Fixed monthly facility fees, guaranteed specific power clauses, ground lease tails, embedded leases under ASC 842, and Chapter 11 rejection.
An on-site industrial gas contract is the primary collateral of an Air Separation Unit. Here is how take-or-pay facility fees, power pass-throughs, embedded leases, and bankruptcy rules actually work.
Worked in full in The Industrial Gas Plant Finance Handbook by Julian R. Sterling, with every figure reproduced in live Excel workbooks.Get the DRM-free PDF, $19.99 →
An Air Separation Unit is cryogenic steel bolted to concrete next to one customer's fence. Because dismantling and relocating a $120.0 million plant nets only a fraction of its cost, no supplier builds an on-site unit without a long-term Gas Supply Agreement (GSA). In the fictional Redcliff ASU case from The Industrial Gas Plant Finance Handbook, a 15-year GSA splits billing into three layers: a fixed monthly facility fee ($1,450,000/month, or $17,400,000/year, indexed at 2.5%), a variable non-power charge ($4.50/t GOX, $2.80/t GAN), and a 100 percent power pass-through at guaranteed specific power.
In a steel recession (the book's Weak state), the host mill drops from 92% to 70% utilization (below the 85% take-or-pay benchmark), merchant liquid volume falls to 70%, merchant prices drop 10 percent, and power rises $0.012/kWh. Because the $17,400,000 fixed facility fee remains 100 percent payable as long as the plant is available, on-site contribution barely moves (from $18,308,040 to $18,090,900). Total EBITDA drops only 17.1% to $13,857,120, keeping project debt service coverage solid at 1.22x.
Two clauses decide whether an on-site contract is truly bankable. First, the ground lease must outlast the GSA: Redcliff ASU sits on a 25-year ground lease (10 years beyond the 15-year GSA) with independent truck and substation access and a non-disturbance agreement from the host's mortgagees. Second, availability guarantees (typically 98.0 to 99.5 percent) are protected by on-site liquid oxygen and nitrogen backup vaporizers and strict exclusion of consequential damages.
Under U.S. GAAP (ASC 842-10-15, described in principle as verified in November 2026), a dedicated on-site ASU contract often contains an embedded lease because the cold box is an identified asset with no substantive substitution right. Fixed facility fees then enter the host customer's balance sheet as a Right-of-Use asset and Lease Liability. Adding substantial third-party merchant liquid capacity (242 TPD at Redcliff ASU) is one commercial lever that can affect whether the host controls substantially all economic benefits. For full lease-accounting mechanics, see The Lease Accounting Handbook.
A take-or-pay contract protects against recessions, not insolvency. Under 11 U.S.C. Section 365, a Chapter 11 debtor may reject an executory GSA under the business judgment standard, turning Redcliff ASU's $74,208,847 Year 6 termination fee into a general unsecured claim worth only $18,552,212 at an assumed 25% recovery. If the debtor keeps running temporarily in bankruptcy, the supplier must immediately demand adequate assurance of post-petition payment under 11 U.S.C. Section 366 so passed-through electricity bills do not pile up unpaid.
Model take-or-pay floors and host closure stress in the free Air Separation Plant Model (Excel). Continue with how an air separation unit makes money and how to finance an on-site industrial gas plant.
No. Under 11 U.S.C. Section 365, a Chapter 11 debtor may reject an executory GSA, turning a $74,208,847 termination fee into a general unsecured claim worth $18,552,212 at 25% recovery.
When the ASU is an identified asset with no substantive substitution right and the host customer controls substantially all economic benefits and directs use.
No. Accounting and bankruptcy rules are described in principle as verified in November 2026; qualified advisers determine what applies to a real contract.
This guide is drawn from The Industrial Gas Plant Finance Handbook, which follows a fictional Air Separation Unit from ambient air through take-or-pay contracts, power pass-throughs, argon netbacks, project debt vs. sale-leasebacks, host closure risk, and two-tier valuation.