Divide stabilized NOI by total development cost, interest during construction included, and compare it with the cap rate: here 11.44% against 6.75%, a spread of 469 bps.
Data center yield on cost is stabilized net operating income divided by total development cost. On a fictional 60 MW turnkey campus, forward NOI of 87.5m over a total cost of 765.1m (12.75m per MW, interest and fees included) gives 11.44%. Against a 6.75% cap rate, the development spread is 469 bps and the campus is worth 1,296.2m.
The case comes from The Data Center Development Handbook and the Data Center Development & Finance course by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or see it on Amazon
Yield on cost is the first number a developer, a lender and an investment committee look at, because it answers the only question that matters before the capital is spent: will the finished, leased asset earn enough on what it cost to be worth more than it cost? The steps below compute it on one campus, with every line traceable.
| Input | Value |
|---|---|
| IT load, in three phases of 20 MW | 60 MW |
| Design peak PUE / utility capacity | 1.30 / 78.0 MW |
| Cost per MW before contingency (turnkey) / contingency | 11.45 / 5% |
| Rent, $ per kW-month (2027), escalator | 110.00, 3% |
| Construction loan: loan to cost + interest reserve | 60% + 6% |
| Cap rate (refinancing and exit) | 6.75% |
Budget = cost per MW × (1 + contingency) × MW = 11.45 × 1.05 × 60 = 721.35m
Interest during construction, to the quarter the last phase starts paying rent: 38.99m
Arrangement fee on the construction loan: 4.76m
Total development cost = 721.35 + 38.99 + 4.76 = 765.10m, or 12.75m per MW
The budget alone would overstate the yield: 87.5 / 721.4 = 12.13%. Interest and fees are part of what it cost to deliver the asset. The case's all-in 12.75m per MW sits inside the $8.9m to $23.3m range of Cushman & Wakefield's 2026 guide; how much a data centre costs to build per MW breaks the lines down.
NOI = rent + power margin − operating costs − management fee
Forward NOI at the refinancing (Q4 2032, the next four quarters): 87.49m
Rent is $110 per kW-month in 2027 money on 60 MW of leased capacity, rising 3% a year. The landlord also keeps a small margin on power, billing the tenant at a PUE of 1.35 and buying at 1.25. Use forward NOI from a fully leased rent roll: on the first fully leased year (84.3m) the yield would read 11.02%. Say which year you use.
A course built on one 60 MW campus, from grid tranches and cost per MW to leases, the power recharge, the construction loan, the refinancing and the stress tests, with Excel exercises, a 162-question quiz and the Data Center Development Model, Pro Edition included ($199).
Yield on cost = 87.49 / 765.10 = 11.44%
Development spread = 11.44% − 6.75% = 469 bps
Value = forward NOI / cap rate = 87.49 / 6.75% = 1,296.2m; value created 531.1m
In Excel: =NOI/TotalCost and =NOI/CapRate-TotalCost
The spread is the margin of safety. Developers usually want a few hundred basis points over the exit cap rate to be paid for the grid, construction and lease-up risks. CBRE put Class A data center cap rates at 100 to 150 basis points over the 10-year Treasury in 2025; the case uses a higher 6.75% to price a single tenant in a secondary market.
| Case | Total cost | Yield on cost | Spread |
|---|---|---|---|
| Turnkey, base case | 765.1 | 11.44% | 469 bps |
| Powered shell on the same site | 227.7 | 11.27% | 452 bps |
| Stress: overrun, late power, lower rent, higher rates and cap rate | 865.9 | 9.17% | 167 bps |
The trap: comparing a yield on cost computed on the budget with one computed on total cost, or a turnkey yield with a powered-shell yield as if the capital were the same. The shell yields 17 bps less on less than a third of the capital; powered shell vs turnkey compares them in full.
Free Excel template: data center financial model.
Every figure is computed by script from the course's running case, Harlow Ridge Data Campus, a fictional 60 MW campus, and checked on 17 November 2026. Market figures are dated assumptions of the case. For education, not investment advice.
A course built on one 60 MW campus, from grid tranches and cost per MW to leases, the power recharge, the construction loan, the refinancing and the stress tests, with Excel exercises, a 162-question quiz and the Data Center Development Model, Pro Edition included ($199).
One that clears the exit cap rate by a few hundred basis points. In the worked case, 11.44% on cost against a 6.75% cap rate leaves 469 bps; the stress case leaves 167 bps.
Yes. Without the 39.0m of interest and the 4.8m fee, the case's yield would read 12.13% instead of 11.44%.
No. Yield on cost divides NOI by what the asset cost to build; the cap rate divides NOI by what a buyer would pay for it. The gap between them is the development spread.
Stabilized NOI from a fully leased rent roll, usually forward NOI at stabilization. State the year: lease-up NOI understates the yield and a later year overstates it.
The turnkey cost is worked into a full underwrite in chapter 13 of The Data Center Development Handbook. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.
Get the book on Amazon →Free companion files
Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada
Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99
Read The Data Center Development Handbook already? A few honest lines on Amazon help the next reader: write a review.