The land floor, the budget in blocks, yield on total and net cost, financing, and the scenarios that break the plan.
A dead mall is priced on what the site can become. This guide walks through the feasibility arithmetic in order, with every figure taken from one worked case.
Worked in full in The Mall Redevelopment Handbook by Julian R. Sterling, with every case figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
A dead mall is not priced on income. The first number to compute is the land floor: what the site would be worth if every building were removed and the land sold in bulk, net of demolition, abatement, and selling costs. It is the value the owner can fall back on and the benchmark every building must beat.
In the fictional case of The Mall Redevelopment Handbook, the buyer of Larkmoor Mall pays $11,220,000 with closing costs and $7,200,000 more for control: a closed anchor box, a consent payment to the department store that remains, and lease buyouts. The cost of entry is $18,420,000. The land floor is $15,166,100, or 82.3 percent of that. The difference is what is at stake if the plan stops after control and before construction.
| Block | Case figure |
|---|---|
| Acquisition | $11,220,000 |
| Control (anchor box, consent, buyouts) | $7,200,000 |
| Hard costs (abatement, demolition, site work, buildings) | $57,330,000 |
| Soft costs, contingency, development fee | $8,599,500, $3,955,770, $2,096,558 |
| Tenant allowances and leasing commissions | $13,712,400 |
| Total cost | $104,114,228 |
| Less land sales (net) and public contribution | $23,560,600 |
| Net cost | $80,553,628 |
Always show both totals. Total cost is what must be financed. Net cost is what the finished center must justify. The offsets are less certain than the costs: a land sale can fail to close and a public payment can be late.
Yield on cost is stabilized net operating income divided by cost. In the case the stabilized income is $7,803,816.
| Cost definition | Yield | Spread over a 7.25 percent exit rate |
|---|---|---|
| Total cost | 7.50 percent | 25 basis points |
| Net cost | 9.69 percent | 244 basis points |
On total cost, the new retail barely earns more than the rate at which it would sell. The margin comes from the surplus land, sold for housing and a hotel, and from the city's share of the new streets. Of a value created of $27,085,209, only $3,524,609 comes from the center being worth more than everything spent on the site. That pattern is common, and it is why a feasibility study has to cover the whole site and not only the stores.
Nobody lends against a dead mall at acquisition. In the case, the purchase and the control costs are paid with equity. A redevelopment loan then funds 65 percent of development costs at 8.00 percent, and the lender takes 60 percent of net land sale proceeds as paydowns. The balance peaks at $47,564,888. Equity contributed is $40,886,469, the unlevered return is 13.7 percent, the levered return is 15.3 percent, and the equity multiple is 1.67x over five years.
| Scenario | Levered return |
|---|---|
| Base case | 15.3 percent |
| Hard costs 10 percent higher | 10.8 percent |
| Rents 10 percent lower | 9.0 percent |
| Land prices 25 percent lower | 13.3 percent |
| No public contribution | 9.7 percent |
| Openings one year late | 11.1 percent |
| Costs 10 percent higher and rents 10 percent lower | 3.9 percent |
A rent shortfall hurts more than a cost overrun of the same percentage, because lost income is capitalized. Two modest misses together remove most of the return. A sound plan therefore commits capital in stages, behind gates: the amended site agreement recorded, approvals in hand, anchor leases signed, and a guaranteed maximum price before the buildings start.
The free Mall Redevelopment Feasibility Model (Excel) follows this structure: inputs, a program of up to 20 components, a budget by year, cash flow with the loan, and returns, with controls that must read zero.
Not on its income. Buyers look at the land floor (the site cleared and sold in bulk, net of demolition and abatement), at the residual value under a redevelopment plan, and at who else could carry out that plan.
Stabilized net operating income divided by project cost. Ask which cost is used: total cost, or net cost after land sales and public contributions. The two can differ widely.
From a low purchase basis, from control of the site, from selling surplus land for other uses, and from the development spread on the new retail. In the worked case most of the value created comes from land sales and the public contribution.
This guide is drawn from The Mall Redevelopment Handbook, following Larkmoor Mall from the locked door to the sale.
Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks
Free download: Mall Redevelopment Feasibility Model (Excel).
Illustrative figures computed by the book model; Larkmoor Mall is fictional. Education only, not legal, tax, or investment advice.