How lenders size $6.87B of senior debt off contracted CFADS, syndicate across banks, ECAs, and bonds, and stress-test 12-month delays and $600M overruns.
In non-recourse LNG project finance, senior debt is never sized off EBITDA multiples or spot LNG forecasts. Lenders size debt strictly from contracted take-or-pay CFADS at a 1.40x minimum DSCR, syndicate across commercial banks, ECAs, and project bonds, and neutralize four-year construction risk through LSTK EPC wraps and Completion Support.
Worked in full in The LNG Export Project Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
In The LNG Export Project Finance Handbook, Calcasieu Point LNG generates $922.44 million of annual Contracted-Only Pre-Tax CFADS ($1,222.00 million contracted fixed fees minus $195.00 million Fixed OpEx, $79.56 million contracted Variable OpEx, and $25.00 million annual MMRA funding). Senior lenders haircut the 1.50 MTPA merchant upside and SPA feedgas retainage to zero and size debt across an 18-year post-COD amortizing tenor (leaving a mandatory 2-year contract tail on 20-year SPAs) at a 6.50 percent all-in hedged rate:
$922.44 million / 1.40x Target DSCR = $658.89 million/year.10.4325 -> DSCR-Sized Senior Debt = $6,873.80 million ($6.87 billion).Four years of cryogenic construction expose the SPV to schedule delays and cost overruns. Calcasieu Point LNG signs a $7,200 million LSTK EPC contract with Delay Liquidated Damages of $0.80 million/day (capped at $720 million), Performance LDs capped at $720 million, an aggregate cap of $1,080 million, $600 million base contingency, and an $800 million standby Sponsor Completion Support LC (covering the full $754.80 million combined delay and overrun equity requirement). Look at how four severe downside stresses impact DSCR and Equity IRR:
| Stress Scenario | Sponsor Equity Funded | Operating DSCR | Pre-Tax Equity IRR |
|---|---|---|---|
| Base Case ($3.20/MMBtu Merchant) | $2,909.22 million | 1.79x | 14.23 percent |
| Stress A: +12-Month COD Delay | $3,064.01 million (+$154.80M net IDC) | 1.79x | 12.23 percent (-200 bps) |
| Stress B: +$600M CapEx Overrun | $3,509.22 million | 1.79x | 12.15 percent (-208 bps) |
| Stress C: Merchant @ $1.00/MMBtu | $2,909.22 million | 1.53x | 9.67 percent (-456 bps) |
| Stress D: Combined Severe Stress | $3,664.01 million | 1.53x | 6.84 percent (-739 bps) |
Notice two vital lessons: first, a +12-month delay destroys nearly as much Equity IRR (-200 bps) as a $600 million CapEx overrun (-208 bps) because EPC DLDs ($292.00 million) cover only 65 percent of full-debt delay IDC ($446.80 million) while all operating cash flows slip a year. Second, senior debt suffers $0.00 credit loss across every single stress test because coverage was sized strictly off contracted CFADS and the $800 million standby Completion Support LC covers the full $754.80 million combined delay and overrun call. Explore how LNG export project finance works, compare LNG Sale and Purchase Agreements (SPAs) and tolling models, and run live stress mutations in the free LNG Export Project Model (Excel).
Amortizing senior debt over 18 years against 20-year take-or-pay SPAs creates a 2-year contracted tail (lifting PLCR to 1.48x vs. 1.40x LLCR), giving lenders two extra years of guaranteed cash flows to recover principal if a major outage forces temporary deferral.
Rarely. In Calcasieu Point LNG, a 12-month delay burns $446.80 million in extra IDC on $6,873.80 million of debt at 6.50 percent, while $0.80 million/day EPC DLDs recover $292.00 million, leaving a $154.80 million net funding gap covered by Sponsor Completion Support.
Once construction risk ends, refinancing the remaining Year-3 debt balance ($6,195.28 million) 75 bps tighter (from 6.50 percent to 5.75 percent) over the remaining 15 years cuts Annual Debt Service from $658.89 million to $627.50 million, saving $31.38 million/year.
This guide is drawn from The LNG Export Project Finance Handbook, following Calcasieu Point LNG Export, LLC from pre-filing through Financial Close, debt sizing, and downside stress testing.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: LNG Export Project Model (Excel).
Illustrative figures computed by the book model; Calcasieu Point LNG Export, LLC is fictional. Education only, not legal, regulatory, engineering, accounting, tax, or investment advice.