Exact 30-year PSC vs. DBFOM NPV math at 4.50%: $14.0 million (2.7 percent) Base VfM, risk quantification, and the 3x3 sensitivity matrix.
Value for Money (VfM) analysis decides whether a courthouse, K-12 school bundle, or civic building belongs in a P3 or traditional public bonds. Here is the exact Public Sector Comparator (PSC) vs. DBFOM NPV math, discount-rate discipline, and sensitivity matrix showing where VfM flips negative.
Worked in full in The Social Infrastructure P3 Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Quantitative Value for Money compares the risk-adjusted 30-year Net Present Value (NPV) of traditional Design-Bid-Build procurement (the Public Sector Comparator, or PSC) against the DBFOM Shadow Bid or binding Best and Final Offer: VfM = Risk-Adjusted PSC (NPV) - DBFOM Proposal (NPV).
Following FHWA P3-VALUE and international Treasury standards, both streams must be discounted at the exact same public-sector borrowing rate (4.50 percent tax-exempt GO yield for AA+/Aa1 Chesapeake County) once project-specific diversifiable risks are explicitly quantified in expected cash flows. Discounting DBFOM payments at a higher private WACC artificially shrinks P3 costs and manufactures fake savings.
| Cost Component (30-Yr NPV @ 4.50%) | Risk-Adjusted PSC | DBFOM Proposal | Variance (PSC - DBFOM) |
|---|---|---|---|
| Upfront CapEx / County Milestone | $254.0 million | $120.0 million | +$134.0 million |
| Capital Availability Payment NPV (30 Yrs) | $0.0 million | $218.3 million | -$218.3 million |
| Routine O&M + Lifecycle NPV (2.50% CPI) | $165.0 million | $138.6 million | +$26.4 million |
| County P3 Procurement & Contract Mgmt | $0.0 million | $6.5 million | -$6.5 million |
| Quantified Transferable Risks | $68.1 million | $0.0 million | +$68.1 million |
| Competitive Neutrality (PV SPV Taxes) | $10.3 million | $0.0 million | +$10.3 million |
| Retained Risks (Shared Identically) | $12.0 million | $12.0 million | $0.0 million |
| Total Risk-Adjusted 30-Yr NPV | $509.3 million | $495.4 million | $14.0 million (2.7 percent) |
In The Social Infrastructure P3 Handbook, we never present a single-point VfM estimate without stress-testing its two dominant drivers. Testing Chesapeake County across three public discount rates (3.50%, 4.50%, 5.50%) and three risk-transfer multipliers (50%, 100%, 125%) exposes the exact breakeven boundary:
Compare delivery options in DBFOM for public buildings, check end-of-term asset protection in P3 handback requirements, and run your own building numbers in the free Public Building P3 Value for Money Model (Excel).
Both the risk-adjusted Public Sector Comparator (PSC) and the DBFOM Proposal cash flows should be discounted at the public authority's tax-exempt municipal borrowing rate (for example, 4.50 percent for an AA+ county) when project-specific risks are quantified directly in expected cash flows.
Competitive Neutrality removes tax and regulatory distortions between public and private delivery by adding the present value of corporate income taxes paid by the private P3 SPV ($10.3 million NPV in Chesapeake) back to the PSC baseline.
Risks that the public authority cannot efficiently transfer (such as extended force majeure, discriminatory changes in law, and utility tariff inflation) are included identically in both columns so decision-makers see total whole-life exposure while the identical values cancel out in the VfM variance.
This guide is drawn from The Social Infrastructure P3 Handbook, following the Chesapeake County Judicial Center (Chesapeake Civic Partners, LLC) through a complete 30-year social infrastructure P3 lifecycle.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Public Building P3 Value for Money Model (Excel).
Illustrative figures computed by the book model; Chesapeake County Judicial Center (Chesapeake Civic Partners, LLC) is fictional. Education only, not legal, tax, accounting, municipal advisory, or investment advice.