FERC's October 2024 two-model DCF + CAPM ROE methodology, the 50 bps RTO adder, 100% CWIP vs. AFUDC, and the zone cap.
Following the D.C. Circuit's vacatur of Opinion No. 569-A and FERC's October 2024 Order on Remand, federal transmission Base ROE is set by an exclusive two-model framework equally weighting DCF and CAPM. On top of Base ROE, FPA Section 219 and Order No. 679 unlock the 50-basis-point RTO participation adder, 100 percent CWIP in Rate Base, and Abandoned Plant recovery.
Worked in full in The Electric Transmission Investment Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Under Federal Power Act Sections 205 and 206, every transmission Return on Equity (ROE) must satisfy the Supreme Court's Bluefield and Hope capital-attraction standard. After years of litigation in the MISO Transmission Owners ROE proceedings, the D.C. Circuit vacated FERC's three-model Opinion No. 569-A in August 2022 for reintroducing the Risk Premium model without reasoned explanation. In its October 17, 2024 Order on Remand, FERC permanently stripped the Risk Premium model and established an exclusive two-model ROE methodology equally weighting:
Pursuant to FPA Section 219 (16 U.S.C. 824s) and FERC Order No. 679 (18 CFR 35.35), transmission developers can petition for ROE and non-ROE incentives by passing the reliability/congestion threshold and the Order No. 679-A nexus test. Critically, Section 219(d) caps total All-In ROE at the top of the composite zone of reasonableness.
In The Electric Transmission Investment Handbook, Alder Ridge Transmission pairs a 10.00 percent Base ROE with the +50 bps RTO Participation Adder for a 10.50 percent All-In ROE (cleanly below the 11.40 percent composite zone ceiling), plus 100 percent CWIP in Rate Base and 100 percent Abandoned Plant recovery:
| Incentive / Sensitivity | Year 1 ATRR Impact | 43-Year Equity IRR Impact |
|---|---|---|
| Base Case (10.50% All-In ROE + 100% CWIP) | $61,520,668 | 11.08 percent OpCo IRR |
| Loss of 50 bps RTO Adder (10.00% ROE) | -$1,457,363 ($60,063,305) | -52 bps (~10.56%) |
| Traditional AFUDC (No CWIP Incentive) | +$6,441,630 ($67,962,298) | -48 bps (10.60%) |
| Year 5 Section 206 Cut to 9.50% ROE | -$2.48M in Y5 (declining with Rate Base) | -51 bps (10.56%) |
Although consumer advocates often challenge CWIP in rate base, the 43-year math in Alder Ridge proves CWIP saves customers $109,735,605 in nominal dollars ($1,640,676,503 vs. $1,750,412,108) and avoids a +$6,441,630 Year 1 rate shock by preventing $46,536,006 of non-cash AFUDC from compounding into COD Gross Plant ($446,536,006 vs. $400,000,000), while delivering $55,188,000 of live construction cash flow that keeps construction debt investment grade.
See how FERC transmission formula rates work, walk through the full transmission revenue requirement (ATRR) calculation, and download the free Transmission Revenue Requirement Model (Excel).
Following the D.C. Circuit's 2022 remand and FERC's October 2024 Order on Remand, FERC uses a two-model methodology equally weighting the two-step DCF model and the CAPM, excluding the Risk Premium model.
No. Under FPA Section 219(d), total ROE (Base ROE plus all approved ROE incentive adders) is strictly capped at the top of the composite zone of reasonableness.
On Alder Ridge's $397,462,500 Year 1 Rate Base with 55.0 percent equity and a 25.0 percent composite tax rate, every 50 bps of ROE shifts Year 1 ATRR by exactly $1,457,363.
This guide is drawn from The Electric Transmission Investment Handbook, following Alder Ridge Transmission, LLC across the full 43-year lifecycle of a FERC-regulated 345 kV corridor.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Transmission Revenue Requirement Model (Excel).
Illustrative figures computed by the book model; Alder Ridge Transmission, LLC is fictional. Education only, not legal, regulatory, tax, engineering, or investment advice.