Companion files
Land, Consent, Cost, Programme and the Delivery of a Scheme
These are the companion files of The Real Estate Development Manager by Julian R. Sterling.The book on Amazon →
Five Excel workbooks. The first is the residual appraisal and the four tests that turn it into a decision document. The second is the worked scheme of Chapter 16, from first site visit to disposal, built to show where the return was actually decided. The third and fourth are the working documents: land diligence in five stages, the cost plan interrogation, the risk register, change control and handover. The fifth writes down the comparison Chapter 14 asks for and does not perform. Three of them are now corrected. Around them: a blank set for your own scheme, thirteen working documents to print, forty questions that mark themselves, and three cases the book names and never takes to a number. All free.
Free to download. No sign-up, no email address, nothing to fill in.
Five workbooks, the blank set, the three cases, the question book, the printable documents and the read-me. Each group below can also be downloaded on its own. Last revised 23 September 2026.
Reading the paperback or the Kindle edition? The same book is also sold as a DRM-free PDF: searchable, printable, yours on any device. $19.99, instant download.Buy the PDF edition → Free sample
Finished the book? Two or more PDF editions bought together are 15% off. Browse the PDF editions →
The working models behind the books, built out for live deals: the Pro models →
Learn to model a commercial property, from rent roll to waterfall: the Real Estate Modeling course →
Optional. When a workbook on this page is corrected or a new worked case goes up, readers on the list get one email, plus a short note when a new book comes out. The downloads do not need it.
Join the reader listRun by MailerLite, off this site. How your address is used.
These carry the book’s own figures. Three were corrected on 23 September 2026; what changed is at the end of the read-me inside. Download these five99 KB
Chapter 3
A scheme with a value of 100 and costs of 80 supports a land price of 20. Move each by five per cent and the land value becomes 11 — two five per cent movements, a forty-five per cent fall. That is why development is a high-beta activity and why competitive land bidding tends to be won by whoever is most optimistic. The four tests of the chapter run live: an 8 per cent cost movement takes the land value from 6.4 to 0.4, because the required profit rises with the cost; a nine-month delay takes it to 2.2, a five per cent value fall to 1.4, and all three together to −8.8. Two further sheets do the work that matters in practice. One asks what the assumptions would have to be for the price on the table to work, and produces the cost overrun and the value decline that would each eliminate the profit — the two numbers the book says belong on the front page. The other is a quarterly cash flow: peak funding requirement, how long it is held, and what a delay costs. On the illustrative scheme the cash flow’s interest is 8.0 against the summary appraisal’s finance line of 4, about a quarter of the profit, and nothing on the summary would have shown it. Corrected: test 4 now applies all three stresses (the first version left out the 8 per cent rise), the profit is recomputed on each test’s costs as the corrected chapter does, and the cash flow now carries the summary’s 12 of fees and statutory costs instead of 7.5.
Download the workbook18 KBChapter 16
At month five the appraisal gives a residual of 3.6 against a conditional contract price of 7.6. The scheme does not work. The team interrogates the inputs rather than abandoning it, the residual moves to 5.9, and a difficult conversation backed by a ground investigation and a daylight assessment moves the price to 6.4. Everything after that was execution — and the workbook proves it: had the developer completed at 7.6, the realised profit would have been 2.4 on a cost of 27.7, about 8.7 per cent for four years of risk. The timeline records every movement in the cost, and the contingency arithmetic beneath it is the whole argument for change control: two draws against 0.8 held leaves 0.30, and had the enlarged entrance at month 24 been approved at 0.28 there would have been 0.02 left when inflation arrived at month 33 — enough to cover it, by 0.02, so the test would have passed, not failed as the first version said. The programme risk that mattered was not construction. One month was lost on site; three were lost to the discharge of conditions nobody had programmed. Added: the profit bridge now matches the movements in value and cost (the lost unit alone is worth 0.66, more than twice the value shortfall), the chapter’s total cost of 26.1 is shown not to rebuild from its own lines (26.7), and the outturn is 18 per cent on the basis of the 20 per cent target, 14 only on total cost.
Download the workbook23 KBAppendices A and B
The 28-point land appraisal checklist in its five stages, with a column for the cost incurred so that the sequence stays honest: desktop work measured in days, then the single obvious problem every site has, then intrusive and specialist work only once stage one clears. Doing them in that order is what makes cheap diligence the highest-return spend on a scheme. Then the six questions to ask of every cost plan, every time — what design information it is based on, what is excluded, what allowances are included, what inflation and to what date, what contingency and whose, and what the abnormals are based on. Plus the four numbers to report monthly and the three rules of contingency discipline.
