Count the fabricator-hours and crew-days first, put engineering and the rented lift inside the self-performed cost, apply the markup, bill the sealant subcontractor on its own line, and count a second trip in hours and glass.
In the worked case, a storefront and entrance package costs $23,397.28 to fabricate and install, engineering and the lift included; a 32% markup and the sealant subcontract bring the price to $32,510, or $69.47 per labor hour of the job. A chipped lite and a second trip cut it to $45.03.
Worked in full in The Glass and Glazing Company Owner by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback
Free: the glass company business model in Excel, with the whole Ardmoor case: the commercial line with its labor hours, the storefront bid and its second trip, residential jobs by the installer-hour, service and door maintenance agreements, the P&L with reported and adjusted EBITDA, break-even, the cash floor and two offers for the company.
A storefront and entrance package is sold on the architect's drawings and paid for in labor hours: aluminum cut and assembled in the shop, door hardware prepped, then a crew of two on site setting frames, glass and the entrance. The estimator counts those hours first, then the materials and the outside costs, and only then applies a markup. The figures below are the worked bid of a fictional company; the markup is the company's own rule, not a market price.
| Line, worked bid (case) | Amount |
|---|---|
| Materials at cost (storefront framing, insulating glass, entrance door and hardware, sealants) | $17,850 |
| Fabricator time, 44 hours at $32.76 loaded | $1,441.44 |
| Field crew time, 4 crew-days at $624.96 loaded | $2,499.84 |
| Fuel | $136 |
| Shop drawings and the engineer's stamped calculations | $950 |
| Rented lift and glass handling equipment | $520 |
| Self-performed cost | $23,397.28 |
| Self-performed price, cost plus 32%, rounded up to the next $100 | $30,900 |
| Perimeter sealant, subcontract billed at cost plus markup | $1,610 |
| Total price | $32,510 |
The shop drawings, the stamped calculations and the rented lift are cost lines inside the self-performed cost, so the markup applies to them as it does to the glass and the hours. Whether a package needs delegated design, and what the shop drawings must show, depends on the architect's specification and the building official, asked on each job. The sealant subcontractor is billed on its own line, at its cost of $1,400 plus the company's subcontract markup. The general contractor holds back 10% of each billing as retainage, $3,251 on this package once fully billed, until the package is accepted: billed, not yet collected.
Contribution of the job = $30,900 − $23,397.28 = $7,502.72, subcontract excluded
Per labor hour of the job = $7,502.72 / 108 hours (shop plus field) = $69.47
That figure carries only the job's own loaded hours. The company's year figure, $49.29 per labor hour, carries the wages of every paid hour, booked to a job or not; the gap between the two is the cost of the hours no job pays for, not a finding about this bid.
On the second day of the set, the crew uncrates an insulating glass lite with a chipped edge. It cannot go in. The lite is reordered and the crew comes back for a second trip when it arrives. The price does not move. The job takes 5 crew-days instead of 4: the added crew-day costs $624.96 at the loaded rate, its fuel $34, and the replacement lite $1,260 at cost, $1,918.96 in all.
Contribution after the second trip = $7,502.72 − $1,918.96 = $5,583.76
Per labor hour of the job = $5,583.76 / 124 hours = $45.03
The trap: counting a broken lite in glass only. The second trip costs a crew-day and its fuel as well as the glass; leaving them out would make the overrun look $658.96 cheaper than it was.
The crew's drive from the shop to the site is paid time: under 29 CFR 785.38, travel from job site to job site during the workday counts as hours worked, and so does travel after reporting to a meeting place to pick up tools or instructions, as the crews do when they load the glass rack truck at the shop. And the open edge is planned in the estimate: under 29 CFR 1926.501, as read in November 2026, an employee at an unprotected side or edge 6 feet or more above a lower level, or at a wall opening whose outside bottom edge is 6 feet or more above the lower level and whose inside bottom edge is less than 39 inches above the working surface, must be protected by a guardrail system, a safety net system or a personal fall arrest system. The case plans window wall and storefront openings above the ground floor as wall openings; the right system for a real opening is for a safety consultant.
Rules read on the eCFR, irs.gov and sba.gov and in published summaries in November 2026; figures checked on 21 November 2026. Every price, wage, cost and multiple on this page is an illustrative assumption of a fictional company, not market data, and nothing here is legal, tax, employment, safety, insurance, engineering, building code or licensing advice.
It depends on the framing, the glass, the entrance, the hours to build and set them, the engineering and the access. In the worked case, a storefront and entrance package for a tenant space comes to $32,510, of which $1,610 for the perimeter sealant. This is a teaching assumption, not a market price.
The case uses its own rule, 32% on self-performed cost, rounded up to the next $100, with subcontracted work marked up separately. The right markup for a real company comes from its own hours, overhead and target, not from a published figure.
In the case, yes: shop drawings, stamped calculations and the rented lift are cost lines inside the self-performed cost that carries the markup. Whatever a company decides, the bid should say it once and apply it the same way on every job.
More than the glass. In the case, the replacement lite costs $1,260, and the second trip adds a crew-day of $624.96 and $34 of fuel, $1,918.96 in all, on a price that does not move.
This article is one calculation from The Glass and Glazing Company Owner, a practitioner’s guide to starting, buying, running and selling a glass and glazing company: storefront bids and labor hours, safety glazing and the codes, the shop and the field crews, shower enclosures, door service agreements, contractor packages and retainage, cash flow and valuation.
DRM-free PDF, $19.99 · Paperback, $32.99, shipped worldwide · Free Excel model