Articles

How do you calculate peak funding on a development?

Peak funding is the highest point of cumulative cost plus rolled-up interest less sales receipts, and on a phased scheme it is set by when sales start, not by how much the scheme costs.

Peak funding is the highest point reached by cumulative costs plus rolled-up interest, less sales receipts, on a monthly cash flow of the scheme. On an illustrative 40-home scheme costing 23,020,000 before finance, with 6,000,000 of equity going in first and debt at 8 per cent, peak funding is 17,608,133 in month 17, 76.5 per cent of cost, and the debt is repaid by month 26. If no home sells before completion the peak rises to 24,000,127.

Worked in full in The Real Estate Development Manager by Julian R. Sterling, with every figure reproduced in a free workbook.Get the DRM-free PDF, $19.99 →or see it on Amazon

What does peak funding mean?

Peak funding, or the peak funding requirement, is the largest amount of money a property development needs outstanding at any one time: the highest point reached by cumulative costs and rolled-up interest, net of sales receipts, on a monthly cash flow. It sets the size of the facility and the equity, and is usually lower than total cost when sales start before the build ends. Peak equity is the equity part of that peak; peak debt is the loan part.

The worked 40-home scheme, from the monthly cash flow below.
MeasureMeaningWorked scheme
Total cost before financeLand, fees and build23,020,000
Peak equityMost equity in at one time (spent first, exhausted in month 8)6,000,000
Peak debtHighest loan balance, month 1711,608,133
Peak fundingEquity + debt at the peak17,608,133
Peak funding with no sales before completionSame scheme sold as one block24,000,127

Why the summary appraisal cannot give you the peak

A summary appraisal states total cost and a finance line, and implicitly treats the whole cost as outstanding at once. A lender, a funding partner and the developer's own treasury need something else: the most money the scheme will ever need at one time, when it is reached, and how long it is held. Those three numbers decide the facility limit, the equity commitment and how exposed the scheme is to a delay. They only come out of a cash flow laid out month by month.

The assumptions

Illustrative 40-home phased scheme
InputValue
Land, paid at month 05,000,000
Acquisition costs (6.8%)340,000
Pre-construction fees, months 1 to 6400,000
Build cost, months 7 to 24 on an S-curve16,000,000
Professional fees during the build (8%)1,280,000
Total cost before finance23,020,000
Homes; price each; sales costs40; 750,000; 2%
First completions and sales; pacemonth 18; 3 a month
Equity, spent first6,000,000
Debt rate, interest rolled up monthly8%

The S-curve puts 0.76 per cent of the build into the first and last months and 8.68 per cent into the busiest. Sales receipts go straight to repaying the debt until it is cleared.

The calculation, step by step

1. Lay out costs by month: 5,340,000 at month 0, the fees over months 1 to 6, build plus fees on the S-curve over months 7 to 24.

2. Spend equity first: the 6,000,000 runs out in month 8, the second month of the build.

3. Each month thereafter: debt balance = opening balance × (1 + 8% / 12) + that month's cost − that month's net sales receipts.

4. Funding outstanding = equity spent + debt balance. Sales of 3 homes from month 18 bring in 2,205,000 a month net, more than the build is spending by then, so the balance turns down.

5. The maximum of the funding row is 17,608,133 at month 17: 6,000,000 of equity and 11,608,133 of debt.

Excel: =MAX(FundingRow) for the peak and =MATCH(MAX(FundingRow),FundingRow,0)-1 for its month.

The peak sits one month before the first sale, not at practical completion, because on a phased scheme the receipts start while the build is still running. Funding stays within 80 per cent of the peak for 6 months; the debt is clear by month 26, the last home sells in month 31, and total interest is 683,414.

What moves the peak, and what only moves the time

Same scheme, one change at a time
CasePeak fundingMonthChangeDebt repaidInterest
Base17,608,13317026683,414
Sales 2 a month17,608,13317030928,839
First sale month 2222,499,28321+4,891,150301,174,724
No sales until completion, then 4 a month24,000,12724+6,391,994311,420,917
Build cost +10%18,796,54817+1,188,41626808,810
Half the land deferred to month 1217,570,57917−37,55426643,546
Debt rate 10%17,677,64817+69,51526865,619

The table separates two kinds of risk. The date of the first sale sets the peak: four months' slippage adds 4,891,150, more than four times what a 10 per cent build overrun adds. The sales pace, once sales have started, does not touch the peak at all; it lengthens the time the money is out and adds 245,425 of interest. A deferred land payment barely helps here, because it falls due before the peak and is funded anyway.

The flats case is the useful benchmark. Where nothing can be sold until the whole building is complete, peak funding exceeds the cost before finance, because the interest rolled up during the build has to be funded too. Phasing is worth 6,391,994 of peak funding on this scheme.

The common mistakes

Takeaway

A quarterly cash flow with the peak funding requirement, how long it is held and what a delay costs is in the free workbooks for this case; the finance cost on the same kind of monthly cash flow is worked in how to calculate interest on a development loan.

Questions readers ask

What is peak funding in property development?

The maximum cash a scheme needs at one time, found as the highest balance of cumulative costs plus interest less sales on a monthly cash flow. On the worked scheme it is 17,608,133 in month 17, against 23,020,000 of total cost, because home sales start before the build finishes.

What is peak equity in real estate?

The highest amount of equity a development or investment requires at any point. When equity goes in first, as here, peak equity is the full equity commitment, 6,000,000, reached once it is spent in month 8; the debt then carries the scheme to its peak.

What is the difference between peak funding and peak debt?

Peak funding is all the money in the scheme at its high point, equity plus debt including rolled-up interest; peak debt is the lender's share. With 6,000,000 of equity going in first, the illustrative scheme's peak funding of 17,608,133 is 11,608,133 of debt, which is the figure the facility limit has to cover.

Does a slower sales rate increase peak funding?

Often not, because the peak is reached before the first sale. In the illustrative case cutting sales from 3 to 2 homes a month leaves the 17,608,133 peak unchanged but keeps debt outstanding until month 30 instead of 26 and adds 245,425 of interest. Delaying the first sale by four months instead adds 4,891,150 to the peak.

Why is peak funding higher than total development cost?

Because rolled-up interest is funded too. If nothing is sold before completion, the illustrative scheme needs 24,000,127 at its peak against 23,020,000 of cost before finance, the difference being interest accrued on the debt during the build.

Run the numbers yourself: the free residual land valuation template works a development appraisal back to land value in Excel. For a monthly model over 60 months with S-curves, senior and mezzanine loans and a JV waterfall, see the Real Estate Acquisition and Development Model, Pro Edition ($99).

Read the whole case

This article is one calculation from The Real Estate Development Manager. The book takes the same case from first principles to the decision, chapter by chapter, and every figure it prints is a live formula in the free companion workbooks.

Get the book on Amazon →Free companion files

Also on Amazon UK · Amazon Germany · Amazon France · Amazon Canada

Prefer a PDF? The same book is sold as a DRM-free PDF edition, searchable and printable. Get the PDF edition, $19.99

Not on Amazon: 19 paperbacks by Julian R. Sterling on markets, funds and compliance, printed on demand and shipped worldwide. Browse the bookshop →

Also on this site

Reading guide: real estate investing, finance and fund management → · All 3450 articles →

If this book helped, or didn’t, a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.