How do you estimate an electrical job?

Take off quantities, apply labor units and material prices, factor the hours, then add consumables, direct costs and markup.

An electrical estimate multiplies each item in the takeoff by a labor unit in hours and a material price, applies factors for difficulty and supervision to the hours, prices them at a burdened composite rate, adds consumables and other direct costs, and marks up the total. In the worked case, 3,404 raw hours and $210,964 of material become a $574,000 bid.

Worked in full in The Electrical Contractor Business Owner by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback

Free: the electrical estimating template in Excel, with the takeoff, the wire sheet and the change order.

Step 1: takeoff and labor units

Every item on the drawings is counted and multiplied by a labor unit: the hours it takes to install one unit under normal conditions. A sample of the fifteen lines on a fictional two-story commercial job:

Labor units from the takeoff (fictional case).
ItemQuantityHours per unitHours
3/4 in. EMT conduit with fittings and supports16,400 ft0.055902.0
4 in. square boxes with plaster rings980 each0.45441.0
2 by 4 LED troffers320 each1.1352.0
1,200 A main switchboard1 each4848.0

All fifteen lines add up to 3,404 raw labor hours and $210,964 of material.

Step 2: price the wire from copper

Building wire is mostly copper. Pricing it from its copper content keeps the estimate tied to the metal market. No. 12 THHN has 19.8 pounds of copper per thousand feet; at $4.40 a pound plus $48 of non-copper cost, it costs $135.12 per thousand feet, and the 54,000 feet on this job cost $7,296. The whole estimate holds 3,680 pounds of copper: every dollar a pound copper rises before purchase costs about $3,680.

Step 3: factors, rate and markup

Hours = 3,404 × (1 + 4% difficulty) × (1 + 8% supervision) = 3,823.4, rounded up to 3,824

Labor = 3,824 × $55.20 composite rate = $211,085

Total cost = labor $211,085 + material $210,964 + 3% consumables $6,329 + other direct costs $46,000 = $474,378

Bid = $474,378 × (1 + 21% markup), rounded up to the next $1,000 = $574,000

The trap: a 21% markup on cost is a 17.4% margin on the price, and it must cover the company's overhead before any profit. The composite rate of $55.20 is the burdened cost of a crew hour, not a wage.

The book goes further

The Electrical Contractor Business Owner covers the labor rate, estimating, copper exposure, productivity, WIP, cash and bonding, with six workbooks. DRM-free PDF, $19.99. Or try the free electrical estimating template.

Step 4: price change orders the same way

A change order estimated at 240 hours and $18,400 of material, at the same rate and markup, is quoted lump sum at $38,300. The work took 292 hours and $19,100 of material, a cost of $35,218. Signed lump sum, it would have earned $3,082; billed time and material at the subcontract rates, it earned $14,779. On uncertain work, the pricing method matters as much as the estimate.

Sources

  1. US Bureau of Labor Statistics, Electricians
  2. London Metal Exchange, copper

Figures checked on 18 November 2026. Federal rules only, illustrative, and not legal or tax advice. The people and properties in the examples are fictional.

Questions readers ask

What is a labor unit in electrical estimating?

The number of hours to install one unit of an item, such as a foot of conduit or one light fixture, under normal conditions. Contractors adjust published units to their own crews' productivity.

What markup should an electrical contractor use?

Enough to cover company overhead and a target profit. A markup on cost is not a margin: 21% on cost is about 17.4% of the price.

How do you account for copper prices in a bid?

Price the wire from its copper content at the current price, state the price the bid assumes, and buy or lock the wire early on jobs with long lead times.

Lump sum or time and material for change orders?

Lump sum is simpler for the customer but puts the risk of overruns on the contractor; time and material protects the margin when the scope is uncertain.

Read the whole book

This article is one calculation from The Electrical Contractor Business Owner, a practical guide to running an electrical contracting company: the labor rate, estimating, copper, productivity, WIP, cash and bonding.

Also on this site