Trust funds, surety bonds, letters of credit, insurance, financial tests and guarantees under 40 CFR 258.74, priced on a fictional county landfill.
Before a municipal solid waste landfill accepts a ton, its owner must show that money will be there to close it and care for it for thirty years. Federal rules list the instruments that qualify. On a fictional $53.04 million estimate, their first-year cost runs from nothing for a guarantee to $2.77 million of cash for a trust fund.
Worked in full in The Landfill Financial Assurance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
A landfill collects its revenue before it pays its most durable costs. Final cover and at least thirty years of leachate management, gas control, groundwater monitoring and cover maintenance fall due after the gate fee has stopped. Financial assurance is the regulator's answer: a solvency rule attached to the permit. Subpart G of 40 CFR Part 258, written under Subtitle D of the Resource Conservation and Recovery Act, has applied to owners and operators of municipal solid waste landfills since April 9, 1997. Local governments are covered. Only state and federal entities are exempt.
This article uses the Alderwick Regional Landfill, the running case of The Landfill Financial Assurance Handbook. The Alderwick County Solid Waste Authority and every figure attached to it are fictional. The article is educational and is not legal, accounting or investment advice. Each state runs its own program, and the state rule and the permit control.
The amount to be assured is a written cost estimate in current dollars. For closure it is the cost of hiring a third party to close the largest area ever requiring final cover at any time during the active life. For post-closure care it is the third-party cost of the full care period. Both are adjusted for inflation every year.
At Alderwick the engineer prices final cover at $210,000 an acre and the largest open area at 74 acres, so the closure estimate is $15.54 million. Post-closure care is $1,250,000 a year for 30 years, or $37.50 million. The estimate is $53.04 million, and next year, at an inflation factor of 2.6 percent, it becomes $54.42 million.
| Mechanism | What it is | Key conditions |
|---|---|---|
| Trust fund | Cash held by a regulated trustee | Paid in over the shorter of the initial permit term and remaining life: next payment = (estimate less fund value) / years remaining |
| Surety bond | Payment or performance guarantee by a surety | Surety on Treasury Circular 570, penal sum at least the estimate, standby trust, 120 days' cancellation notice |
| Letter of credit | Bank's irrevocable undertaking to pay the state | At least one year, automatic extension, 120 days' notice of non-renewal |
| Insurance | Policy with a face amount at least the estimate | Closure and post-closure only, cancellable only for non-payment, assignable to a successor |
| Corporate financial test | Self-assurance by a strong company | Investment-grade rating or one of two ratios, tangible net worth above covered costs plus $10 million |
| Local government financial test | Self-assurance by a strong local government | Investment-grade general obligation rating or two ratios, limit of 43 percent of total annual revenue |
| Corporate or local government guarantee | Promise by a related party that passes the test | Guarantor performs or funds a trust if the owner fails |
| State-approved mechanism | Anything else the state accepts | Must be sufficient, timely, continuous and enforceable |
Mechanisms may be combined, with one restriction: an instrument that guarantees performance of the work, as opposed to payment, must stand alone.
Alderwick holds a trust fund of $19.80 million, so its gap to the estimate is $33.24 million. The quotes below are fictional indications used in the book.
| Option | Year 1 cost | What is left at closure |
|---|---|---|
| Trust alone, regulatory pay-in over 12 years | $2.77 million of deposits | A full fund |
| Surety bond for the full estimate, 1.25 percent plus collateral | $895,050 | Nothing |
| Letter of credit for the full estimate at 1.75 percent | $928,200 | Nothing |
| Insurance for the full estimate at 2.2 percent | $1,166,880 | Nothing |
| Trust plus a bond for the gap | $0.98 million of deposits plus $560,925 | A fund built by plan |
| Trust plus a county guarantee for the gap | $0.98 million of deposits plus a $83,100 fee | A fund built by plan |
Bonds, letters of credit and insurance are cheap in any one year and build nothing. Over the remaining 24 years of the site, bond costs on the full estimate would total $29.3 million, and the owner would still owe the whole cost of closure and care. A trust is real money but the regulatory pay-in is front-loaded: $2.77 million a year against the $0.98 million level deposit that would actually fund the obligation by the closure date.
The local government financial test asks for cash and marketable securities of at least 0.05 of total expenditures and annual debt service of no more than 0.20 of total expenditures, and it caps assured costs at 43 percent of total annual revenue. A single-purpose landfill authority usually fails. Alderwick's debt service ratio is 0.32, and 43 percent of its $24.00 million revenue is $10.32 million, a fraction of the estimate. The county that created it passes with ratios of 0.18 and 0.09 and a limit of $133.3 million. A county guarantee, drafted as a promise to fund the trust, fills the gap.
A surety, bank or insurer can decline to continue on 120 days' notice. If the owner cannot replace the instrument in time, the state draws the full amount into a standby trust, and the owner owes that amount to the provider at once. Lenders therefore treat outstanding bonds and letters of credit as contingent debt.
The amount assured depends on remaining life, so start with how to calculate landfill airspace and remaining life. Public owners should also read how the GASB 18 landfill closure liability is calculated, because the liability in the audit is not the regulatory estimate. To test the options on your own site, the free Landfill Closure Cost Model (Excel) computes the estimate, the trust payment, the funding plan and the annual cost of each mechanism.
It is the demonstration, required by 40 CFR Part 258 Subpart G and state rules, that funds will be available to pay a third party for closure, post-closure care and corrective action even if the owner cannot.
Section 258.74 lists a trust fund, surety bond, letter of credit, insurance, corporate financial test, local government financial test, corporate guarantee, local government guarantee, state-approved mechanisms and state assumption of responsibility. States may restrict the list.
For closure and post-closure care the next payment equals the current cost estimate less the current value of the fund, divided by the years remaining in the pay-in period, which is the shorter of the initial permit term and the remaining life of the unit.
Only if it passes the local government financial test, and only up to 43 percent of its total annual revenue. General-purpose governments often qualify. Single-purpose solid waste authorities usually need a guarantee or another instrument.
This guide is drawn from The Landfill Financial Assurance Handbook, which follows the Alderwick County Solid Waste Authority through cost estimates, airspace, financial assurance mechanisms, accounting, a funding plan, post-closure risk and a proposed sale.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Landfill Closure Cost Model (Excel).
Illustrative figures computed by the book model; the Alderwick County Solid Waste Authority is fictional. Education only, not legal, tax, accounting, engineering, or investment advice.