Measure the cut in bank cubic yards, convert the fill through the shrinkage, multiply the export by the swell, then divide by the loose yards per load and the loads a truck makes in a day.
Bank cubic yards are length times width times depth in feet, divided by 27. With the case's swell of 25%, one bank yard becomes 1.25 loose yards in the truck. A pad that exports 1,244 bank yards fills 86 loads of 18 loose yards, 10.8 truck-days.
Worked in full in The Excavation Contractor Business Owner by Julian R. Sterling.Get the DRM-free PDF, $19.99 →or the paperback
Free: the excavation company model in Excel, with the Corbeck case: four job types with quantities, prices and costs, dirt and truck math, contribution per crew-day, crews and overhead, the P&L with equipment payments, break-even and stress tests, equipment cost per hour and two offers for the company.
A cubic yard of dirt in the ground (a bank cubic yard, BCY) grows when it is dug and loaded (loose cubic yards, LCY) and shrinks when it is compacted in a fill (compacted cubic yards, CCY). The book’s case assumes a swell of 25% and a shrinkage of 10% for its common earth; real factors come from the soils report and the compaction tests.
Bank cubic yards = length × width × average depth (feet) ÷ 27
Loose cubic yards = bank yards × (1 + swell) = 1 BCY × 1.25
Compacted cubic yards = bank yards × (1 − shrinkage) = 1 BCY × 0.90
Truck loads = loose yards ÷ loose yards per load (18 in the case)
A retail pad of 240 by 180 feet (43,200 square feet) has an average cut of 3.0 feet; the parking area needs 3,200 compacted cubic yards of fill.
| Step | Calculation | Result |
|---|---|---|
| Cut | 129,600 cubic feet ÷ 27 | 4,800 BCY |
| Bank yards to make the fill | 3,200 CCY ÷ 0.90 | 3,556 BCY |
| Export | 4,800 − 3,556 | 1,244 BCY |
| In the trucks | 1,244 BCY × 1.25 | 1,556 LCY |
| Loads | 1,556 ÷ 18 | 86 |
| Truck-days | 86 ÷ 8 loads a day | 10.8 |
The trap: dividing bank yards by the truck’s capacity. Forgetting the swell would have priced a fifth fewer loads than the job needs.
A truck’s day is a loop. In the case, the dump site is 12 miles away at about 25 miles an hour: 29 minutes each way, 8 minutes to load, 6 to dump and 3 waiting, a 75-minute cycle and 8 loads in a ten-hour day.
| Typical site package export | Amount |
|---|---|
| Bank yards exported | 1,600 |
| Loose yards | 2,000 |
| Loads | 111 |
| Hired truck-days at $1,050 | 13.9 |
| Trucks and dump fees | $19,028 |
| Cost per bank yard | $11.89 |
| Unit price billed per bank yard | $19.00 |
Every extra mile of haul lengthens the cycle, cuts the loads per truck-day and raises the cost per yard. On a long haul, the answer is more trucks, not a bigger excavator.
At 9 feet deep, a trench 4 feet wide inside a trench box moves 1.33 bank yards per foot; sloped one to one, the steepest slope allowed in soil a competent person has classified as Type B, it is 22 feet wide at the top and moves 4.33, 3.2 times as much. OSHA’s Appendix B to the excavation standard sets the maximum slopes by soil type for excavations under 20 feet deep, once a competent person has classified the soil; without that classification, a sloped excavation must be no steeper than one and one-half to one.
Figures checked on 20 November 2026. Illustrative case assumptions, not market data, and not legal, tax, employment, insurance or safety advice. The company in the examples is fictional.
Multiply length, width and average depth in feet, then divide by 27 cubic feet per cubic yard. That gives bank cubic yards, the dirt as it sits in the ground; convert to loose yards for trucks and to compacted yards for fill.
It depends on the truck and the material. The book's case uses 18 loose cubic yards for a tri-axle, which is about 14.4 bank yards of its soil after the swell; check your own trucks and the dump site's tickets.
Swell is the growth from bank to loose volume when soil is dug. It varies with the soil; the case assumes 25% for common earth. Use the soils report or measured loads on your own jobs.
Divide the working day by the round-trip cycle: wait, load, haul, dump and return. In the case, a 75-minute cycle gives 8 loads in a ten-hour day.
This article is one calculation from The Excavation Contractor Business Owner, a practitioner’s guide to starting, buying, running and selling an excavation and site work company: dirt math and takeoffs, unit prices and bids, trucks and export, utilities and trench safety, crews and equipment cost per hour, builders and developers, cash flow and valuation.