Download the workbook15 KBAppendices C, D, E and F
The risk register with its five fields, including the trigger — the observable event that says this is materialising, which is the field nobody fills in and the one that turns a register from a document into a management tool. The eleven risks that recur, to be reviewed monthly at the same meeting as the cost report and the programme, because they are the same subject seen three ways. The six-step change control protocol with the category table and the claims discipline. The completion and handover checklist, built on the principle that the handover package is not something you receive but something you check. And ten interview questions with what a good answer contains, useful from either side of the table.
Download the workbook19 KBAppendix H · Chapter 14
Chapter 14 says the judgement is a probability-weighted comparison and then, in three words: “Write that comparison down.” It never does. This writes it down, on the chapter’s own scheme — four floors, an occupier wanting two of them at eight per cent below market on a fifteen-year term, conditional on a dedicated entrance.
The rent concession costs 1.91 times its own NPV. A developer prices it as 16,000 a year for fifteen years — 145,727 discounted. A buyer capitalises it in perpetuity, so at exit it is 278,261. The rule worth carrying out of this file: divide rent foregone by your exit yield, not by your discount rate.
The void of the whole building costs 682,000, two and a half times the concession. But the occupier takes two floors of four, and what a two-floor pre-let removes is the holding cost, rent-free and fees on those two: 206,000 over a twelve-month void. The interest runs until the other two let. And the largest line in it is not the interest everyone watches; it is the rent-free incentive a completed empty building needs, which speculative appraisals routinely omit because it feels like rent arriving later rather than a cost.
Then the comparison itself, corrected. The first version’s “certain” pre-let let the other two floors on completion day, and charged the speculative void interest on 60 per cent of the loan. With the same four outcomes applied to both, the pre-let earns 316,422 to 1,092,661 and speculation -801,333 to 831,667. The pre-let wins in every outcome, by at least 260,994, so no probability makes speculating right. The room to concede is smaller than the first version said: it keeps winning in every outcome up to a 15.3 per cent discount and beats the expected case up to 21.5 (not 21 and 31). The occupier asked for eight.
And the concession nobody priced. The dedicated entrance takes three per cent of the building and is worth the same as a six per cent rent discount — permanently, where the rent discount runs fifteen years. The occupier asked for eight on rent and six in configuration, and the negotiation was about the eight, because the eight had a number attached. Eight plus six is fourteen: a point and a bit inside the level at which the pre-let stops winning in every outcome. Twenty-one checks.
Download the workbook26 KBTwo workbooks with every input emptied. The checks sheets count what is still missing and test what holds for any inputs.
Chapters 3 and 14 · Appendix H
The residual appraisal with your value, costs and required profit, the four tests with your own delay, the reverse question for the price on the table, and a quarterly cash flow that is checked against the summary: it says so when the two stop carrying the same costs. And the pre-letting decision for your own offer: the concession priced three ways, the void, your own four outcomes for the floors not pre-let, the discount at which the pre-let stops winning, and any condition priced as a rent discount.
The book’s figures are listed in a text file inside the archive. Typed back in, they return 6.4, 0.4, 2.2, 1.4 and −8.8, and a pre-let that wins in every outcome up to 15.3 per cent.
Download the blank set42 KBThirteen pages to print and use. A4, with margins wide enough for US Letter.
Chapters 2 to 15 · Appendices A to E and H
The first pass and the walk-away number. Land diligence in five stages, with the cost of each item. The residual on one page with the four tests and the two numbers for the front page. Consent as four risks, with satisfactory consent defined and every approval mapped. The brief and where cost concentrates. The cost plan’s six questions and the monthly four numbers. Procurement and the terms that matter. The facility and the cost-to-complete test. The programme review and the site walk. The risk register with its trigger. The change control register. The pre-let paper. And completion, handover and stabilisation, to the facility’s maturity.
Download the documents36 KBA workbook that marks itself. Answer in the yellow cells; the marking fills in as you go.
All parts of the book
Seven on the role, land and the residual, seven on consent, design, cost and procurement, seven on funding, programme, the team and change, six on risk, performance, pre-letting and completion, seven on Chapter 16 and Appendix H, and six on the three cases below. Numbers are marked to a tolerance, multiple choice to the letter, and the score sheet counts your errors part by part: that is your revision list.
Nothing is hidden. The marking sheet holds every answer, every tolerance, and the reason for each answer.
