DBFOM for Public Buildings: Availability Payments, GASB 94, and 63-20 Financing

Worked $280M courthouse P3 architecture: $120M milestone payment, Taxable USPP vs. Tax-Exempt 63-20, GASB 94 APA liability, and S&P/Moody's credit ratios.

Courthouses, K-12 public schools, and civic buildings do not collect tolls. Under availability-payment DBFOM, a private consortium designs, builds, partially finances, and maintains the facility for 30 years. Here is how U.S. counties structure milestone payments, USPP vs. 63-20 debt, GASB 94 accounting, and credit ratings.

Worked in full in The Social Infrastructure P3 Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

How Availability-Payment DBFOM Works for Public Buildings

Traditional Design-Bid-Build (DBB) separates architectural design, low-bid construction, and 30-year maintenance into disconnected silos. Counties frequently absorb 10 to 20 percent construction overruns and then defer HVAC, roofing, and elevator renewals whenever tax revenues tighten. In an availability-payment Design-Build-Finance-Operate-Maintain (DBFOM) partnership (authorized under state statutes such as Virginia's PPEA Va. Code Ann. Section 56-575.1, Florida's Fla. Stat. Section 255.065, Maryland's Section 10A-101, and Indiana Code Section 5-23), the public authority retains 100 percent ownership and core public services while paying a monthly Unitary Availability Payment conditioned strictly on physical building uptime.

In The Social Infrastructure P3 Handbook, every structure is modeled on one fictional 385,000 GSF, 18-courtroom courthouse with a 950-space parking deck, the Chesapeake County Judicial Center (Chesapeake Civic Partners, LLC):

Delivery Structure (30-Yr NPV @ 4.50%)Total 30-Yr NPVSavings vs. Comparable PSCKey Trade-Off
Traditional DBB (Risk-Adjusted PSC)$509.3 million ($499.1 million ex-tax)BaselineLowest bond rate; high overrun & deferred-maint risk
Taxable USPP DBFOM ($120.0 million Milestone)$495.4 million$14.0 million (2.7%)$24.0 million private equity cushion; 0 IRS 141 limits
Tax-Exempt 63-20 Nonprofit Conduit (5.10%)$469.8 million$29.3 million (5.9%)Saves $25.6 million vs. USPP ($15.3 million whole-of-gov); Rev. Proc. 2017-13
Design-Build-Maintain (Public GO Bonds)$430.5 million$68.6 millionNo private financing spread; no equity at risk

Methodological note: Taxable USPP DBFOM is benchmarked against the $509.3 million PSC (which includes $10.3 million of Competitive Neutrality for SPV corporate taxes), whereas tax-exempt DBM and 63-20 are benchmarked apples-to-apples against the $499.1 million PSC excluding SPV corporate tax neutrality.

Why Milestone Payments and GASB 94 Reshape Modern U.S. Civic P3s

Because an AA+/Aa1 county issues 30-year tax-exempt GO bonds at 4.50 percent while private taxable U.S. Private Placement (USPP) notes price at 5.75 percent plus sponsor equity (13.1 percent IRR), financing 100 percent privately destroys Value for Money. Paying a $120.0 million Substantial Completion Milestone Payment (42.9 percent of $280.0 million Total Project Cost) using County GO bonds slashes private capital to $160.0 million ($136.0 million USPP debt over 28 years with a 2-year debt tail + $24.0 million equity), keeping Minimum DSCR at 1.17x (Year 1 DSCR 1.35x).

Crucially, DBFOM is no longer off-balance-sheet. Under GASB Statement No. 94 (effective for fiscal years beginning after June 15, 2022), Chesapeake County records a $218.3 million Availability Payment Arrangement (APA) liability and a $338.3 million capital asset at Substantial Completion. S&P Global Ratings adds the full Capital AP NPV to County direct debt (lifting Debt-to-GF Revenue from 77.4 percent to 132.0 percent), while Moody's and Fitch cap the recognized liability at underlying senior project debt (118.7 percent).

Explore the full NPV math in Value for Money analysis for P3s, review Year 30 protection in P3 handback requirements, and download the free Public Building P3 Value for Money Model (Excel).

Questions practitioners ask

How is a DBFOM public building paid for if it has no tolls?

The public authority pays a monthly Unitary Availability Payment from its operating budget (subject to annual appropriation), split into a fixed unindexed Capital Component and CPI-indexed Routine O&M and Lifecycle components, reduced automatically if spaces or MEP systems fall below Output Specifications.

Are social infrastructure P3s off-balance-sheet under GASB 94?

No. GASB Statement No. 94 requires governments to record a capital asset and a long-term financed-purchase APA liability equal to the present value of capital-related availability payments, and S&P, Moody's, and Fitch all count availability payment obligations in municipal debt ratios.

When does a Tax-Exempt 63-20 nonprofit conduit beat Taxable USPP DBFOM?

A 63-20 conduit can save roughly 5 percent in total NPV ($25.6 million on a $280 million courthouse) through tax-exempt municipal yields, provided the building is 100 percent governmental use and all O&M agreements comply strictly with IRC Section 141 and IRS Revenue Procedure 2017-13 safe harbors.

Read the full handbook

This guide is drawn from The Social Infrastructure P3 Handbook, following the Chesapeake County Judicial Center (Chesapeake Civic Partners, LLC) through a complete 30-year social infrastructure P3 lifecycle.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Public Building P3 Value for Money Model (Excel).

Illustrative figures computed by the book model; Chesapeake County Judicial Center (Chesapeake Civic Partners, LLC) is fictional. Education only, not legal, tax, accounting, municipal advisory, or investment advice.