Articles

Schedule of Values Explained: Auditing AIA G703 and Catching Front-Loading

How to structure a 10-to-20 division Schedule of Values, run four quantitative front-loading tests before Draw #1, and police stored materials roll-off.

A Schedule of Values (AIA G703) divides a construction contract into trade line items that govern every monthly progress wire. Auditing early-trade shares against executed subcontracts before closing catches hidden front-loading before a lender unknowingly finances a contractor's working capital.

Worked in full in The Construction Draw Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

What Is a Schedule of Values (AIA A201 Section 9.2 & G703)?

Under AIA Document A201-2017 Section 9.2, the general contractor must submit a Schedule of Values (SOV) allocating the entire Contract Sum to portions of the work before the first Application for Payment. Mounted on AIA Document G703 (Continuation Sheet), the SOV tracks Scheduled Value (Col. C), Previous Work (Col. D), Work This Period (Col. E), Materials Presently Stored (Col. F), Total Completed and Stored (Col. G), Balance to Finish (Col. H), and Retainage (Col. I).

In The Construction Draw Handbook, Alderbrook Commons' $26,000,000 Base GMP is mapped cleanly across 10 CSI trade divisions, isolating General Conditions ($2,200,000, 8.5 percent) and Contractor Fee & Insurance ($1,200,000, 4.6 percent) so both bill strictly pro rata with physical trade progress.

How Front-Loading Hides Inside a Clean Total

Front-loading inflates early-sequence trades (General Conditions, Sitework, Concrete) while starving late-sequence finishing trades (Interior Finishes, Elevators, Landscaping) so the bottom line still equals $26,000,000. On Alderbrook Commons, the inspecting consultant caught a $1,200,000 pre-closing front-load before Draw #1:

Trade DivisionDraft GC SOVAudited Approved SOVHidden Distortion
Div 01 General Conditions$2,850,000$2,200,000+$650,000 inflated
Div 02 Sitework & Utilities$2,950,000$2,400,000+$550,000 inflated
Div 07 Interior Finishes$1,700,000$2,600,000-$900,000 starved
Div 08 Elevators$500,000$800,000-$300,000 starved

Had the lender missed that distortion, it would have advanced $1,080,000 of excess unsecured cash by Month 5 while leaving finishing trades $1,200,000 underfunded if the contractor defaulted mid-build.

Four Quantitative Tests to Audit Any SOV

  1. Subcontract Cross-Check: Match every major SOV division directly against signed subcontracts and winning trade bids.
  2. Early-Trade Share Benchmark: Flag General Conditions above 9.5 percent or combined finishing trades (Finishes + Elevators + Landscaping) below 11.0 percent on mid-rise multifamily builds.
  3. Stored Materials & Column F Roll-Off: Require Bills of Sale, bonded segregated storage, photo verification, and named-insured property coverage for off-site goods (AIA A201 Section 9.3.2). At Draw #9 of Alderbrook Commons, enforcing this rule disallowed $250,000 of undocumented off-site plumbing fixtures alongside $320,000 of overbilled framing ($570,000 total inspector cut).
  4. Append Change Orders as New Rows: Never overwrite original Scheduled Values. Append approved Change Orders (such as Alderbrook's $2,100,000 Month 9 COs) as numbered rows below Division 10 to preserve the original baseline.

Build your own audited G703 engine using the free Construction Draw Tracker Template (Excel), and read our guides on the construction loan draw process and the construction loan-in-balance test.

Read the full handbook

This guide is drawn from The Construction Draw Handbook, following Alderbrook Commons from closing budget and equity-first exhaustion through Draw #9 balancing cure, retainage step-down, and permanent takeout.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Construction Draw Tracker Template (Excel).

Questions practitioners ask

Why is front-loading a Schedule of Values dangerous for construction lenders?

Front-loading shifts dollars into early trades so the contractor collects excess cash early in the build. If the contractor defaults mid-project, the remaining undisbursed loan funds are insufficient to pay a replacement contractor to finish the starved late-stage trades.

How many line items should a commercial construction Schedule of Values have?

For a mid-size commercial or multifamily project, 10 to 20 CSI MasterFormat-aligned trade divisions on the lender's Master SOV (backed by the GC's detailed subcontract ledger) give clean inspection visibility without clerical bloat.

How should approved Change Orders appear on AIA G703?

Never overwrite original Scheduled Values. Append each executed Change Order as a separate numbered row at the bottom of the G703 Continuation Sheet so original trade budgets remain intact for variance tracking.

What happens to G703 Column F stored materials when they are installed?

When funded stored materials are physically installed, their dollar value must be removed from Column F (Materials Presently Stored) as it moves into Column E (Work Completed This Period) so the lender never pays twice for the same materials.