share would be 20.0 per cent and the claim 333,913; at 200,000,000 it would be 12.0 per cent and 200,348. A contractor whose other work grew during the delay therefore claims less, which is consistent with the formula's premise that the overhead was absorbed elsewhere.

The common mistakes

Takeaway

The time-related costs of a delay on site, priced alongside head office overhead, are in the free workbook for this case, and worked in full in how to calculate prolongation costs. Productivity losses from the same delay are in the measured mile calculation.

Questions readers ask

What is the difference between the Eichleay and Emden formulas?

Both allocate head office overhead by the contract's share of turnover. Emden takes the overhead percentage from the accounts, applies it to the contract sum and divides by the original contract period; Eichleay divides by the actual days of performance including the delay. On the illustrative figures Emden gives 288,000 for 90 days and Eichleay 250,435, 13.0 per cent less.

Why does dividing by the original contract period overstate an Eichleay claim?

Because the overhead allocated by billings already covers the whole performance period, delay included. Spreading 1,920,000 over 600 days instead of 690 lifts the daily rate from 2,782.61 to 3,200 and the claim from 250,435 to 288,000, 15.0 per cent more, which reproduces Emden rather than Eichleay.

Does a longer delay give a proportionally larger Eichleay claim?

No. The allocable overhead is fixed by the billings ratio, so each extra day of delay also lowers the daily rate. On the illustrative contract 90 days are worth 250,435 and 180 days 443,077, not twice as much; Emden, with a fixed daily rate, would give 576,000 for 180 days.

Read the whole case

This article is one calculation from Construction Cost Control. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Also on this site

Reading guide: business operations: cost, contracts, pricing and supply chain → · All 1340 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.