Homes per month, concessions, the operating breakeven, carry and the reserves, with a slow-fill test.
A new manufactured housing community fills one home at a time, and every month it is not full the construction loan keeps charging interest. Model the fill monthly, in whole homes, and it will show the one number annual columns hide: how long the project lives on its reserves.
Worked in full in The Manufactured Housing Community Development Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
An apartment lease-up is a marketing problem. A community lease-up is a home problem: a site is occupied only when a home has been built, delivered, set up, inspected and sold or rented to a household that can finance it. The pace is therefore counted in homes per month, and it is capped by what the developer's home program can deliver. This article follows the lease-up model of The Manufactured Housing Community Development Handbook on its fictional case, Quarry Bend Village. Every figure is an illustration computed by the book's model, not market data or advice.
The case opens its first 100 sites after a 12-month build. It assumes 4 homes a month in the first operating year, 5 in the second and 4 thereafter, counted in whole homes, with the second phase of 80 sites delivered in operating month 22, before the first phase is full.
| Operating month | Occupied homes | Occupancy | Community-owned rentals |
|---|---|---|---|
| 6 | 24 | 13.3% | 4 |
| 12 | 48 | 26.7% | 9 |
| 24 | 108 | 60.0% | 21 |
| 36 | 156 | 86.7% | 31 |
| 40 | 171 | 95.0% | 34 |
Stabilization at 95% arrives in operating month 40. Is four or five homes a month credible? Test it three ways: against the pool of qualified households in the market, against the recent sales of homes into comparable communities, and against what buyers can borrow. The Consumer Financial Protection Bureau found that about 42% of manufactured home purchase loans were chattel loans secured by the home alone, with a median rate of 8.6% against 4.9% for manufactured home mortgages, and that half of chattel applications were denied (HMDA data for 2019, published May 2021). When buyers cannot finance, the developer ends up renting homes or carrying them.
The average lot rent is $705, grown at 4% a year. The first 60 homes receive a move-in concession of $150 a month for 12 months, $108,000 in all. Rent growth and concessions both deserve local support: Northmarq reported an average community rent of $800 a month in the second quarter of 2026, up 6.4% in a year (Market Insights, Manufactured Housing, Q2 2026), but a new community's rent has to clear its own affordability test, built from the home price and the payment a buyer can obtain.
| Operating month | Effective gross income | Operating expenses | NOI | Rental home income | Interest | Net after interest |
|---|---|---|---|---|---|---|
| 1 | $2,412 | $26,276 | -$23,864 | $0 | $10,274 | -$33,698 |
| 12 | $28,948 | $29,312 | -$364 | $2,987 | $16,960 | -$14,007 |
| 24 | $82,515 | $45,687 | $36,828 | $7,248 | $47,538 | -$3,021 |
| 36 | $126,553 | $52,234 | $74,319 | $11,128 | $53,712 | $32,065 |
Net after interest equals NOI plus rental home net income and the small residual margin on homes sold ($110 per home, adding $330 to $440 in the months shown), less loan interest.
A community opens with most of its fixed costs on day one: a manager, insurance, common utilities, marketing and property tax. Net operating income turns positive only in operating month 15, with 63 homes occupied, and operations cover interest from operating month 25. Until then the gap is carry.
The case funds carry from two reserves inside the loan: an interest reserve of $380,000 and an operating reserve of $170,000. The model sizes each on its own use. To the sale, interest not covered by operations totals $309,818 and operating shortfalls $128,669, a carry need of $438,487 against $550,000 reserved.
Now slow the fill to three quarters of the planned pace. Stabilization moves from operating month 40 to 54, the carry need rises to $735,050, the reserves run out in operating month 20, and the sponsor has to add $185,050 of equity. The levered return falls from 14.5% to 3.9%. Nothing about the infrastructure changed. The pace did.
Run your own fill curve in the free Manufactured Housing Development Pro Forma (Excel): change the homes per month and watch the month in which the reserves run out. Budget assumptions are covered in what it costs to develop a manufactured housing community; existing communities with vacancies in the economics of filling vacant sites.
It depends on demand, the home program and buyer financing. In the handbook's fictional case, 180 sites stabilize at 95% in operating month 40 at four to five homes a month; at three quarters of that pace stabilization moves to month 54.
Because most operating costs start on opening day while income grows one home at a time. In the case, net operating income turns positive in operating month 15 and covers interest from month 25.
On a monthly model of the loan balance and of income during the fill, then tested at a slower pace. The case keeps a separate operating reserve, because operating shortfalls and uncovered interest are different uses.
This guide is drawn from The Manufactured Housing Community Development Handbook, which follows Quarry Bend Village from the feasibility study through the infrastructure, the home program, the fill, financing and the exit.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Manufactured Housing Development Pro Forma (Excel).
Illustrative figures computed by the book model; Quarry Bend Village is fictional. Market figures are quoted from the sources named in the text. Education only, not legal, tax, accounting, or investment advice.