Exact all-in Yield on Cost math, 166 bps development spread, break-even exit cap rate (7.55%), and Fixed-Rent vs. Open-Book cost-overrun sensitivities.
Yield on Cost (YoC) is the master feasibility ratio of build-to-suit real estate development: Stabilized Year 1 NNN NOI divided by all-in Total Development Cost. Here is how to calculate YoC without interest-reserve shortcuts, why a 150-plus basis point development spread is non-negotiable, and how to solve for your exact break-even exit cap rate.
Worked in full in The Build-to-Suit Development Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Institutional developers compute two versions of Yield on Cost on every build-to-suit pro forma, and both must include 100 percent of hard contingency, soft costs, and developer fee:
Year 1 Stabilized NOI / Total Development Cost (incl. Loan Fee & Cap. Interest)Year 1 Stabilized NOI / Unlevered Project CostAll-In YoC - Institutional Exit Cap RateIn The Build-to-Suit Development Handbook, Redwood Logistics Center generates $2,700,000 of Year 1 absolute NNN NOI (250,000 RSF at $10.80/RSF) on an all-in Total Development Cost of $35,233,058 ($34,020,000 unlevered cost + $234,000 loan origination fee + $979,058 equity-first capitalized construction interest). That produces an all-in 7.66 percent YoC (7.94 percent unlevered) against a 6.00 percent net lease exit cap rate - a 166 bps development spread.
Many developers assume their break-even exit cap rate equals their Yield on Cost (7.66 percent). That forgets selling costs (1.50 percent brokerage, legal, and transfer taxes = $675,000 on $45,000,000). Setting Net Sale Proceeds equal to Total Development Cost gives the exact break-even threshold:
Break-Even Exit Cap Rate = (NOI_Y1 x (1 - Selling_Cost_%)) / TDC = ($2,700,000 x 0.985) / $35,233,058 = 7.55 percent
Redwood Logistics Center therefore carries 155 bps of cap-rate cushion above its 6.00 percent base exit cap before losing a dollar of development cost:
| Exit Cap Rate | Gross Exit Price | Levered Net Profit | Levered IRR |
|---|---|---|---|
| 5.50 percent (-50 bps) | $49,090,909 | $13,372,118 | 57.0 percent |
| 6.00 percent (Base) | $45,000,000 | $9,342,573 | 41.4 percent |
| 6.50 percent (+50 bps) | $41,538,462 | $5,932,957 | 27.3 percent |
| 7.00 percent (+100 bps) | $38,571,429 | $3,010,430 | 14.3 percent |
Under a Fixed-Rent BTS lease, a +10.0 percent hard-cost overrun (+$2,400,000) lifts TDC to $37,752,960 (including incremental carry interest), compresses YoC by 51 bps from 7.66 percent to 7.15 percent, forces sponsor equity up from $12,600,000 to $14,352,960, and cuts levered IRR from 41.4 percent to 30.2 percent. Under an Open-Book Cost-Indexed BTS holding YoC at 7.66 percent, Year 1 rent resets from $10.80 to $11.57/RSF ($2,893,107 NOI), preserving a 43.0 percent IRR.
See the full project lifecycle in how build-to-suit development works, review delay sensitivities in build-to-suit lease commencement and delay risk, and run your own deal in the free Build-to-Suit Development Model (Excel).
Institutional developers generally target 125 to 175 basis points of Yield on Cost spread above the stabilized exit cap rate for investment-grade industrial build-to-suits, and 175 to 225 basis points for sub-investment-grade or specialized-TI facilities.
Yes. Institutional underwriting always includes the 3 to 4 percent Developer Fee, owner hard-cost contingency, loan origination fee, and S-curve capitalized construction interest inside Total Development Cost so Yield on Cost reflects true all-in basis.
Because brokerage, legal, and transfer selling costs (typically 1.50 percent) reduce net sale proceeds. At 7.66 percent YoC and 1.50 percent selling costs, break-even exit cap rate is 7.55 percent (11 bps below YoC).
This guide is drawn from The Build-to-Suit Development Handbook, following Redwood Logistics Center (Parcel 4B) from Month 0 land closing through Month 21 merchant exit and 10-year net lease buyer hold.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Build-to-Suit Development Model (Excel).
Illustrative figures computed by the book model; Redwood Logistics Center (Parcel 4B) and all named parties are fictional. Education only, not legal, accounting, tax, engineering, or investment advice.