Billed hours over available hours, by machine group and by month: what a flat total hid in one shop's year.
Machine shop utilization is billed hours divided by available hours, read by machine group and by month. In the worked case it fell from 69.8 to 65.6 percent while billed hours stayed almost flat: the mills lost a customer's part families and a second five-axis machine arrived before its work.
Worked in full in The Machine Shop Owner by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback
Free: the machine shop rate calculator in Excel, prefilled with the worked case of the book.
Utilization is billed hours divided by available hours. Available hours are the hours a machine is staffed and scheduled to run in the shop's calendar: machines times working days times attended shift hours. Billed hours are the spindle hours charged to customers. Read the measure by machine group and by month, because each group has its own customers, and each month its own working days.
Utilization, 2025 = 30,800 billed hours ÷ 46,976 available hours = 65.6 percent (69.8 percent in 2024: 30,700 ÷ 44,000)
Halvercote Precision, the fictional CNC job shop of The Machine Shop Owner, works 250 days a year on two attended 8-hour shifts: 16 available hours per machine per working day.
| Machine group (fictional case) | 2024 billed / available | 2025 billed / available | Utilization |
|---|---|---|---|
| Vertical mills (three-axis) | 16,800 / 24,000 | 15,400 / 24,000 | 70.0 to 64.2 percent |
| CNC lathes | 10,900 / 16,000 | 10,900 / 16,000 | 68.1 to 68.1 percent |
| Five-axis machining centers | 3,000 / 4,000 | 4,500 / 6,976 | 75.0 to 64.5 percent |
| All machines | 30,700 / 44,000 | 30,800 / 46,976 | 69.8 to 65.6 percent |
The total moved little, and that is why it misleads. The vertical mills lost hours: from April 2025 the largest customer moved two part families to a second supplier, and mill hours fell from 16,800 to 15,400. The five-axis group gained 1,500 billed hours, yet its utilization fell from 75.0 to 64.5 percent, because a second five-axis machine ran from 1 April 2025, before the aerospace work it was bought for had arrived. Two causes, two groups, one total that hides both.
The shop's own target is a case policy: billed hours of at least 65 percent of available hours, by group and by month. In 2025 the mills and the five-axis machines were below it and the lathes above it.
Each month's utilization is that month's billed hours over that month's available hours. In 2025 the highest month for all machines was February, at 67.3 percent, and the lowest was December, at 61.9 percent, the month of the holidays. In 2024 the same months were 71.5 and 65.9 percent.
The trap: buying capacity to fix utilization. A new machine raises available hours on the day it is installed and billed hours only when its work arrives. Count whose hours the machine will run before signing the loan.
Rules as read in November 2026. The shop in the examples is fictional; nothing here is legal, tax, accounting or investment advice.
Divide the hours you billed on a machine group by the hours that group was staffed and scheduled to run in the period. Do it for each group and each month.
Use billed hours for utilization, and track hours run separately: the gap between the two is overruns and rework, which the shop pays for and does not bill.
There is no general figure. Set your own target with your costs, rates and debt in view; in the book's case it is a shop policy of 65 percent by group and by month.
It raises available hours first. Utilization rises only if the extra hours are billed.
This article is one calculation from The Machine Shop Owner, a practitioner’s guide to the numbers of an independent CNC job shop: machine hours and shop rates, quoting, scrap and overruns, payroll, machines, cash, the lease and the bank covenant.