Free calculators

Eichleay formula calculator

Unabsorbed home office overhead on a delayed contract by the Eichleay formula, with the Hudson and Emden formulas side by side. Free, in the browser, no sign-up.

The Eichleay formula allocates the contractor’s home office overhead to the delayed contract in proportion to its billings, divides it by the days of performance and multiplies by the days of compensable delay. With the defaults below, a 24,000,000 contract for a contractor billing 160,000,000 with 12,800,000 of overhead, delayed 90 days, the rate is 2,782.61 a day and the Eichleay claim is 250,435, against 288,000 by Emden and 216,000 by Hudson.

Calculate

Results, updated as you type. The defaults reproduce the worked case.
ResultValue
Allocable overhead1,920,000
Daily overhead rate2,782.61
Eichleay claim250,435
Emden claim (actual overhead percentage)288,000
Hudson claim (tender overhead percentage)216,000

Runs in your browser: nothing you type is sent anywhere.

Using this for a real deal?

The formula

1. Allocable overhead = contract billings / total billings × total home office overhead

2. Daily rate = allocable overhead / actual days of performance

3. Claim = daily rate × days of compensable delay

Emden = actual overhead % × contract sum / contract period × delay; Hudson uses the tender overhead % instead.

How it works

Use billings and overhead for the same period, the actual performance period of the delayed contract, and overhead only, excluding profit, so the three formulas compare like with like. US federal boards and courts allow Eichleay only where the government delayed the work for an uncertain period, the contractor was on standby and could not reasonably take on replacement work; in the UK and the Commonwealth, Hudson and Emden do the same job.

The arithmetic is the easy part. The claim stands or falls on proving the standby and the inability to take other work, and on overhead records that tie to the audited accounts.

Go further with the worked example, step by step and the companion files for Construction Cost Control.

Embed this calculator

Free to embed on your website, blog or intranet, with no sign-up and no tracking. Copy the code below and paste it into any HTML block; the calculator resizes itself to fit.

Preview the embedded version

Questions people ask

How do you calculate the Eichleay formula?

In three steps: contract billings over total billings times total home office overhead gives the allocable overhead; divided by the actual days of performance it gives a daily rate; times the days of compensable delay it gives the claim. 1,920,000 / 690 days × 90 days = 250,435.

What is the difference between Eichleay, Hudson and Emden?

Eichleay allocates the actual overhead by billings over the days performed. Emden applies the actual overhead percentage to the contract sum per day; Hudson uses the overhead percentage in the tender. On the default figures they give 250,435, 288,000 and 216,000.

When can a contractor use the Eichleay formula?

On US federal work, where the government caused a delay of uncertain length, the contractor was on standby and could not reasonably take on other work. The formula prices the claim; it does not prove entitlement.

The book behind this calculator

This calculator comes from Construction Cost Control by Julian R. Sterling, which works the same case in full, with every figure in a free workbook.

Get the book on Amazon → DRM-free PDF edition, $19.99

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review.

Not on Amazon: 11 paperbacks by Julian R. Sterling on banking, credit and payments, printed on demand and shipped worldwide. Browse the bookshop →

All free calculators → · Free Excel templates →