Why ERP standard cost sheets create an overhead death spiral under FASB ASC 330, how to apply the Actionability Test, and how to price opportunity cost.
In a make-or-buy decision, only future cash flows that differ between making and buying are relevant. Comparing a fully absorbed ERP standard cost against a vendor quote includes unavoidable plant overhead that remains on your income statement and triggers an overhead death spiral under FASB ASC Topic 330.
Worked in full in The Make-or-Buy Decision Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
Under U.S. GAAP (FASB ASC Topic 330), manufacturers must allocate fixed production overhead (factory rent, property taxes, general utilities, plant leadership, ERP licenses) into inventory standard costs based on normal capacity. That rule produces accurate financial statements, but it breaks make-or-buy decisions.
In The Make-or-Buy Decision Handbook, Kestrel Precision Controls' ERP system prints a $74.00 per unit ($4,440,000 per year) standard cost for its Series-400 Hydraulic Manifold Block (60,000 units/year). When Domestic CM quotes $61.00 per unit ($3,660,000 per year), a naive comparison claims $13.00/unit ($780,000/year) in savings. Yet dissecting the ERP cost sheet reveals the cash reality:
| Cost Layer | Per Unit | Annual (60,000 u) | Relevant to Make-or-Buy? |
|---|---|---|---|
| Direct Materials, Labor & VOH | $45.00 | $2,700,000 | YES (100% variable cash) |
| Avoidable Direct Fixed Overhead | $9.00 | $540,000 | YES (dedicated cell costs) |
| Internal COPQ (0.8% scrap/rework, added outside $74.00 ERP sheet) | $1.00 | $60,000 | YES (symmetrical quality cost) |
| Unavoidable Allocated Plant OH | $20.00 | $1,200,000 | NO (remains if outsourced) |
| ERP Absorbed Standard Cost (excl. COPQ) | $74.00 | $4,440,000 | Misleading GAAP book rate |
| Relevant Make Operating Cost (YES rows) | $55.00 | $3,300,000 | True cash baseline for Make-or-Buy |
Because Kestrel must still write the $1,200,000 annual rent and plant-overhead check if the Series-400 cell sits empty, paying Domestic CM $3,660,000 raises total annual cash leaving the bank from $4,440,000 to $4,860,000 - a $420,000 annual cash loss on the invoice alone before adding freight ($90,000), supplier management ($120,000), and external defects ($90,000).
To prevent wishful thinking when classifying fixed costs, apply the Actionability Test: a fixed cost is avoidable only if leadership can name the exact headcount position, OEM machine service contract, or lease addendum cancelable within 90 days. At Kestrel, only four dedicated cell expenses (cell supervisor, CNC service contract, dedicated CMM fixtures, and cell material handling = $540,000/year) passed the test.
What happens to the remaining $1,200,000 of common plant overhead if management outsources anyway? Under FASB ASC 330-10-30, fixed production overhead must be allocated using normal capacity; when outsourcing leaves abnormal idle capacity, the unallocated fixed overhead cannot be capitalized into remaining inventory and must be expensed directly to Cost of Goods Sold - hitting quarterly gross margin immediately and triggering an overhead death spiral on remaining lines.
Test your own ERP cost sheet inside the free Make-or-Buy Decision Calculator, see the full four-option case in worked make-or-buy analysis example, and audit external quotes in contract manufacturing total landed cost comparison.
Relevant costs include direct materials, truly variable direct labor, variable overhead, avoidable direct fixed costs that terminate within 90 days, future CapEx and salvage values, expected COPQ, working capital shifts, and any verified opportunity cost of constrained capacity. Unavoidable allocated plant overhead and historical sunk costs are excluded.
Yes. Avoidable direct fixed costs tied exclusively to the part or machining cell (such as a dedicated cell supervisor or OEM machine maintenance contract) are 100 percent relevant because they disappear if you outsource. Common plant-wide fixed costs (building lease, property taxes, ERP) are irrelevant unless you physically close or sublease the space.
Under FASB ASC 330-10-30, fixed production overhead must be allocated based on normal capacity. If outsourcing creates abnormal idle capacity in the plant, the unallocated fixed overhead cannot be added to remaining inventory costs and must be expensed immediately as a period cost in Cost of Goods Sold.
This guide is drawn from The Make-or-Buy Decision Handbook, following Kestrel Precision Controls, Inc. across four sourcing options, constrained capacity, 70/30 hybrid peak shaving, and reshoring economics.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Make-or-Buy Decision Calculator (Excel).
Illustrative figures computed by the book model; Kestrel Precision Controls, Inc. is fictional. Education only, not legal, tax, customs, or external accounting advice.