Every closure number starts from hectares and unit rates. What changes between the owner's budget and the regulator's figure is the footprint, the rates and the loading. Here is the build on a worked gold mine.
A closure cost estimate looks like an engineering document, but it is the root of every financial number that follows: the bond the regulator demands, the liability in the accounts and the deduction a buyer takes off the price. This guide builds one step by step on a fictional open-pit gold mine, the Drumlarne Mine, and shows where the big differences come from.
Worked in full in The Mine Closure and Reclamation Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
An estimate starts with what has to be reclaimed. At Drumlarne that is 640 hectares today, split between waste rock dumps (300 hectares), a heap leach pad (140), a tailings storage facility (120) and roads, ponds and yards (80). By the end of mining in Year 12 the footprint grows to 840 hectares. Which of those footprints the estimate covers is the first decision, and it changes the answer more than any unit rate.
Each component gets a unit rate per hectare: regrading, cover, revegetation, drainage. Items that do not scale with area, such as demolishing the plant or building a water treatment plant, are lump sums.
| Component | Third-party rate per hectare | Owner rate per hectare |
|---|---|---|
| Waste rock dumps | $75,000 | $52,000 |
| Heap leach pad | $95,000 | $70,000 |
| Tailings storage facility | $120,000 | $96,000 |
| Roads, ponds and yards | $28,000 | $20,000 |
The two columns answer different questions. Third-party rates are what a contractor hired by the regulator would charge if the operator walked away. Owner rates are what the operator expects to spend doing the work with its own fleet and people. On the final footprint the owner's direct cost is 23.1% below the third-party figure.
Direct cost is only the start. A regulator's estimate adds mobilization (4%), engineering and design (6%), contractor overhead and profit (10%), agency administration (5%) and contingency (15%): 40% in total in the example. The owner adds its own engineering, team and contingency, 22% in total.
Contingency is not a margin. It covers uncertainty inside the defined scope. A regulator that later requires partial backfill of the pit, or a seepage collection system no one planned, is a change of scope, and no contingency percentage covers it.
Closure does not end with the earthworks. Drumlarne needs $0.5 million a year of monitoring for 30 years and water treatment of $1.2 million a year with no foreseeable end. The owner budgets thirty years of both, $51.0 million undiscounted. A regulator capitalizes them instead, which is the subject of why the bond, the ARO and the closure budget never match.
| Owner's budget | Regulator's works | |
|---|---|---|
| Footprint | Final (840 ha) | Largest in the next three years (711 ha) |
| Rates | Owner | Third-party |
| Direct cost ($ million) | 71.64 | 82.42 |
| Indirect costs | 22% | 40% |
| Works ($ million) | 87.4 | 115.4 |
The regulator's works on a smaller footprint come out higher than the owner's works on the final one, because rates and loading outweigh the extra hectares. Priced at third-party rates with the full loading, the final footprint would cost $130.4 million, 49.2% more than the owner's figure.
The free Mine Closure Cost and Bonding Model (Excel) builds both estimates from one table of components and rates and adds the assurance amount and the accounting obligation. For the cost of guaranteeing the result, read what reclamation bonding really costs a mining company. The full case is worked in The Mine Closure and Reclamation Finance Handbook.
Owner rates reflect the operator doing the work with its own equipment and staff during or just after operations. Third-party rates reflect a contractor hired by the regulator after the operator has gone, including mobilization and the contractor's overhead and profit. Regulators use third-party rates because financial assurance exists for the case in which the operator does not perform.
There is no single figure. It depends on the stage of the plan, the quality of the data and the rules of the regulator. The 15 percent in this guide is an illustration, not a benchmark. Contingency should cover uncertainty within the defined scope; changes of scope are addressed by scenarios.
Many regimes set the assurance on the disturbance expected before the next review, often a few years ahead, and recalculate it at each review. That keeps the amount close to the liability that would exist if the operator failed in that period.
This guide is drawn from The Mine Closure and Reclamation Finance Handbook, following Aldervane Mining Corp. and its Drumlarne gold mine from the closure plan to a sale offer, an early closure and the call on the assurance.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Mine Closure Cost and Bonding Model (Excel).
Illustrative figures computed by the book model; Aldervane Mining Corp. and every company named are fictional. Education only, not legal, tax, accounting, or investment advice.