Mine Closure: Why the Bond, the ARO and the Closure Budget Never Match

One closure plan produces three numbers: what the owner will spend, what the regulator requires to be guaranteed and what the balance sheet shows. Here is the reconciliation on a worked gold mine.

Ask what closing a mine will cost and three honest answers come back. They are not three estimates of the same thing. They answer three different questions, and most of the confusion in closure finance comes from using one where another belongs. This guide reconciles them on the fictional Drumlarne Mine.

Worked in full in The Mine Closure and Reclamation Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

The three numbers

NumberAmountQuestion it answers
Owner's closure budget$138.4 millionWhat will we spend, in today's dollars?
Financial assurance required$173.8 millionWhat must third parties guarantee?
Asset retirement obligation (US GAAP)$77.2 millionWhat is the obligation worth today?

The guarantee is more than twice the liability: the book obligation is 44.4% of the assurance. Anyone who reads the balance sheet to learn how much bonding capacity a mine consumes is reading the wrong document.

Difference 1: footprint

The owner budgets the final footprint, the one it will actually close. The regulator prices the largest disturbance expected before its next review. The accounting obligation covers only the disturbance that exists today and adds a new layer each year as the mine grows. Three footprints, three different areas.

Difference 2: rates and loading

The owner uses its own rates and a modest loading. The regulator uses third-party rates with mobilization, engineering, overhead, administration and contingency. The accounting estimate also uses third-party rates, because fair value is what a market participant would charge, but adds only the contractor's costs, then weights outcomes by probability and adds a market risk premium: a combined loading of 1.3388 times direct cost. The build is explained in how a mine closure cost estimate is built.

Difference 3: time

The owner's budget and the regulator's works are in today's dollars. The obligation is not. Its cash flows are inflated at 2.5% to the years they will be paid and discounted at the credit-adjusted risk-free rate, 6.8%. Closure works fall in Years 13 to 16, so discounting cuts them sharply: undiscounted and nominal, the obligation's cash flows total $1,009.5 million, and the obligation is 7.6% of that.

Difference 4: water

Treatment of $1.2 million a year with no end date is where the three numbers diverge most. The owner budgets thirty years. The regulator capitalizes it forever at a real rate of 2.5%, which adds $48.0 million to the assurance; at one point lower it would add $80.0 million. The accounts carry a hundred years of treatment discounted at 6.8%, where distant years count for almost nothing.

Difference 5: the accounting framework

The same cash flows discounted at a risk-free rate of 4.3%, as an IFRS-style measurement would broadly do, give $134.0 million: 1.74x the US GAAP figure, a difference of $56.8 million that has nothing to do with rock. Comparisons between companies reporting under different frameworks must adjust for it.

How to present the reconciliation

The free Mine Closure Cost and Bonding Model (Excel) produces all three from one set of inputs. The guarantee side, and what it costs in collateral and liquidity, is covered in what reclamation bonding really costs a mining company. The full case, from the closure plan to a sale of the mine and an insolvency, is in The Mine Closure and Reclamation Finance Handbook.

Questions practitioners ask

Why is a mine's asset retirement obligation lower than its reclamation bond?

The obligation covers only today's disturbance and is discounted from the years in which closure will be paid, often decades away. The bond covers a larger footprint at third-party rates in today's dollars and capitalizes perpetual costs at a low real rate. In the worked example the obligation is less than half the bond.

Does IFRS give a higher closure provision than US GAAP?

Often, because IFRS discounts at a rate that reflects the time value of money and the risks of the liability, generally close to a risk-free rate, while US GAAP uses the entity's credit-adjusted risk-free rate. The difference depends on rates, timing and the company's credit standing; it is not a fixed rule.

Which closure number should a lender use?

It depends on the question. Leverage comparisons usually start from the book liability, restated to a common discount rate. Recovery analysis should deduct the full third-party cost of closure. Liquidity analysis needs the assurance amount and the collateral behind it.

Read the full handbook

This guide is drawn from The Mine Closure and Reclamation Finance Handbook, following Aldervane Mining Corp. and its Drumlarne gold mine from the closure plan to a sale offer, an early closure and the call on the assurance.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Mine Closure Cost and Bonding Model (Excel).

Illustrative figures computed by the book model; Aldervane Mining Corp. and every company named are fictional. Education only, not legal, tax, accounting, or investment advice.