How much can a data centre earn by reselling power that customers contract but never draw?

Colocation customers rarely draw all the power they contract for. The gap is stranded capacity, and selling part of it again turns it into revenue at the price of a risk the operator has to measure.

A 36.0 MW campus has 32.4 MW under contract, but customers peak at only 67% of what they bought. That leaves 10.69 MW stranded. Selling half of it again at $145 per kW per month earns $9.30m a year and lifts contracted capacity to 37.75 MW. The campus stays safe until the customers' peak ratio passes 95.4%.

Learn the whole method: Data Center Development & Finance

A course built on one 60 MW campus, from grid tranches and cost per MW to leases, the power recharge, the construction loan, the refinancing and the stress tests, with Excel exercises, a 162-question quiz and the Data Center Development Model, Pro Edition included ($199).

Try module 3 and ten quiz questions, free →

The assumptions

Illustrative colocation campus, invented figures
ItemValue
Critical capacity of the campus36.0 MW
Capacity under contract32.4 MW (90%)
Peak draw of customers, share of contracted67%
Average draw of customers, share of contracted58%
Price of contracted capacity$145 per kW per month
Share of the unused gap the operator sells again50%

Customers pay for what they contract, not for what they draw, so the operator already earns 32.4 × 1,000 × $145 × 12 = $56.4m a year. The question is what to do about capacity that is contracted but never used.

Step 1: how much capacity is stranded

Average draw = 32.4 × 58% = 18.79 MW

Peak draw = 32.4 × 67% = 21.71 MW

Stranded at peak = 32.4 − 21.71 = 10.69 MW, or 29.7% of the whole campus

Excel: =32.4*(1-67%)

Step 2: what reselling half of it earns

Capacity resold = 10.69 × 50% = 5.35 MW

Revenue = 5.346 × 1,000 × 145 × 12 = $9.30m a year

Contracted capacity becomes 32.4 + 5.35 = 37.75 MW, or 104.9% of the campus

Peak draw becomes 37.75 × 67% = 25.29 MW, 70.2% of capacity

Excel: =32.4*(1-67%)*50%*1000*145*12/1000000

The campus is contracted above 100% but its peak draw stays at 70.2% of capacity. The resale works only while customers keep drawing a small share of what they have bought. The revenue is also the least secure on the campus, because the new customers have the same rights to ramp up as the old ones.

What if: the peak draw is higher or lower

Resale of half the stranded gap, by peak draw ratio
Peak draw ratioStranded gapResoldExtra revenueContracted afterPeak draw after
55%14.58 MW7.29 MW$12.68m39.69 MW21.83 MW (60.6%)
67%10.69 MW5.35 MW$9.30m37.75 MW25.29 MW (70.2%)
80%6.48 MW3.24 MW$5.64m35.64 MW28.51 MW (79.2%)
90%3.24 MW1.62 MW$2.82m34.02 MW30.62 MW (85.0%)

The lower the peak ratio, the more there is to sell and the more room is left. The break-even is how far the peak ratio can rise before the campus cannot serve everyone: with 37.75 MW contracted it is 36.0 ÷ 37.75 = 95.4%. At 80% the peak draw would be 30.20 MW, and at 90% it would be 33.97 MW, 94.4% of capacity, which leaves no margin for a cooling or distribution fault.

Extra revenue at a different price, 67% peak ratio
Price per kW per monthExtra revenue a year
$100$6.42m
$120$7.70m
$145$9.30m
$170$10.91m

The common mistakes

Takeaway

Free Excel template: data center financial model.

Questions readers ask

What is stranded capacity in a data centre?

Power that is contracted to customers but never drawn. Here customers contract 32.4 MW and peak at 21.71 MW, which leaves 10.69 MW.

How much can an operator earn by reselling it?

In this example half of the gap is 5.35 MW. At $145 per kW per month that is $9.30m a year.

What stops the operator from selling all of it?

The risk that customers draw more at the same time. With 37.75 MW sold the campus runs out of power if the peak ratio passes 95.4%.

The workbooks behind this article

The free companion files for The Data Center Operations Handbook rebuild a 36 MW colocation campus month by month for three years after handover, with the operating checklists in editable form. The customer contracts in this article are invented and are not in them. No account and no email address.

Open the companion files →