Articles

How to estimate asphalt tons and price a paving job

Tons come from square feet, compacted inches and the weight of the mix; the price comes from tons, crew-days at their real cost, trucks, milling, overhead and profit, with a minimum for small jobs.

Tons equal square feet times compacted inches times about 12.2 pounds, divided by 2,000. In the worked case, 18,500 square feet at 2 inches is 226 tons, and the bid built line by line comes to $39,736, or $2.15 a square foot.

Worked in full in The Asphalt Paving Company Owner by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback

Free: the asphalt paving company model in Excel, with the Fairlow case: five job types with tons, prices and costs, contribution per crew-day, crews and overhead, the P&L, break-even and stress tests, cash month by month and two offers for the company.

From square feet to tons

Asphalt is bought by the ton, so every paving price starts with a tonnage. A common rule of thumb is that compacted asphalt weighs about 110 pounds per square yard per inch of thickness, about 12.2 pounds per square foot per inch. The real weight depends on the mix: the plant’s ticket decides.

Tons = square feet × compacted inches × 12.2 ÷ 2,000

Compacted thickness; add a waste allowance on commercial bids.
Job (Fairlow case)Square feetInchesTons
Residential driveway9002.513.7
Commercial overlay32,0001.5293
Full-depth patch1,400325.7
Bid example18,5002226

Example 1: a commercial bid built line by line

A property manager asks for a mill and overlay of 18,500 square feet at 2 inches: 226 tons, 235 with a 4% waste allowance.

Fairlow, fictional case; the asphalt price is a case assumption.
LineBasisAmount
Asphalt235 tons at $78.00$18,342
Tack coat18,500 sq ft at $0.04$740
Milling subcontract18,500 sq ft at $0.30$5,550
Paving crewone crew-day at its cost per production day$4,001
Hired trucks3 trucks, 10 hours at $105$3,150
Fuel and repairsone day$720
Overhead recoveryone paving day$2,975
Profit12% of cost and overhead$4,257
Price$168.98 a ton, $2.15 a sq ft$39,736

The crew is priced at its cost per production day, $4,001 in the case: the season’s crew cost divided by the days asphalt actually went down. Pricing the crew at its wages for the hours on the job forgets every rain day and travel day the crew was paid.

Example 2: per square foot, per ton and the job minimum

Fairlow prices driveways at $5.25 a square foot ($4,725 for 900 square feet) and commercial overlays at $150 a ton plus milling. A 300-square-foot patch at the driveway price would bill $1,575 but cost $1,688, with a quarter crew-day and the plant’s small-load fee. A job minimum of $2,400 turns it into $712 of contribution.

The trap: forgetting the trucks. On a commercial overlay the company’s own trucks cannot keep the paver fed; hired trucks at $105 an hour are a separate line, and too few of them stop the paver.

Sources

  1. U.S. Access Board, Guide to the ADA Standards, Chapter 5: Parking
  2. OSHA, 29 CFR 1926.1153, Respirable crystalline silica (construction)

Figures checked on 20 November 2026. Illustrative case assumptions, not market data, and not legal, tax, employment, insurance or safety advice. The company in the examples is fictional.

Questions readers ask

How many tons of asphalt do I need?

Multiply the square feet by the compacted thickness in inches and by the weight per square foot per inch (about 12.2 pounds as a rule of thumb), then divide by 2,000. Add an allowance for waste on commercial jobs, and use your plant's figure for the mix.

How do paving contractors price a job?

From the takeoff: tons of asphalt at the plant price, tack, base, milling, hired trucks, the crew at its cost per production day, fuel and repairs, then overhead and profit written separately. Small jobs carry a minimum charge.

Is asphalt priced per ton or per square foot?

Both are used. Homeowners usually get a price per square foot; commercial clients and general contractors often get a price per ton placed, which follows the thickness the lot really needs.

Why do small paving jobs cost so much per square foot?

Because the trip, set-up, cleanup and the plant's small-load fee do not shrink with the area. In the case a 300-square-foot patch costs $1,688 to do, more than the square-foot price would bill.

Read the whole book

This article is one calculation from The Asphalt Paving Company Owner, a practitioner’s guide to starting, buying, running and selling an asphalt paving and sealcoating company: takeoffs and tons, pricing per ton and per square foot, asphalt, trucking and milling, crews and overtime, equipment, commercial bids and driveways, weather, cash and valuation.