How Build-to-Suit Development Works

Four-party deal architecture, equity-first non-HVCRE construction loans, merchant exit vs. permanent refinance, and worked profit math on a 250,000 RSF industrial BTS.

In a build-to-suit commercial real estate project, a developer acquires entitled land, arranges construction financing, and constructs a custom facility for an identified corporate tenant that signs a binding long-term triple-net (NNN) lease before groundbreaking. Here is the complete end-to-end mechanics, capital stack, and profit math worked on a 250,000 RSF Class A industrial build-to-suit.

Worked in full in The Build-to-Suit Development Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

The Four-Party Architecture of Build-to-Suit Development

Unlike speculative real estate development (where a sponsor builds first and hopes tenants lease the space later), a build-to-suit (BTS) transaction eliminates absorption risk on Day 0 by synchronizing four counterparties in a single Month 0 closing:

Worked Example: Redwood Logistics Center (250,000 RSF Industrial BTS)

In The Build-to-Suit Development Handbook, every budget line, monthly draw, loan test, and exit waterfall is worked on one fictional project: Redwood Logistics Center (Parcel 4B), a 250,000 RSF Class A regional medical logistics facility developed by Alder Ridge Development Partners, LLC for Meridian Medical Supply Corp. (15-year absolute NNN lease at $10.80/RSF = $2,700,000 Year 1 NOI, 2.5 percent annual escalations):

Project MetricRedwood Logistics CenterBasis / Notes
Total Development Cost (TDC)$35,233,058 ($140.93/RSF)Land $5.4M, GMP $24.0M, Cont. $1.2M, Soft $2.16M, Fee $1.26M, Fin. $1.21M
Capital Stack (Equity-First)$12,600,000 Eq / $22,633,058 Debt64.2% LTC at 7.50% (clears $6.75M HVCRE floor by $5.85M)
Yield on Cost vs. Exit Cap7.66 percent vs. 6.00 percent166 bps development spread; 7.55% break-even cap rate
Merchant Exit (Month 21)$45,000,000 gross / $44,325,000 net$9,342,573 levered profit, 25.8% MoC, 1.74x EM, 41.4% IRR

Merchant Sale vs. Permanent Refinance Hold

Upon Substantial Completion at Month 18 and Rent Commencement at Month 19, the developer holds two clean exits. Selling to an institutional net lease buyer (Granitegate Net Lease Partners, LP) at Month 21 at a 6.00 percent cap rate crystallizes $9,342,573 of levered profit (41.4 percent IRR), while Granitegate earns a 7.63 percent unlevered / 9.34 percent levered 10-year IRR (2.08x EM) powered by 2.5 percent annual escalations. Alternatively, refinancing into a 10-year fixed permanent mortgage at 6.25 percent (30-year amort, DSCR-constrained at 1.30x = $28,109,808, 62.5 percent LTV) pays off the $22,633,058 construction loan, repatriates $5,195,652 tax-free, and leaves $7,404,348 of remaining equity earning an 8.42 percent Year 1 Cash-on-Cash yield.

Explore the exact spread math in build-to-suit Yield on Cost and development spread, review delivery penalties in build-to-suit lease commencement and delay risk, and download the unlocked free Build-to-Suit Development Model (Excel).

Questions practitioners ask

How does a build-to-suit developer make money?

A build-to-suit developer earns profit from the spread between Yield on Cost (Year 1 NNN NOI divided by Total Development Cost) and the market exit capitalization rate, plus a 3 to 4 percent development fee. On Redwood Logistics Center, a 7.66 percent Yield on Cost sold at a 6.00 percent cap rate creates $9,091,942 profit on sale ($9,342,573 total levered profit with seasoning carry) and a 41.4 percent levered IRR.

What is the difference between Fixed-Rent and Open-Book build-to-suit leases?

In a Fixed-Rent BTS, Year 1 base rent ($10.80/RSF) is locked upfront and the developer absorbs construction cost overruns. In an Open-Book (Cost-Indexed) BTS, Year 1 rent resets post-completion to Final Audited TDC multiplied by an agreed Target Yield on Cost, shifting cost-inflation risk to the tenant.

Does a build-to-suit lease go on the tenant's balance sheet during construction?

Under FASB ASC 842-40-55-5, a lessee avoids accounting ownership during construction so long as it does not control the asset under construction (developer owns the land, no mid-build purchase option, and the shell has alternative use). The tenant records a standard ROU asset and lease liability only at Lease Commencement.

Read the full handbook

This guide is drawn from The Build-to-Suit Development Handbook, following Redwood Logistics Center (Parcel 4B) from Month 0 land closing through Month 21 merchant exit and 10-year net lease buyer hold.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Build-to-Suit Development Model (Excel).

Illustrative figures computed by the book model; Redwood Logistics Center (Parcel 4B) and all named parties are fictional. Education only, not legal, accounting, tax, engineering, or investment advice.