Twelve questions a data center development, infrastructure or lending team asks, each answered in a few sentences and one number, on the same campus.
Data center development interviews test whether a candidate thinks power first. The twelve questions below cover IT and utility megawatts, rent commencement, cost per MW, rent per kW-month, the power recharge, construction and stabilized loans, yield on cost, IRR and stress, each answered on one fictional 60 MW campus that yields 11.44% on cost and 25.32% to its equity.
The case comes from The Data Center Development Handbook and the Data Center Development & Finance course by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or see it on Amazon
Interviewers in this sector come from real estate, infrastructure and project finance, and they probe the places where data centers differ from all three: the grid date decides the rent date, the denominator decides the cost per MW, and the lease PUE decides whether power is a profit or a loss. Working every answer on the same campus is the quickest way to prepare, because the follow-up questions are links between the answers.
| Input | Value |
|---|---|
| IT load, in three phases of 20 MW | 60 MW |
| Design peak PUE / utility capacity | 1.30 / 78.0 MW |
| Cost per MW before contingency (turnkey) / contingency | 11.45 / 5% |
| Rent, $ per kW-month (2027), escalator | 110.00, 3% |
| Construction loan: loan to cost + interest reserve | 60% + 6% |
| Cap rate (refinancing and exit) | 6.75% |
Because the tenant buys power and cooling, not space, and the cost scales with megawatts. Two halls of the same size can differ several times in power, and in value.
IT MW is what the servers can draw; utility MW is what the grid must deliver, IT load times the design peak PUE. The case's 60 MW needs 78.0 MW from the utility at a 1.30 peak PUE.
From the later of two dates: the building is ready, and grid power is available for it. If the first grid tranche of the case slips four quarters, phases 1 and 2 both start in Q11 and the equity IRR falls from 25.32% to 24.21%.
In the case, 11.45m per MW before contingency, of which 64% is electrical and mechanical plant; 12.75m all in with contingency, interest and fees. Cushman & Wakefield's 2026 guide gives $8.9m to $23.3m for the US and Canada.
Because of the denominator and the scope: per IT MW or per utility MW, with or without land, contingency, interest and fees. The case is 12.75m per IT MW all in, but 9.81m per utility MW.
A course built on one 60 MW campus, from grid tranches and cost per MW to leases, the power recharge, the construction loan, the refinancing and the stress tests, with Excel exercises, a 162-question quiz and the Data Center Development Model, Pro Edition included ($199).
In dollars per kW of contracted IT capacity per month. At $110, 1 MW earns $110 × 1,000 × 12 = 1.32m a year, whether or not the tenant uses it; power is billed on what it draws.
By billing metered IT energy at the PUE written in the lease and buying it at the PUE the building achieves. Billed at 1.35, bought at 1.25: a margin of a few million dollars a year here, which disappears if the building drifts to 1.35.
On the approved budget: 60% loan to cost plus a 6% interest reserve, a 476.1m commitment. Equity goes in first (288.5m); the reserve only pays interest, so a 10% overrun (69.3m) is all equity.
The smallest of three limits: loan to value, debt yield and debt service cover. Here 55% of a 1,296.2m value binds at 712.9m, which repays the construction loan and returns 272.8m to the equity.
Stabilized NOI over total development cost: 11.44%. Minus the 6.75% cap rate: 469 bps of spread, 531.1m of value created.
Compound it: (1 + 5.805%)^4 − 1 = 25.32%. Multiplying by four would give 23.22% and understate it.
In the case, rent: 10% lower costs 393 bps of equity IRR. Run together, overrun, late power, lower rent and a higher cap rate cut the IRR to 12.73%, push the refinancing to Q26 and need 69.3m of extra equity: only a full run shows that.
The trap: quoting a cost per MW without its denominator. Say "per MW of IT load, all in" before the interviewer asks, or 12.75m and 9.81m will sound like two different buildings.
Every figure is computed by script from the course's running case, Harlow Ridge Data Campus, a fictional 60 MW campus, and checked on 17 November 2026. Market figures are dated assumptions of the case. For education, not investment advice.
A course built on one 60 MW campus, from grid tranches and cost per MW to leases, the power recharge, the construction loan, the refinancing and the stress tests, with Excel exercises, a 162-question quiz and the Data Center Development Model, Pro Edition included ($199).
IT versus utility MW and PUE, grid interconnection and rent commencement, cost per MW, rent per kW-month and lease terms, the power recharge, construction loans and refinancing, yield on cost, IRR and stress tests.
Often, for investment and finance roles: a short Excel case to phase a campus, compute cost, NOI and yield on cost, and size the debt. Practising on one complete case is the best preparation.
Using IT MW and utility MW interchangeably. The case's 60 MW campus needs 78.0 MW from the grid; sizing the connection on IT load would leave the last phase without power.
The turnkey cost is worked into a full underwrite in chapter 13 of The Data Center Development Handbook. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.
Get the book on Amazon →Free companion files
Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada
Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99
Read The Data Center Development Handbook already? A few honest lines on Amazon help the next reader: write a review.