The long-term service agreement decides when a gas plant's turbines come offline, what the owner pays every month, and what the owner still pays in an outage year. It is one of the first documents a buyer should read.

Worked in full in The Gas-Fired Power Plant Handbook by Julian R. Sterling, with every figure reproduced in Excel workbooks.Get the DRM-free PDF, $19.99 →

What an LTSA is

A long-term service agreement, or LTSA, is the contract under which a turbine manufacturer or an independent provider maintains a plant's gas turbines for many years. Gas turbines must be inspected and rebuilt on a schedule set by how many hours they run and how many times they start, and the parts and skills involved are specialized. The LTSA turns that schedule into a predictable stream of payments and moves part of the maintenance risk to the provider. For a buyer of a gas plant, it is one of the three or four documents that most affect value.

How the fees work

Most agreements combine three kinds of payment:

Fees escalate with an index, usually a blend of labor and materials. In the fictional plant of The Gas-Fired Power Plant Handbook, the LTSA fixed fee is $4.00 million a year and the variable fees sit inside variable O&M of $3.00 per MWh, so they rise and fall with generation.

Hours, starts, and the counters that drive the schedule

An LTSA defines how operating hours and starts are counted, including factors that make a trip or a fast start count as more than one start, or high-load operation count as more than one hour. Those factors decide when the plant reaches its next combustion, hot gas path, or major inspection. A plant that shifts from steady baseload to daily cycling, as many combined cycles have, can reach its inspections years earlier than its original plan, and pay more along the way. That is why diligence starts from the turbine counters, not from the calendar.

What the LTSA does not cover

The scope usually covers gas turbine parts and services, sometimes generators, rarely the steam turbine, and almost never the heat recovery steam generators or the balance of plant. The owner pays for everything else. In the case, the plant has major outages in years 3 and 6 (2029 and 2032); in each, availability falls from 92 percent to 88 percent and the owner funds $18.0 million of work outside the agreement's scope. Cash flow before debt service drops from $67.05 million in year 2 to $46.35 million in year 3, and the debt service coverage ratio from 2.65x to 1.98x, the lowest of the hold.

Guarantees and damages

Many agreements guarantee availability, output, or heat rate after an inspection, with liquidated damages if the guarantee is missed. Read three things: how the guaranteed metric is measured, what is excluded (owner-caused outages, fuel quality, grid events), and the cap on damages, which is usually far below the margin a plant loses when it is offline in high-priced hours. A guarantee is a partial refund, not insurance against lost revenue.

OEM or third party

The original manufacturer brings original parts, engineering data, upgrade packages, and a balance sheet behind its guarantees, which lenders often prefer. Independent providers can be cheaper, more flexible on refurbishment, and willing to tailor the scope. Near the end of an OEM agreement the manufacturer has strong negotiating leverage, so a buyer should know the expiry date, the alternatives, and the likely cost of renewal before bidding.

What to check in diligence

  1. Where each turbine stands in its inspection cycle, in counted hours and starts, against the plan in the model.
  2. The fee formula, the escalation index, and the balance of any prepaid or accrued accounts.
  3. Scope exclusions and the owner-funded work they imply in outage years.
  4. Guarantees, exclusions, and damage caps.
  5. Termination fees, end-of-term obligations, and whether the agreement survives a change of control with or without consent.

Maintenance timing changes cash flow, coverage, and the price a buyer pays, as how to value a gas-fired power plant explains. To see how a major outage year moves the numbers, change the inspection years in the free Gas Plant Spark Spread Model (Excel), and see the spark spread explained for the margin side of the same plant.

Read the full handbook

This guide is drawn from The Gas-Fired Power Plant Handbook, following Harlan Ridge Energy Center (720 MW combined cycle) from its first income statement through heat rate, gas supply, dispatch, capacity revenue, a toll offer, two major outages, diligence, valuation, a term loan B, stress tests, and exit.

Paperback, $32.99 PDF edition, $19.99 Book page and companion workbooks

Free download: Gas Plant Spark Spread Model (Excel).

Questions practitioners ask

What does a gas turbine LTSA cover?

Scheduled maintenance of the gas turbines, including parts and services for combustion, hot gas path, and major inspections, sometimes the generators. The steam turbine, heat recovery steam generators, and balance of plant are usually outside its scope.

How are LTSA fees calculated?

Usually a fixed monthly fee plus variable fees per equivalent operating hour or factored start, escalated by an index, sometimes with milestone payments at major inspections.

Do LTSA guarantees cover lost revenue?

Rarely in full. Availability, output, and heat rate guarantees pay capped liquidated damages that are usually well below the margin a plant loses during an outage.