GASB 18 Landfill Closure and Post-Closure Liability: Formula and Worked Example

Estimated total current cost, capacity used, next year's expense, the funded ratio that misleads, required disclosures and the Statement 83 exclusion.

GASB Statement 18 recognizes a public landfill's closure and post-closure cost in proportion to capacity used. In a worked example the liability is $18.192 million, the trust fund is $19.80 million, and the owner is still far from funded. Here is why.

Worked in full in The Landfill Financial Assurance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

What Statement 18 Does

Governmental Accounting Standards Board Statement No. 18, issued in August 1993, governs how counties, cities and authorities account for the cost of closing a municipal solid waste landfill and caring for it afterward. Its principle is that this cost belongs to the waste that fills the landfill and should be recognized as capacity is used, not when cash is paid decades later.

The example is the Alderwick County Solid Waste Authority, the fictional owner in The Landfill Financial Assurance Handbook. All Alderwick figures are invented for illustration. This article is educational and is not accounting advice: your auditor determines how the standard applies to your landfill.

The Estimated Total Current Cost

The starting point is the estimated total current cost of closure and post-closure care: what it would cost if all the equipment, facilities and services were acquired in the current period. It covers equipment and facilities installed near or after the date the landfill stops accepting waste, final cover, and post-closure care. It is stated in current dollars, without discounting, re-estimated every year for inflation and for changes in plans or conditions, and based on laws and regulations approved as of the balance sheet date, whatever their effective date.

AlderwickAmount
Closure outlays to date (62 acres capped)$11.20 million
Remaining closure at current cost (118 acres)$24.78 million
Post-closure care (30 years at $1,250,000)$37.50 million
Estimated total current cost$73.48 million

The Authority's policy treats every capping event as closure cost and charges the outlays against the liability. Practice on phased capping varies, so the policy should be written down and agreed with the auditor.

The Formula

Amount recognized to date = estimated total current cost x cumulative capacity used / total estimated capacity

The period's expense is that amount less what was recognized in earlier periods. Outlays for closure reduce the liability. Alderwick has used 9,600,000 of 24,000,000 cubic yards, or 40 percent:

Next Year's Expense Has Two Parts

Next year capacity used rises to 42.5 percent and remaining costs are re-estimated for 2.6 percent inflation, taking the total to $75.099 million. The cumulative amount becomes $31.917 million and the year's expense is $2.525 million, or $6.01 per ton.

ComponentAmount
Capacity used during the year, at last year's cost$1.837 million
Re-estimation of cost, applied to cumulative capacity used$0.688 million
Closure and post-closure expense$2.525 million

The second line is a catch-up on waste already in the ground. It grows as the landfill fills, which is why mature landfills see their expense jump when an engineer re-prices the final cover or a new requirement is adopted. A survey revision works the same way: cutting total capacity by 1,000,000 cubic yards would raise the percentage used to 41.7 percent and add $1.278 million of expense at once.

The Most Misread Ratio in Landfill Finance

Trust assets are reported separately as restricted assets. They are never netted against the liability, and their earnings are revenue. Alderwick's fund of $19.80 million is 109 percent of its $18.192 million liability. That does not mean the obligation is funded.

The same fund measured againstRatio
The accounting liability ($18.192 million)109 percent
The present value of the funding target ($35.49 million)56 percent
The regulatory financial assurance estimate ($53.04 million)37 percent
The remaining cost at current prices ($62.28 million)32 percent

The liability is only the share of total cost attributed to the capacity used so far, less what has been spent. It was never meant to measure the cash required. To know whether an owner is saving enough, compare the fund with a funding target built from the actual closure date, inflation and investment earnings. In the book's plan Alderwick needs $81.03 million on the closure date and a level deposit of $0.98 million a year to get there.

Required Disclosures

These items also satisfy the public notice component of the local government financial test, one of the financial assurance mechanisms for landfill closure and post-closure care.

What About Statement 83?

Statement No. 83 on certain asset retirement obligations expressly excludes landfill closure and post-closure care. A public landfill stays under Statement 18. The same government may report other retirement obligations under Statement 83, measured differently, so the two liabilities should not be added as though they were alike.

Check Your Inputs

The percentage of capacity used comes from the airspace survey, so read how to calculate landfill airspace and remaining life before testing the liability. The free Landfill Closure Cost Model (Excel) computes the Statement 18 liability, next year's expense and the four funded ratios from your own figures.

Questions practitioners ask

How is the GASB 18 landfill closure liability calculated?

Multiply the estimated total current cost of closure and post-closure care by cumulative capacity used divided by total estimated capacity. That is the amount recognized to date. Outlays already made for closure reduce the reported liability.

Is the GASB 18 liability discounted?

No. It is based on current cost: what the work would cost at today's prices, re-estimated each year for inflation and changes in plans, conditions and approved regulations.

Does a trust fund larger than the liability mean the landfill is fully funded?

No. The liability reflects only the share of total cost attributed to capacity used so far. Adequacy should be judged against a funding target based on the expected closure date, cost inflation and investment earnings.

Does GASB Statement 83 apply to landfills?

No. Statement 83 on certain asset retirement obligations excludes landfill closure and post-closure care obligations, which remain under Statement 18.

Read the full handbook

This guide is drawn from The Landfill Financial Assurance Handbook, which follows the Alderwick County Solid Waste Authority through cost estimates, airspace, financial assurance mechanisms, accounting, a funding plan, post-closure risk and a proposed sale.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Landfill Closure Cost Model (Excel).

Illustrative figures computed by the book model; the Alderwick County Solid Waste Authority is fictional. Education only, not legal, tax, accounting, engineering, or investment advice.