What It Costs to Develop a Manufactured Housing Community

The budget per site, by system, with off-site works, soft costs, the home program and the yield on cost it has to support.

A new manufactured housing community is a subdivision whose lots are never sold: streets, utilities and pads are built once and rented for decades. Here is how the development budget is built, site by site, what sits above the infrastructure, and the yield on cost the budget has to support.

Worked in full in The Manufactured Housing Community Development Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →

Budget per site, not per acre

A community earns lot rent per occupied home site, so the budget is read per site. This article follows the method used in The Manufactured Housing Community Development Handbook on its running case, Quarry Bend Village, a fictional community of 180 home sites on 46 acres, built in two phases of 100 and 80 sites. Every figure of the case is invented for illustration and computed by one model. The article is educational, not an appraisal, a cost estimate or investment advice.

Step 1: The on-site cost of one home site

The engineer's estimate is organized by system. Each line is the cost of that system divided by the number of sites it serves.

SystemPer siteAll 180 sites
Clearing and grading$3,900$702,000
Streets and curbs$7,400$1,332,000
Water distribution$3,300$594,000
Sanitary sewer$4,700$846,000
Storm drainage$3,100$558,000
Electric and gas$3,900$702,000
Home pad, foundation and connections$5,600$1,008,000
Landscaping, signs and lighting$1,600$288,000
On-site total$33,500$6,030,000

Streets and the home pad are the two largest lines. Both depend on design choices the developer controls: street width and section, site depth, and the foundation and anchoring system the installation standards and the local government require. A per-site figure from another project is a starting point for questions, not a budget.

Step 2: What sits above the sites

Three blocks are not per site at all. Off-site works ($650,000 in the case: a sewer extension of $420,000 and a road and turn lane of $230,000) are fixed by the location. Amenities, the clubhouse and the office ($560,000) are a choice. A hard cost contingency of 8% covers the rest of the unknowns. Together they take the hard cost to $7,819,200, or $43,440 per site.

Soft costs come next: engineering, surveys and permits ($430,000), utility connection fees of $3,200 per site ($576,000), legal and title, a development fee, pre-opening marketing, taxes and insurance during construction, and a soft cost contingency. They total $1,715,600, or 21.9% of the hard cost. Connection fees deserve a letter from each utility before the land closes; they are set locally and can change.

Land comes last in the order of thinking, though first in the order of spending: $1,242,000 ($6,900 per site), or $1,327,000 ($7,372 per site) with closing costs.

Step 3: The full budget

BlockAmountShare
Land and closing$1,327,0008.8%
Hard cost with contingency$7,819,20051.8%
Soft costs$1,715,60011.4%
Home program (rental homes and working capital)$3,580,80023.7%
Loan fee and reserves$640,0004.2%
Total budget$15,082,600100%

The line that surprises developers from other product types is the home program. A community fills only as fast as homes arrive on its sites, and in many markets the developer has to supply them: buying homes to sell, and owning some as rentals. The case budgets 36 community-owned rental homes at an average of $95,300 each. That capital earns home rent, not lot rent, so the book keeps it out of the yield on cost and reports two figures: a total cost of $83,792 per site and a core cost, without the home program, of $63,899 per site.

Step 4: The yield the budget has to support

At stabilization the case holds 171 occupied homes (95%) at an average lot rent of $705. Its stabilized, untrended net operating income is $972,677, which gives an untrended yield on the core budget of 8.46%. Against an exit capitalization rate of 6.50%, the development spread is 196 basis points before rent growth.

For context only: Northmarq reported a national average capitalization rate of about 6.5% for manufactured housing communities since the start of 2026 and a median price of $62,000 per site, up 19% from 2025 (Market Insights, Manufactured Housing, Q2 2026). The case's core cost of $63,899 per site sits close to that median price, which is exactly the comparison an investor will make: why build, at the risk of a lease-up, when existing sites trade at about the same price? The answer has to be a spread on cost, a location that existing communities do not serve, or both.

Two decisions that move the budget

Seven checks on a development budget

  1. Per-site costs come from an engineer's estimate or a bid, by system, not from a rule of thumb.
  2. Off-site works and connection fees are supported by letters from the utilities and the road authority.
  3. The contingency is stated separately for hard and soft costs.
  4. The home program is budgeted, and kept out of the yield on cost.
  5. Interest and operating reserves are sized on their own uses and tested on a slow fill (see modeling the lease-up of a new community).
  6. The yield on cost is stated untrended, with the trended figure beside it.
  7. Phase two is tested at the margin: its own cost against the income its sites add.

Enter your own system costs, fees and rents in the free Manufactured Housing Development Pro Forma (Excel) to see the cost per site, the yield on cost and the reserve your project needs. Existing communities with vacant sites follow very different arithmetic, covered in the economics of filling vacant sites.

Questions practitioners ask

What does it cost to build a manufactured home community per site?

It depends on the site, the utilities and the design. The case in the handbook is fictional: an on-site cost of $33,500 per site, a hard cost with off-site works and amenities of $43,440 per site, and a core budget of $63,899 per site including land, soft costs and financing. Real budgets come from an engineer's estimate and contractor bids.

Should the cost of the homes be included in the development budget?

It should be budgeted, because the community fills only as homes arrive, but kept separate from the yield on cost. Homes owned by the community earn home rent, are valued differently at the exit, and are limited by permanent lenders.

What yield on cost does a new community need?

Enough above the capitalization rate at which it could be sold to pay for the lease-up risk. In the fictional case the untrended yield on cost is 8.46% against an exit capitalization rate of 6.50%.

Read the full handbook

This guide is drawn from The Manufactured Housing Community Development Handbook, which follows Quarry Bend Village from the feasibility study through the infrastructure, the home program, the fill, financing and the exit.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Manufactured Housing Development Pro Forma (Excel).

Illustrative figures computed by the book model; Quarry Bend Village is fictional. Market figures are quoted from the sources named in the text. Education only, not legal, tax, accounting, or investment advice.