How do you calculate a measured mile for a disruption claim?

The contractor's productivity on the same work, before and during the disruption, is the record that turns lost hours into money.

A measured mile compares the contractor's productivity on the same work in an unimpacted period with its productivity in the impacted one, and prices the hours lost at the difference. On an illustrative drylining package, 4.00 m2 an hour before the disruption against 3.00 after, adjusted for harder floors and the contractor's own rework, the claim is 656.1 hours, or 30,180. The total cost method, measured against the tender, would claim 55,200.

Worked in full in Construction Cost Control by Julian R. Sterling, with every figure reproduced in a free workbook.See the book on Amazon →

Disruption is lost productivity: the work gets done, but it takes more hours than it should because of something the client carries, late information, out-of-sequence access, trades stacked on the same floor. Unlike prolongation, there is no weekly rate to multiply. The loss has to be shown from the contractor's own records, and the measured mile is the method that does this with the least assumption: the contractor is compared with itself, on the same job, in the same trade.

The assumptions

Illustrative drylining package on an apartment block, from the contractor's daily allocation sheets.
InputValue
Unimpacted period, floors 2 to 4: area completed, m24,600
Unimpacted period: operative hours1,150
Impacted period, floors 5 to 8: area completed, m212,600
Impacted period: operative hours4,200
Tender output, typical floors, m2 per hour4.20
Tender output, upper floors with more bathroom pods and shafts, m2 per hour3.86
Hours of the contractor's own rework in the impacted period120
All-in cost per operative hour46.00

The impacted period is the one in which, on the record, the client's late services coordination drawings forced the drylining gangs to work around incomplete risers and return to finished areas. The unimpacted period is floors 2 to 4, completed before the drawings were late.

The calculation, step by step

Step 1: the two productivity rates. Unimpacted: 4,600 ÷ 1,150 = 4.00 m2 an hour. Impacted: 12,600 ÷ 4,200 = 3.00 m2 an hour. Productivity fell by 25.0 per cent.

Step 2: the hours the impacted work should have taken. At the unimpacted rate, 12,600 ÷ 4.00 = 3,150 hours. The raw loss is 4,200 − 3,150 = 1,050 hours, 48,300 at 46.00. That is the number that usually appears first, and it is not yet a claim.

Step 3: make the comparison like for like. The upper floors are harder work: the contractor's own tender priced them at 3.86 m2 an hour against 4.20 on typical floors, a ratio of 0.92. Applying that ratio to the measured rate gives an expected upper-floor output of 4.00 × 0.92 = 3.68 m2 an hour.

Lost hours = actual hours − impacted quantity ÷ (unimpacted rate × complexity factor) − contractor's own hours

= 4,200 − 12,600 ÷ 3.68 − 120 = 4,200 − 3,423.9 − 120 = 656.1 hours

Value = 656.1 × 46.00 = 30,180

In Excel, with impacted hours in B5, impacted m2 in B4, unimpacted m2 and hours in B2 and B3, the factor in B7 and own hours in B8: =(B5-B4/(B2/B3*B7)-B8)*B9, the hourly cost in B9.

Step 4: take out the contractor's own losses. The allocation sheets record 120 hours of rework on boards damaged by the contractor's own follow-on trades. Those hours sit in the impacted period but are not the client's risk, so they come off. What remains, 656.1 hours, is 15.6 per cent of the hours actually worked in the impacted period.

The result

From the raw comparison to the claim.
StepHoursValue
Raw measured mile, no adjustment1,050.048,300
After the 0.92 complexity factor776.135,700
After removing 120 hours of own rework656.130,180
Total cost method, against the tender rate1,20055,200

The total cost method takes the tender output of 4.20 as the benchmark: 12,600 ÷ 4.20 = 3,000 hours expected, 1,200 lost. It overstates the defensible claim by 25,020, or 82.9 per cent, because it charges the client for three things the client did not cause: the harder floors, the contractor's own rework, and a tender that was 5.0 per cent more optimistic than the gangs ever achieved, even on the good floors.

The Society of Construction Law's Delay and Disruption Protocol prefers project-specific productivity comparisons, of which the measured mile is the best known, to industry studies or to total cost claims. It works only if the records exist: daily hours by gang and by area, and the area completed. Without them, there is nothing to measure.

What if: the two adjustments

Claim value by complexity factor and by own-caused hours. Unimpacted rate 4.00, hourly cost 46.00.
Complexity factorNo own hours120 own hours240 own hours
0.8828,54123,02117,501
0.9235,70030,18024,660
0.9642,26236,74231,222
1.0048,30042,78037,260

Each step of 0.04 on the complexity factor moves the claim by between 6,038 and 7,159, more than another 120 hours of own rework would, at 5,520. The factor is where the argument will be, and it is strongest when it comes from the contractor's own tender build-up, as here, rather than from a judgment made after the dispute began.

The choice of unimpacted window matters as much. If the good floors averaged 3.80 m2 an hour, the claim falls to 475.9 hours and 21,891; at 4.20 it rises to 819.1 hours and 37,680. A window chosen because it shows the best week of the job will be attacked, and should be.

The common mistake

The common mistake is to treat the tender as the measured mile. A tender rate is a price, not a record of what the gang could do on this job, and any gap between the two that existed before the disruption is the contractor's risk. The client's quantity surveyor should ask first for the unimpacted rate actually achieved, then for the evidence behind any complexity factor, then for the rework log. Each one usually takes a slice off the claim, and together they took 45.3 per cent off this one.

Takeaway

The book traces disruption, prolongation and every other line of a final account back to inputs that existed at signature, and the free workbook for this case on the Construction Cost Control companion page runs the productivity loss as one of its sensitivities. The time-related side of the same delay is priced in how to calculate prolongation costs for an extension of time.

Questions readers ask

What is the measured mile method in construction?

It measures lost productivity by comparing the same contractor, on the same work and the same project, in a period without disruption and a period with it. In the worked case drylining ran at 4.00 m2 an hour on unaffected floors and 3.00 on affected ones; after adjustments the loss is 656.1 hours, priced at 30,180.

Why is the total cost method weaker than a measured mile?

It assumes the tender was achievable and that every overrun was the client's fault. Measured against a tender rate of 4.20 m2 an hour the drylining claim is 1,200 hours and 55,200, which includes harder floors, the contractor's own rework and a tender 5.0 per cent more optimistic than the gangs ever achieved.

What if there is no unimpacted period to measure?

Use the closest comparable: another floor, another trade gang, or a similar earlier project of the same contractor, adjusted for differences, and accept that the claim weakens. The adjustment itself carries weight: here a complexity factor between 0.88 and 1.00 moves the claim from 23,021 to 42,780.

Read the whole case

This article is one calculation from Construction Cost Control. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Also on this site

Reading guide: business operations: cost, contracts, pricing and supply chain → · All 1340 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.