Closure is paid after the mine stops earning, so it looks small in a discounted model. Escalation, the discount rate and the funding method move the answer.
A $90.0m closure estimate, escalated at 2.5% a year and paid in years 11 to 13, becomes $120.5m of cash and is worth $48.6m at an 8% discount rate. That cuts a $216.0m mine to $167.4m. Funding it with a cash trust over 10 years raises the cost to $66.8m of present value.
| Item | Value |
|---|---|
| Project | Initial capex $200.0m, then $62.0m of cash flow a year for 10 years |
| Cost of capital | 8.0% a year |
| Closure cost | $90.0m in today’s money, rising 2.5% a year |
| Closure spending | Years 11 to 13 after the start: 40%, 40% and 20% |
| Trust fund return | 3.0% a year if cash is set aside |
| Surety bond fee | 2.5% a year on a face amount equal to the escalated closure cost |
Before closure the project is worth -200.0 + 62.0 × 6.7101 = $216.0m at 8%, where 6.7101 is the 10-year annuity factor.
Year 11: 90.0 × 1.02511 × 40% = $47.2m
Year 12: 90.0 × 1.02512 × 40% = $48.4m
Year 13: 90.0 × 1.02513 × 20% = $24.8m
Total paid = $120.5m, 33.8% more than the $90.0m estimate in today’s money
PV at 8% = 47.2 ÷ 1.0811 + 48.4 ÷ 1.0812 + 24.8 ÷ 1.0813 = $48.6m
Project value after closure = 216.0 − 48.6 = $167.4m, a cut of 22.5%
Excel, yearly cash flows in B6:N6 (years 1 to 13): =NPV(0.08,B6:N6)
Closure is paid after the mine stops earning, so its present value is 40.4% of the amount paid, and the mine still carries a value of $167.4m.
| Discount rate | PV of closure, $m | Mine value after closure, $m |
|---|---|---|
| 8.0% | 48.6 | 167.4 |
| 5.0% | 67.7 | 148.3 |
| 3.0% | 85.0 | 131.0 |
At 3% the liability is $85.0m, 1.7 times its value at 8%. The project discount rate prices risky mine cash flows; the closure cost is close to a fixed obligation, which is why accounting and regulators discount it at a much lower rate.
Cash trust: the fund must hold 114.2 at year 10, so annual deposits at 3% are 114.2 ÷ 11.4639 = $9.96m, a present value at 8% of $66.8m
Surety bond: fees of 2.5% a year on a face of $92.2m in year 1 rising to $115.2m in year 10 have a present value of $17.1m, on top of the closure cost itself
| Method | Present value, $m | Mine value after closure, $m |
|---|---|---|
| Unfunded, paid in years 11 to 13 | 48.6 | 167.4 |
| Surety bond, closure paid later | 65.7 | 150.3 |
| Cash trust built over 10 years | 66.8 | 149.2 |
The trust costs $18.2m more than the unfunded case, because cash earning 3% sits in a fund while the mine’s own money is worth 8%. The bond costs $17.1m more and keeps the cash in the business. What the regulator accepts decides which is available.
| Estimate, today’s money | Paid in years 11 to 13, $m | PV at 8%, $m | Mine value after closure, $m |
|---|---|---|---|
| $90.0m | 120.5 | 48.6 | 167.4 |
| $135.0m | 180.7 | 72.9 | 143.1 |
| $180.0m | 240.9 | 97.2 | 118.8 |
Doubling the estimate to $180.0m cuts the mine to $118.8m. The model has no salvage value, no post-closure monitoring and no tax relief on the spending.
Escalate the estimate to the years it is paid and discount it. Here $90.0m becomes $120.5m paid in years 11 to 13, worth $48.6m at 8% and $85.0m at 3%.
In this case it takes 22.5% of the value, from $216.0m to $167.4m, even though it is paid after production ends.
Here yes: the bond fees cost $17.1m of present value against $18.2m of extra cost for the trust, because trust cash earns 3% while the mine’s capital costs 8%.
The free companion files for The Mining Finance Professional rebuild a fictional mining finance fund: a silver stream, a gold royalty and a lithium project loan, with all-in sustaining cost, resources and reserves, feasibility economics and a gold collar. The figures in this article use invented inputs and are not in them. No account and no email address.
Not on Amazon: 19 paperbacks by Julian R. Sterling on markets, funds and compliance, printed on demand and shipped worldwide. Browse the bookshop →
Reading guide: corporate finance, valuation and markets → · All 1908 articles →