Construction Loan Draw Process: 7 Exhibits, AIA G702 Math, and 5-Day Funding

How commercial construction lenders and developers standardize monthly draw packages, verify equity-first draws, pair lien waivers, and cut turnaround from 14 to 5 business days.

A construction loan does not fail at the credit committee; it fails at the draw desk when uninspected billing, missing unconditional lien waivers, or unverified stored materials drain the commitment before the building is complete. A standardized 7-exhibit package paired with Day 0 pencil draws cuts monthly turnaround from 14 business days to 5 business days while keeping lender lien priority intact.

Worked in full in The Construction Draw Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

How a Commercial Construction Draw Actually Moves Cash

Unlike a permanent mortgage funded in one lump sum at closing, a commercial construction loan disburses incrementally over 12 to 24 months as labor and materials convert into real property collateral. Every monthly draw sits at the intersection of five controls: equity-first verification, AIA G702/G703 arithmetic, physical field inspection, forward Loan-in-Balance testing, and title date-down endorsements (ALTA 33-06).

In The Construction Draw Handbook, every formula, retainage step-down, and balancing cure is worked on one fictional 144-unit mid-rise multifamily development, Alderbrook Commons ($40,000,000 initial total cost: $14,000,000 sponsor equity at 35.0 percent plus a $26,000,000 senior construction loan at 65.0 percent LTC and 52.0 percent As-Completed LTV against $50,000,000 appraised value, clearing the 15.0 percent HVCRE threshold at 28.0 percent).

The 5-Business-Day Institutional Draw Calendar

Unstandardized draw desks average 14 business days per draw because of fragmented emails and post-submission inspector disputes. High-performing banks and developers cut turnaround by 64.3 percent to 5 business days using a fixed monthly cadence:

Business DayMilestonePrimary Owner
Day 0 (25th)On-site pencil draw walkthrough to agree physical % completeGC, Developer & Inspector
Day 1 (1st)Complete 7-exhibit draw package upload (12:00 p.m. hard gate)Borrower / Project Acct
Day 2Independent Field Inspection & Cost-to-Complete ReportInspecting Consultant
Day 3G702/G703 tie-out, soft-cost audit, waivers & Loan-in-Balance testLoan Administrator
Day 4Clean ALTA 33-06 date-down commitment & Loan Officer sign-offTitle Escrow & Officer
Day 5Senior loan wire released by 11:00 a.m. & title escrow disbursementLender & Title Company

Worked Example: Draw #5 (First Senior Loan Advance)

Under equity-first funding, Alderbrook Development Partners deployed 100 percent of its $14,000,000 equity during Months 0 to 4 ($5,000,000 land, $6,120,000 net hard costs after 10.0 percent retainage of $680,000, and $2,880,000 soft costs). At Draw #5, the general contractor billed $2,200,000 of new physical work plus $400,000 of verified stored materials ($9,400,000 cumulative completed and stored = 36.2 percent of the $26,000,000 base GMP):

The Golden Lagging Lien Waiver Rule & ALTA 33-06

Before releasing the $2,580,000 wire, the draw desk pairs Current Conditional Progress Waivers for Draw #5 with Prior Unconditional Progress Waivers for Draw #4 (proving last month's cash reached downstream subcontractors), using mandatory state statutory forms (such as California Civil Code Sections 8132-8138 or Texas Property Code Section 53.284), backed by a clean ALTA 33-06 Disbursement Endorsement advancing title coverage.

Next, learn how to run a Schedule of Values (AIA G703) audit, master the construction loan-in-balance test, and download the unlocked free Construction Draw Tracker Template (Excel).

Read the full handbook

This guide is drawn from The Construction Draw Handbook, following Alderbrook Commons from closing budget and equity-first exhaustion through Draw #9 balancing cure, retainage step-down, and permanent takeout.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Construction Draw Tracker Template (Excel).

Questions practitioners ask

How long should a commercial construction loan draw take to fund?

A disciplined draw desk using Day 0 on-site pencil draws, a hard Day 1 7-exhibit intake gate, and parallel title/inspection reviews funds routine monthly draws in 5 business days rather than the 14-day industry average.

Why do construction lenders require equity-first funding?

Equity-first funding ensures 100 percent of sponsor equity is verified and invested in project costs before debt advances, protecting lender collateral and satisfying the 15.0 percent HVCRE contributed capital exemption under 12 CFR Section 3.2.

What is the difference between conditional and unconditional lien waivers on a draw?

Conditional progress waivers take effect only when the current draw clears and are submitted with Draw #N; unconditional progress waivers are irrevocable and are collected on a one-draw lag for Draw #(N-1) to prove prior funds reached subcontractors.

What does an ALTA 33-06 Disbursement Endorsement do?

Issued after a monthly public-records date-down search, ALTA 33-06 advances the title policy's Date of Coverage, records the current and cumulative loan disbursements, and confirms zero intervening mechanics' liens on Schedule B.