Companion files

Construction Cost Control

Construction Cost Management and Contract Administration from the Contract Sum to the Final Account

These are the four Excel workbooks that go with the book. Every figure the book prints is reproduced in them by a live formula rather than a typed constant — change the design completeness, the provisional sums released, the weeks of extension of time or the escalation index, and every dependent number moves. Each one ends with a Checks sheet setting the printed figure beside the computed one: 242 controls in all, every one green. If a control ever reads FAIL, the workbook is wrong, not the book.

Free to download. No sign-up, no email address, nothing to fill in.

All four workbooks

Download the ZIP72 KB

Everything described below is inside it, with the read-me.

The four workbooks

Conventions used throughout

Blue textan input — change it and everything recomputes
Yellow fillan assumption that decides the answer rather than merely feeding it
Black texta formula — do not overtype these
Grey texta note
Checks sheetthe printed figure beside the computed one, the difference, a PASS or a FAIL, and the tolerance being applied

Why the checks matter more than the models

A workbook that agrees with a book proves nothing on its own — the author wrote both. What the Checks sheets do is different: they force the model to reproduce a number that was printed before the model existed, from a formula rather than from the number itself.

On this book the discipline caught the liquidated damages line. The client recovers damages for the weeks the contractor is late less the weeks it carries an extension of time, at 14,500 a week and under a cap, and the model writes that as max(0, weeks late less weeks with an extension). Written the obvious way, as a MIN against the cap with no floor beneath it, the arithmetic runs on past zero the moment the extension exceeds the delay — and one of the sensitivity tables does exactly that, taking the extension of time from 0 up to 16 weeks against a delay of 14. At the top row the line changed sign: a 43,500 credit to the client became a 29,000 charge against it, a contractor paid damages for finishing early on time it had been granted, and the movement column carried the error without ever looking wrong.

The second thing the checks caught is smaller, and it is left in view rather than tidied up. Construction costs are carried between the workbooks rounded to the pound, as the book prints them, so a figure the appraisal rebuilds from a rounded input can land one pound from the figure on the page. Six do: five in the appraisal, on the finance line, the total cost, the profit and the profit lost to the gap, and one in the pre-signature workbook. None of the six is smoothed away by widening a percentage or nudging an input. Instead every Checks sheet carries a sixth column stating the tolerance it applies, one pound on the fifty money checks that are fed a rounded cost and eight decimal places on the other 192, and the difference column prints the pound. 236 of the 242 land on zero.

Where two readings of the same quantity are defensible, both are printed. The Case A final account returns 8.59 per cent profit on cost with the facility held at the amount it was sized on, and 7.99 where the facility is stretched to cover the overrun instead of the equity being called; Case B, 13.40 and 13.14. Neither column is the answer on its own, and the workbook does not choose between them.

Opening the files

The workbooks open in Microsoft Excel, LibreOffice Calc, Google Sheets and Numbers. They use no macros and no add-ins, so nothing needs to be enabled or trusted. If your spreadsheet asks to update links on opening, decline — there are none.

Also by Julian R. Sterling

The other books with companion files. The full list of titles is on the author page.