The seller does not receive the headline price. It receives a probability-weighted price, later, with a fallback if the deal fails. Put every bid on that basis.
A seller has two bids for an infrastructure platform. Bid A is $520m, needs a regulatory approval that has a 75% chance and closes in 12 months. Bid B is $495m, is 95% likely and closes in 3 months. At the seller's 8% discount rate, A is worth $466.4m and B $483.1m. B is worth $16.7m more despite a $25m lower price.
| Item | Bid A | Bid B |
|---|---|---|
| Headline price | 520 | 495 |
| Chance the approval is granted | 75% | 95% |
| Months to completion | 12 | 3 |
| Reverse break fee if refused | 15 | 5 |
| Value of the platform if the sale fails | 440 | 440 |
| Seller's discount rate | 8% | 8% |
If the approval is refused, the seller keeps the platform, worth $440m at that date, and collects the break fee. The platform's cash flows during the wait go to the seller under either bid, so they are left out.
Expected value = chance × price + (1 − chance) × (fallback value + break fee)
Bid A = 0.75 × 520 + 0.25 × (440 + 15) = 390.00 + 113.75 = $503.75m
Bid B = 0.95 × 495 + 0.05 × (440 + 5) = 470.25 + 22.25 = $492.50m
Bid A = 503.75 ÷ 1.0812/12 = $466.4m
Bid B = 492.50 ÷ 1.083/12 = $483.1m
Excel: =(0.95*495+0.05*(440+5))/(1+8%)^(3/12)
| Measure | Bid A | Bid B |
|---|---|---|
| Headline price | 520.0 | 495.0 |
| Expected value at completion | 503.8 | 492.5 |
| Present value today | 466.4 | 483.1 |
| Present value if completion were certain | 481.5 | 485.6 |
Even if A were certain to be approved it would be worth $481.5m, below B's $483.1m, because a year of waiting costs 8% of the price. That is the point of the lower bid winning: A needs a higher price, not only a better chance.
Price A such that 0.75 × price + 0.25 × 455 = 483.1 × 1.08
Price A = (521.8 − 113.75) ÷ 0.75 = $544.0m, 24.0 above the actual bid
| Case | Bid A | Bid B | Higher |
|---|---|---|---|
| Base case | 466.4 | 483.1 | Bid B |
| Bid A approval chance 90% | 475.5 | 483.1 | Bid B |
| Discount rate 4% | 484.4 | 487.7 | Bid B |
| Bid B chance 85% | 466.4 | 478.2 | Bid B |
| Bid A chance 90% and discount rate 4% | 493.8 | 487.7 | Bid A |
One change is not enough to reverse the ranking, but two together are. At a 4% discount rate bid A needs a 80.3% chance of approval to match bid B, and at 8% it can never match it because even a certain approval leaves it behind.
Weight each price by its chance of completing, add the fallback value and break fee for the failure case, and discount over the time to completion. Here that gives $466.4m and $483.1m.
A year's wait at 8% costs about 7.4% of the price, and the 25% chance of refusal costs a further $16.3m in expected value. Bid B, at $495m, is worth $16.7m more.
$544.0m in this example, or $24.0m above the actual bid, at a 75% chance of approval.
The free companion files for The Infrastructure M&A Handbook rebuild the sale of a fictional tank storage platform, with two binding bids, regulatory delay cases, equity bridge and exit in live formulas. The two bids in this article are invented and are not in them. No account and no email address.
Not on Amazon: 19 paperbacks by Julian R. Sterling on markets, funds and compliance, printed on demand and shipped worldwide. Browse the bookshop →
Reading guide: infrastructure, data centres and energy → · All 1908 articles →