Articles

P3 Stipends, Bid Costs, and Go/No-Go Expected Value Math

Phase-by-phase pursuit budgeting ($10.60M pre-award), 23 CFR 636.113 stipends ($2.50M), Gate 1 and Gate 2 break-even win probabilities, and IP retention.

Preparing a binding U.S. P3 proposal on an $850 million corridor costs $10.60 million in pre-award cash, while the public agency's stipend typically reimburses less than a quarter of that burn. Here is the exact Gate 1 and Gate 2 Expected Value math, break-even win probability, and Stipend vs. IP retention rule.

Worked in full in The P3 Bid Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

What a U.S. P3 Bid Actually Costs by Phase

Bidding on a major U.S. P3 is binary, unlevered equity capital allocation. In The P3 Bid Handbook, Appalachian Mobility Partners budgets $10.60 million in pre-award third-party pursuit costs across Phases 1 through 4 (1.25 percent of $850.0 million Total Uses), plus $3.40 million in Phase 5 closing costs incurred only if AMP wins (totaling $14.00 million, reimbursed 100 percent at Financial Close):

Pursuit Phase / Decision MetricAMP Base CaseShare / Impact
Phases 1 & 2: Pre-RFQ + RFQ/SOQ$1.20 million100% lost if not shortlisted ($0 stipend)
Phases 3 & 4: RFP Design, ATCs & Committed Finance$9.40 million88.7% of pre-award cash burn
Total Pre-Award Bid Cost (Phases 1 to 4)$10.60 million1.25 percent of $850.0 million Uses
PDOT Optional Stipend (23 CFR 636.113)$2.50 millionCovers 23.6 percent of pre-award spend
Net Loss if Shortlisted & Unsuccessful$8.10 millionGranite Ridge 55% = $4.46 million

Gate 1 (Pre-RFQ) and Gate 2 (Post-Shortlist) Expected Value Math

At AMP's bid Annual MAP ($73.65 million), 30-year equity cash flows ($12.20 million/yr) deliver an 11.50 percent Equity IRR and an Equity NPV of $17.94 million at AMP's 9.50 percent hurdle rate. Adding AMP's $4.50 million Financial Close development fee sets the economic Value of Winning (V_win) at $22.44 million.

When to Decline a P3 Stipend to Keep Your IP

Under 23 CFR Section 636.113(b)-(c), stipend acceptance is optional. A losing consortium should decline a $2.50 million stipend only when the expected present value of reusing a genuinely proprietary, repeatable ATC across future corridors exceeds $2.50 million. Inside the Consortium Teaming Agreement, include a DBJV Stipend Buy-Out Clause allowing the contractor to decline the stipend only if it pays equity partners their pro-rata share of the forgone cash.

Model your own corridor immediately in the free P3 Bid Cost and Go/No-Go Excel Model, review the full U.S. P3 procurement process, and see how ATCs win bids in Alternative Technical Concepts (ATCs) in P3 bidding.

Questions practitioners ask

What percentage of project CapEx does a U.S. P3 bid typically cost?

Pre-award pursuit costs on major U.S. transportation P3s typically run 1.0 to 1.5 percent of total project uses (roughly $8 million to $15 million on an $800 million to $1.2 billion corridor), with nearly 90 percent spent after shortlisting.

How much of a consortium's bid cost does a P3 stipend reimburse?

State DOT stipends under 23 CFR Sections 636.112 and 636.113 typically cover only 20 to 30 percent of total pre-award bid costs ($2.50 million on a $10.60 million pursuit = 23.6 percent), leaving losing shortlisted teams with a substantial net cash write-off.

What is the exact relationship between Gate 1 and Gate 2 Expected Value?

Gate 1 EV equals P(Shortlist) multiplied by Gate 2 EV, minus cumulative RFQ sunk cost: (0.70 x $4,705,082) - $1,200,000 = $2,093,558. This exact identity is verified automatically on the Controls tab of the companion Excel template.

Read the full handbook

This guide is drawn from The P3 Bid Handbook, following Appalachian Mobility Partners, LLC from Go/No-Go through Financial Close on an $850.0 million Availability Payment DBFOM.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: P3 Bid Cost & Go/No-Go Model (Excel).

Illustrative figures computed by the book model; Appalachian Mobility Partners, LLC is fictional. Education only, not legal, tax, engineering, or investment advice.