Articles

How much diesel does a data centre need for 48 hours of backup?

Size the tanks on the load the generators actually carry, cooling included, and the 48 hours turn into a logistics question as much as a storage one.

Backup fuel is facility load, not IT load, times the hours of autonomy times the engines' fuel burn per kWh. An illustrative 60 MW IT building at a 1.35 peak PUE puts 81 MW on its generators; at 0.26 litres per kWh it burns 21,060 litres an hour, so 48 hours of autonomy needs 1.01 million litres of diesel, about 267,075 US gallons. Beyond the tanks, staying on generators means 14.9 road tankers a day.

Worked in full in The Data Center Development Handbook by Julian R. Sterling, with every figure reproduced in a free workbook.See the book on Amazon →

The assumptions

All figures are illustrative. Specific fuel consumption, the litres a generator burns per kWh it produces, comes from each engine's data sheet and rises at part load.

Illustrative 60 MW building
InputValue
Critical IT load60 MW
Peak PUE, hot day, full load1.35
Autonomy required48 hours
Fuel burn at full load0.26 L per kWh
Fuel burn at half load0.29 L per kWh
Generator rating3.0 MW
Diesel price$1.10 per litre
Road tanker capacity34,000 litres

Forty-eight hours is a common design target in tenant specifications and lender technical reviews, not a universal rule; some sites are built to 24 hours, some to 72 or more.

Step 1: the load the generators carry

Facility load = IT load × peak PUE = 60 × 1.35 = 81 MW = 81,000 kW

Running generators = 81 / 3.0 = 27

The chillers, pumps, fans and UPS losses all move to backup with the servers. The design case is the hot day at full IT load, because that is when the grid is most likely to fail and the cooling works hardest.

Step 2: litres per hour and per 48 hours

Fuel per hour = 81,000 kW × 0.26 L per kWh = 21,060 litres (780 per generator)

Fuel per day = 21,060 × 24 = 505,440 litres

Fuel for 48 hours = 21,060 × 48 = 1,010,880 litres = 267,075 US gallons (at 3.785 litres per gallon)

Excel: =IT_MW*1000*PUE_peak*SFC*Hours

That is 16,848 litres per MW of IT load, or 37,440 litres per running generator, which is roughly the size of a large belly tank under each set. The fuel follows the load, not the engine count: spreading 81 MW over more generators changes the tank layout, not the litres.

Step 3: what the stock costs and what it buys

Fuel inventory = 1,010,880 × $1.10 = $1,111,968

Carrying cost at 8 per cent a year = $88,957

Tankers to keep running = 505,440 / 34,000 = 14.9 a day, one every 1.6 hours

The inventory is trivial beside a building that costs several hundred million dollars. What matters is the logistics: 29.7 tanker loads would be needed to refill the tanks after a 48 hour event, during a regional outage, when every hospital and telecom site is calling the same distributors. Fuel supply contracts with priority clauses, and fuel polishing to keep stored diesel usable, are part of the diligence, not an operational footnote.

What if the load or the hours change?

Real outages rarely hit at full design load. At half load the engines burn more per kWh, so fuel does not fall in proportion.

Diesel needed, million litres
Load, share of 81 MWL per kWh24 h48 h72 h96 h
50%0.2900.280.560.851.13
75%0.2750.400.801.201.60
100%0.2600.511.011.522.02

At half load the 48 hour figure is 55.8 per cent of the full-load figure, not 50, because of the part-load penalty. Moving to 72 hours of autonomy at full load needs 1,516,320 litres, $1.67m of fuel and half as much tank space again, which on a tight site competes with the generator yard for land.

A building sized on full load stores more hours than its name says on an ordinary day: a 48 hour tank lasts about 86 hours at 50 per cent load. Lenders and tenants specify the design case precisely so that the label means the same thing on the worst day.

The common mistake

Sizing autonomy on IT load. Forty-eight hours at 60 MW is 748,800 litres. At the 81 MW the building actually draws on a hot day, that lasts 35.6 hours: the tanks are 25.9 per cent short, which is exactly the PUE gap. The opposite error is sizing on installed nameplate. With one spare per block of five, the site has 33 generators and 99 MW of nameplate; 48 hours at nameplate is 1,235,520 litres, 22.2 per cent more than the load needs and $0.25m of extra stock, plus the tanks and the land to hold it. Spares are there for redundancy, not to run at the same time as the units they back up.

The same PUE that sets the fuel also caps how much IT load a grid connection supports, worked in how much leasable IT capacity a higher PUE costs. Where the generators run continuously rather than as backup, the economics change entirely, as in what on-site gas power costs per MWh.

Takeaway

The book's power and site work, with the underwrite of its 180 MW case, is in the free workbook for this case.

Questions readers ask

How much fuel does a 3 MW diesel generator burn per hour?

At an illustrative specific fuel consumption of 0.26 litres per kWh at full load, a 3.0 MW generator burns 780 litres an hour, about 18,720 litres a day. At half load consumption per kWh rises, to an illustrative 0.29, so the engine burns less fuel in total but less efficiently. Manufacturer data sheets give the curve for each engine.

Why do data centres store 48 hours of fuel rather than refuelling?

Because refuelling at full load is a logistics operation, not a phone call. The illustrative 60 MW building burns 505,440 litres a day: 14.9 road tankers of 34,000 litres, one every 1.6 hours, during the same event that caused the outage. Storage buys time for supply contracts with priority delivery to work.

Should backup fuel be sized on IT load or facility load?

On facility load. Cooling, UPS losses and lighting run on the generators too. Sizing 48 hours on the 60 MW IT load stores 748,800 litres, which lasts 35.6 hours at the 81 MW the site actually draws: a 25.9 per cent shortfall.

Read the whole case

This article is one calculation from The Data Center Development Handbook. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Also on this site

Reading guide: infrastructure, data centres and energy → · All 1340 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.