Download the question book16 KBNew material, not a restatement. Three situations the chapters name and never take to a number. Each case is one workbook: the note is the first sheet, the model is the rest, and a checks sheet closes it. Type your own figures in and every finding recomputes.
Chapter 4 · Case one
Chapter 4 says to quantify the consentable scheme against the optimal one and that “the comparison is rarely close”. On Chapter 16’s scheme the four units are 0.87 of margin, a quarter of the profit; an appeal after a refusal at month 13 outruns the 24-month option by 7 months. Route B wins only once the refusal risk passes 34.3 per cent: close enough that it has to be written down.
Chapters 7 and 9 · Case two
Chapter 16’s contract of 15.6 and facility of 16.5. A week of delay costs the developer 0.0454 if the client caused it, 0.0238 if it was neutral and 0.0038 if the contractor did and pays damages: the same month costs twelve times more when the client causes it. The damages cap covers 39 weeks; beyond it delay is free to the contractor.
Chapter 15 · Case three
Chapter 15’s stabilisation on Appendix H’s building: half pre-let, a floor let at month seven with nine months rent-free, the last floor empty when the facility matures. The balance is 4,116,640; on contracted income net of incentives the lender advances 3,044,167. The developer must find 1,072,473, and the rent actually being paid covers the new loan’s interest 1.01 times. Fully let, as the appraisal assumed, there is no gap.
Download the three cases33 KB| Blue text | a hardcoded input — you may edit these |
| Black text | a formula — do not overtype these |
| Green text | a link to another sheet |
| Amber fill | an input in the blank set and the cases, all emptied or marked |
| ADDED | a figure the book does not give, used in the cases and marked wherever it appears |
| Yellow fill | the assumptions that carry the answer |
Fifty lines are checked across the three computing workbooks (fourteen in the residual appraisal, fifteen in the worked scheme, twenty-one in the pre-letting decision), and twelve internal checks were added on 23 September 2026; all pass. Each line carries its own tolerance, set to the precision the book actually prints. Every other workbook ends with its own checks sheet.
Two readings had to be taken out of the arithmetic rather than from the text, and both are stated on the sheet where they matter. Chapter 3 recomputes the required profit at 20 per cent of each test’s own costs, which gives 0.4 and 2.2 (test 4, which the chapter calls only “negative”, is −8.8); the first edition held it at 15.6 and printed 1.4 and 2.9, and a note on the sheet keeps that reading. Chapter 16 states a revised residual of 5.9 without itemising the revised cost; solving backwards gives a cost excluding land of 20.4. In each case the input that carries the reading is blue, and the note beside it says what the other reading would produce.
The Real Estate Development Manager develops the complete framework behind these models, with the assumptions, trade-offs and worked examples tied together.
View the book on Amazon Read the related analysisAlso as an ebook on Apple Books · Google Play.
The workbooks open in Microsoft Excel, LibreOffice Calc, Google Sheets and Numbers; the PDF prints on A4 or US Letter. They use no macros and no add-ins, so nothing needs to be enabled or trusted. If your spreadsheet asks to update links on opening, decline — there are none.
The Real Estate Development Manager by Julian R. Sterling. The workbooks reproduce the worked examples in the chapters; the book is where the reasoning behind them is set out.
| 23 Sep 2026 | Three workbooks corrected. The residual appraisal: test 4 left out the 8 per cent cost rise (-7.1, not −2.1), and the cash flow carried 7.5 of fees and statutory costs against 12, so its interest is 8.0, not 7.3. The worked scheme: had the entrance been approved, the cost-to-complete test would have passed by 0.02, not failed; the profit bridge now matches the movements. The pre-letting decision: a two-floor pre-let removes 206,000 of the 682,000 void, and the “certain” pre-let let the other floors on completion day; corrected, it still wins in every outcome, up to a 15.3 per cent discount rather than 21. Added: a blank set, thirteen working documents, forty questions that mark themselves and three new cases. Each workbook can now also be downloaded on its own. |
| 8 Nov 2026 | The residual appraisal realigned on the corrected Chapter 3: the required profit is recomputed at 20 per cent of each test’s own costs, so an 8 per cent cost rise takes the land value to 0.4 (a 94 per cent fall), a nine-month delay to 2.2, and all three stresses to −8.8. |
More in real estate, with free companion files. The full list of titles is on the author page.
Also available as a standalone free template: residual land valuation.
If this book helped — or didn’t — a few lines on Amazon are worth more than they look: they are what the next reader goes on. Write a review. The workbook stays free either way.