The right level of leakage is not zero. It is the point where the next cubic metre saved costs more than the water is worth.
Four leakage measures cost between $0.201 and $1.133 a m3 saved. Where a saved m3 is worth only its $0.28 production cost, just 1 measure pays and the utility should fix 1.2 million m3; where it defers a $0.62 source, 3 measures pay and 3.0 million m3 should go; where the water can be sold at $1.33 net, all 3.6 million m3 pay.
| Item | Value |
|---|---|
| System input | 60.0 million m3 a year, of which 22% is physical leakage: 13.2 million m3 |
| Tariff | $1.40 a m3, 95% collected, $1.33 net |
| Variable production cost | $0.28 a m3 (energy and chemicals) |
| Cost of new supply | $0.62 a m3 over the long run, if the leakage saved defers a new source |
| Capital | 7.0% over 20 years, a capital recovery factor of 0.0944 |
Capital recovery factor = 0.07 ÷ (1 − 1.07−20) = 0.0944. Four measures can each be bought, each one cheaper per m3 than the one after it:
| Measure | Saved, m m³ | Capex, $m | Opex, $m a year | Annual cost, $m | Cost per m³ saved |
|---|---|---|---|---|---|
| Pressure management | 1.2 | 1.5 | 0.10 | 0.242 | $0.201 |
| Active leak detection | 1.0 | 1.4 | 0.30 | 0.432 | $0.432 |
| Mains repairs | 0.8 | 2.8 | 0.10 | 0.364 | $0.455 |
| Mains replacement | 0.6 | 7.2 | 0.00 | 0.680 | $1.133 |
Annual cost = capex × 0.0944 + opex; cost per m3 = annual cost ÷ volume saved
Pressure management: (1.5 × 0.0944 + 0.10) ÷ 1.2 = 0.242 ÷ 1.2 = $0.201
Mains replacement: 7.2 × 0.0944 ÷ 0.6 = 0.680 ÷ 0.6 = $1.133
Excel, capex in C6, opex in D6, volume in B6: =(C6*0.07/(1-1.07^-20)+D6)/B6
The measures rise in cost from $0.201 to $1.133 a m3, a factor of 5.6. That rising cost is why the right amount of leakage is not zero.
A saved cubic metre is worth the cost the utility avoids, and that depends on the system. If supply is ample it saves only production cost; if it defers a new source it saves that source’s cost; if the system is short it frees water to sell.
Value of a saved m3 = $0.28 (production cost), $0.62 (deferred supply) or $1.33 (tariff 1.40 × 95%)
Measure pays if its cost per m3 is below that value. At $0.28 only pressure management qualifies
| Value of a m³ | Measures that pay | Volume saved, m m³ | Capex, $m | Net annual value, $m |
|---|---|---|---|---|
| $0.28 (production cost only) | 1 of 4 | 1.2 | 1.5 | 0.094 |
| $0.62 (deferred new supply) | 3 of 4 | 3.0 | 5.7 | 0.822 |
| $1.33 (water sold in a short system) | 4 of 4 | 3.6 | 12.9 | 3.070 |
At $0.28 the utility should fix 1.2 million m3, 9.1% of the 13.2 million m3 of physical leakage, for a net gain of $0.094m a year. At $0.62 it should fix 3.0 million m3, 22.7% of leakage, for $0.822m. At $1.33 it should fix all 3.6 million m3, 27.3% of leakage, for $3.070m.
| Case | Measures that pay | Volume saved, m m³ | Net annual value, $m |
|---|---|---|---|
| Costs 20% lower, production cost only | 1 of 4 | 1.2 | 0.143 |
| Costs 20% lower, deferred new supply | 3 of 4 | 3.0 | 1.030 |
| Costs 20% lower, water sold in a short system | 4 of 4 | 3.6 | 3.414 |
| Base costs, production cost only | 1 of 4 | 1.2 | 0.094 |
| Base costs, deferred new supply | 3 of 4 | 3.0 | 0.822 |
| Base costs, water sold in a short system | 4 of 4 | 3.6 | 3.070 |
| Costs 20% higher, production cost only | 1 of 4 | 1.2 | 0.046 |
| Costs 20% higher, deferred new supply | 3 of 4 | 3.0 | 0.614 |
| Costs 20% higher, water sold in a short system | 3 of 4 | 3.0 | 2.744 |
The cut-off is set by the value of the water, not by the cost of the measures: a 20% cost swing moves the answer by one measure at most. The model has no leakage rebound, no loss of savings over time and no interest during construction.
The level at which the next measure costs more per m3 saved than the water is worth. Here it is 1.2, 3.0 or 3.6 million m3 of the 13.2 million that leaks, depending on the value of water.
Because a saved m3 only earns the tariff if there is demand the system could not otherwise meet. With ample supply it saves $0.28 of production cost, a quarter of the $1.33 net tariff.
No. The last measure costs $1.133 a m3, 5.6 times the first, and pays only if water is worth more than that.
The free companion files for The Water Infrastructure Investor rebuild a fictional regulated water utility bought at 1.60x rate base and a 150,000 m3 a day desalination plant bid as a build-operate-transfer project, with the capacity charge, sculpted debt and take-or-pay. The figures in this article use invented inputs and are not in them. No account and no email address.
Not on Amazon: 24 paperbacks by Julian R. Sterling on insurance and retirement, printed on demand and shipped worldwide. Browse the bookshop →
Reading guide: infrastructure, data centres and energy → · All 1908 articles →